Bristol City Council
Cabinet, Tuesday 2 April 2019 at 4.00pm

Avonmouth Severnside Enterprise Area Infrastructure Phase 2

Approved Executive 6 papers

Cabinet approved this item on Tuesday 2 April 2019. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Cabinet approved the Council’s involvement in the scheme for the design, construction and maintenance of flood defences and ecology mitigation works within the Avonmouth Severnside Enterprise Area (ASEA) detailed in Appendix A. 2. Cabinet approved the Council’s contribution of up to a maximum of £31.95m for the scheme to be funded initially through borrowing but which will be reimbursed from the West of England Economic Development Fund (EDF) as detailed in the report. 3. Cabinet agreed the Council’s capital programme be amended to incorporate the budget profile as set out in Table 1 to Appendix G of this report and associated funding sources as detailed in this report. 4. Cabinet agreed to reprofile £20m of the EDF to the scheme as referred to in Appendix A paragraph 35c and Appendix G). 5. Cabinet noted that it is intended that £36.6 m grant funding, in total, for the flood defence design build scheme will also be provided by DEFRA (administered by the Environment Agency )- £4m via the Wessex Regional Flood and Coastal Committee (confirmed) and £32.6m via Flood Defence Grant in Aid (business case approved but no allocation yet made – see Appendix A paragraphs 24-28 and Appendix G). 6. Cabinet delegated authority to the Strategic Director for Growth and Regeneration, in consultation with the Cabinet Member for Finance, Governance and Procurement , and the Director of Finance: a) to agree the completion of the Inter-Authority Legal Agreement between the Council, Environment Agency, and South Gloucestershire Council, and b) to take programme and financial decisions within the budget envelope and scheme of delegation as the project develops. 7. Cabinet approved the process for the award of the contract for the scheme, which has been procured via the Environment Agency’s Water and Environmental Management Framework (Lot 4), on the basis of the Contract Award Report . 8. Cabinet acknowledged both the economic benefits and the financial and contractual risks associated with the implementation of the scheme, (as detailed in the report) and therefore, requires Officers to utilise the project governance arrangements to identify opportunities to re-programme the scheme as necessary to ensure (so far as practicable) the scheme can be completed within the budget envelope. It is noted that further Cabinet approval will be required to agree any scheme re-programming which has a financial impact on the Council.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Appendix I

Full Business Case

Scheme: ASEA Infrastructure Phase 2 Flood Defence and Ecology Mitigation

Originated Reviewed Authorised Date

1 Version 1.0 GW BS 11/01/2018

2 Version 2.0 Jacobs ASEA Delivery Board IS 30/7/2018

Doc v21 Last updated Nov 2017 Executive Summary

The project comprises delivery of significant flood defence and ecological assets designed to unlock and safeguard development at Avonmouth-Severnside Enterprise Area (ASEA), located between the Bristol Channel and the City of Bristol and spanning South Gloucestershire (SGC) and Bristol City Council (BCC). The flood defence element of the project will primarily enhance and upgrade existing flood defence infrastructure along a 17km stretch. The infrastructure will provide flood risk management to a 1 in 200-year (0.5% Annual Exceedance Probability [AEP]) Standard of Protection (SOP), based on hybrid 2076 and 2098 design levels (i.e. taking into account climate change, coastal change and sea level rise). The 2098 design level will be provided south of Binn Wall to maximise protection of existing and future development in ASEA. The 2076 design level will be delivered north of Binn Wall, where flood risk to ASEA is lower. The ecological mitigation element of the project comprises the provision of at least 85 ha of wetland habitat creation, in line with the recommendations of the Cresswell Study1.

The project rationale is underpinned by local and sub-regional economic development and planning aspirations to unlock the full economic potential of ASEA. Flood defence investment is required to ensure that future development at ASEA benefits from the Environment Agency’s (EA) recommended SoP for new developments, i.e. 1 in 200 years (0.5% AEP). The ecological mitigation is required to ensure that the statutory environmental impacts of ASEA development are managed to satisfy the requirements of the Cresswell Study. By satisfying the EA and Cresswell Study regulations, full development at ASEA is more likely to be acceptable in planning terms thus bringing forward desirable economic growth for the region.

The rationale for public sector investment in the project is predicated on the presence of market failure at ASEA as well as the proposed flood defence infrastructure and ecological assets acting in the general public interest. From a market failure perspective, the presence of the 1957/58 planning consent creates imperfect competition conditions at ASEA. The planning consent allows development in the 1957/58 planning envelope to proceed based on legacy planning consents, without requirement for appropriate investment in strategic flood or ecological mitigation. As such, the financial burden of delivering these assets would be passed onto development plots lying outside the 1957/58 planning envelope or public authorities holding statutory responsibility for the measures, impacting on the financial viability of such sites and therefore the ability to bring forward the development. These conditions confer competitive advantage on sites within the 1957/58 envelope. Development viability is also a concern in the absence of strategic flood defence infrastructure, as localised land raising (which has been pursued at some development sites to date), would become increasingly expensive over time ashigher levels of land raising are required to mitigate against climate change effects. This will erode development viability by increasing land raising costs and reducing the scale of development area. From a public good perspective, the flood defence element of the scheme will also help to safeguard existing economic activity already located in ASEA as well as safeguarding properties from flood events.

1 Identified by the Severnside and Avonmouth Wetland Habitat Project (Stage 1 & 2) and referred to as the Cresswell Study

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
180516 ASEA Phase 2 Report Appendix BAppendix 3.7 MB Download
PDF
180716 ASEA Phase 2 Report Appendix DAppendix 676 KB Download
PDF
20180529 Appendix E: Equalities Relevance Check_v2_signedAppendix 110 KB Download
PDF
20190321 ASEA Phase 2 Report Appendix A.PG.RM.KO.RMv2Appendix 221 KB Download
PDF
ASEA Phase 2 FBC.draft.v3.1.July18.docxReport 1.7 MB DownloadRead as text
PDF
Avonmouth Severnside Enterprise Area Infrastructure Phase 2Report 154 KB Download

At this meeting

Whole meeting

Who was there

9 of 14 attended
MR
Marvin ReesCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, apologies
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HG
Councillor Helen GodwinCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
AK
Councillor Anna KeenCommittee Member, present
PS
Councillor Paul SmithCommittee Member, present
SP
Councillor Steve PearceCommittee Member, present
RA
Rachel AbbaOfficer, expected
SM
Sara ManixOfficer, expected

All 14 on the meeting page

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies