Resolved
That the Cabinet Notes the Port Communities Resilience Fund Project Closure Report
Cabinet decided this item on Tuesday 2 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Cabinet Notes the Port Communities Resilience Fund Project Closure Report
Decision Pathway – Report
PURPOSE: For reference
MEETING: Cabinet
DATE: 02 June 2020
TITLE Port Communities Resilience Fund – Project Closure Report
Ward(s) Avonmouth and Lawrence Weston Wards Author: Warren Pickles Job title: PCRF Enabling Manager Cabinet lead: Cllr Asher Craig Executive Director lead: Stephen Peacock Proposal origin: Councillor Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. Report for information only including a summary of the projects delivered and lessons identified from the Port Communities Resilience Fund Capital spend project. Evidence Base: 1. The PCRF Project Closure Report included at Appendix A provides a summary of the Capital spend phase of the programme. 2. The Capital spend delivery phase was delivered through the Enabling Manager role and ceased on 31 March 2020 with all of the funds being spent/committed at that point. Monitoring of target outcomes will continue until end March 2023. A summary of each of the PCRF themes is provided below. a. Community Facilities Theme - £315K All grants have been paid and an annual monitoring workshop initiated. Capital grants were awarded to: i. Ambition Community Energy CiC for development of the community owned inshore wind turbine ii. Avonmouth Community Centre for building renovation works iii. Avonmouth Football Club for clubhouse improvements and extension iv. Avonmouth Old Boys Rugby Football Club for pitch maintenance equipment v. Twyford House Cricket Club (in association with Shirehampton Football Club) for refurbishment and extension of the clubhouse b. Jobs, Training and Enterprise Theme - £450K JTE Hubs: Four will be delivered within the ward using PCRF Capital funding to deliver accessible and useable spaces: i. Lawrence Weston Community Hub building expected to deliver spatial requirement from late 2020 but remains subject to approval. ii. Avonmouth spatial requirement to be included in renovated community centre from early 2020. iii. Shirehampton hub capacity to be delivered through an improved Methodist church hall from Spring 2020. iv. A Sea Mills hub capability to be delivered at the library with improved AV and furniture from spring 2020. Space4Makers: A grant has been paid to Oasis Community Hub to develop the textile and design programme. A new Space4Makers community workshop is to be available at the Bristol North West Foodbank from summer 2020. Community Market: A grant has been paid to Avonmouth Projects Group to run community markets in the ward supporting local sole traders and home based start –ups. Markets to commence in spring 2020. c. Thriving High Streets - £135K BCC Highways team have installed improvements in Sea Mills and are developing installation plans for April
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PCRF Project Closure Report-CabinetAppendix A | 277 KB | Download |
PDF |
Port Communities Resilience Fund Closure ReportDecisions | 186 KB | DownloadRead as text |
Follow Cabinet at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Apr 2024 | Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... | Decided | Open |
| 9 Apr 2024 | Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... | Approved | Open |
| 9 Apr 2024 | Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... | Noted | Open |
| 9 Apr 2024 | TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... | Approved | Open |
| 9 Apr 2024 | Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.