Bristol City Council
Cabinet, Tuesday 1 December 2020

Stabilisation of Redland Hill - Parapet Wall and Retaining Rock Face

Approved Executive 3 papers

Cabinet approved this item on Tuesday 1 December 2020. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

Cabinet: 1. Approved the additional spend of £442,217 to reflect the increase in costs as highlighted in the report. 2. Noted that the Spire Hospital are paying for all the full costs of the stabilisation works.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
RA: Appendix D: Risk RegisterAppendix 17 KB Copy on its way
PDF
Stabilisation of Redland Hill: Parapet Wall and Retaining Rock FaceReport 193 KB Copy on its way
PDF
Stabilisation of Redland Hill Wall Rockface: Appendix AAppendix 2 MB Copy on its way

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies