CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bristol City Council
Cabinet, Tuesday 14 September 2021

Youth Zone – funding request

Approved Executive 3 papers

Cabinet approved this item on Tuesday 14 September 2021. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Cabinet : Approved in principle to spend up to £4.2m on the Bristol Youth Zone scheme as 50% of project cost, subject to the feasibility study, approval of final business case and confirmation of total contribution required from the Council. Approved the immediate use of £350,000 from the capital budget to cover the at-risk cost of technical feasibility work required as part of project development to understand site constraints. Approved the immediate use of £45,000 from the capital budget to employ the Capital Strategic Partner to oversee the feasibility stage of this scheme. Approved progression of this project towards Full Business Case stage. Noted the decision (Cabinet, 9 March 2021) that ongoing revenue funding of £400,000 per year (30% of operating costs) will be sourced through the re-commissioning of youth services, and notes that plans for this activity will also be submitted to Cabinet for decision in due course.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Project PlanAppendix B 35 KB Copy on its way
PDF
Apppendix A -Map of proposed siteReport 350 KB Copy on its way
PDF
Youth Zone: funding requestReport 623 KB Copy on its way

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open