Item8
Resolved
Cabinet : Approved in principle to spend up to £4.2m on the Bristol Youth Zone scheme as 50% of project cost, subject to the feasibility study, approval of final business case and confirmation of total contribution required from the Council. Approved the immediate use of £350,000 from the capital budget to cover the at-risk cost of technical feasibility work required as part of project development to understand site constraints. Approved the immediate use of £45,000 from the capital budget to employ the Capital Strategic Partner to oversee the feasibility stage of this scheme. Approved progression of this project towards Full Business Case stage. Noted the decision (Cabinet, 9 March 2021) that ongoing revenue funding of £400,000 per year (30% of operating costs) will be sourced through the re-commissioning of youth services, and notes that plans for this activity will also be submitted to Cabinet for decision in due course.
Word for word from the decision Bristol published for this meeting.
Source: democracy.bristol.gov.uk