That Cabinet: 1. Approved a request for an additional £1.2m from WECA to fund additional NR costs and £0.2m for BCC costs. 2. Approved the request for up to £0.2m of revenue operating costs from WECA over three years. 3. Authorised the Executive Director Growth and Regeneration in consultation with the Cabinet Member Transport, to take all steps required to submit the requests for additional funding and if approved, negotiate and enter into any required grant agreements with WECA to enable this funding to be drawn down and spent on the project as outlined in this report. 4. Noted the completion of the Portway Park & Ride Rail Station, which will open to passengers by summer 2023.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Avonmouth & Lawrence Weston Author: Andrew Davies Job title: Principal Transport Planner Cabinet lead: Cllr Don Alexander Executive Director lead: Stephen Peacock, Executive Director Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To provide an update on the progress of the Portway Park & Ride Rail Station project. 2. To highlight a significant cost increase to the project. 3. To seek approval to request additional funding from the West of England Combined Authority (the Combined Authority) to meet the funding shortfall Evidence Base:
1. The Portway Park & Ride Rail Station is now substantially complete and due to open by summer 2023. It will be the first new rail station to be delivered as part of the MetroWest rail enhancement programme. It will be the first new rail station to open in Bristol since Parson Street in 1927, and the first new rail station to open in the West of England area since Filton Abbey Wood in 1996.
2. Work is also progressing to deliver an upgrade to the Park & Ride site to increase its size and improve access and facilities. These works are expected to complete at the end of March in time for the station opening. A project is also underway to improve the public transport corridor that the P&R service uses currently to bring the corridor up to metrobus standard with enhanced stops, increased priority measures and walking and cycling enhancements. This scheme has carried out engagement and is currently in the process of drawing up designs and going through the business case process.
3. Taken together, when completed, these schemes will offer a step change in sustainable transport options for local residents and the wider community.
4. As a third party promoted and funded rail station, Bristol City Council has been responsible for setting out the case for the station, identifying funding to develop and deliver it and; takes overall responsibility for the delivery of the scheme. Funding has been awarded from the Department for Transport and the Combined Authority as well as funding from the City Council. As a part funder of the scheme and given that the station falls within the wider MetroWest rail programme, the Combined Authority is supporting its delivery.
5. The City Council has signed an ‘emerging cost’ contract with Network Rail to deliver the main civils / rail infrastructure works for the station. Network Rail has contracted the main building works to an external contractor and is supporting the work with its own internal resources. Construction commenced in January 2022 and was due to complete in September 2022. However, a number of issues and challenges have delayed the programme and increased the scope of works, which have driven a significant increase in costs
1 Version Feb 2022 and delayed the opening until summer 2023. The station is now substantially complete with the testing, commissioning and safety validation processes currently underway.
6. Network Rail advised in August 2022 that additional costs had been incurred and would need to be funded by the city council or other partners. The final cost figure has now been confirmed as £1.19m over and above previously agreed costs.
7. Reasons for the cost increase are due to additional works required for track works, signalling, certification costs, power and communications connections, reduced possession (track closure) access, personnel costs and allowances made for risk. Some redesign work and changes to construction methodology were required, due to challenging ground conditions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.