CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bristol City Council
Cabinet, Tuesday 7 March 2023 at 4.00pm

Portway Park & Ride Rail Station

Approved Executive 1 paper

Cabinet approved this item on Tuesday 7 March 2023. Below is the council's own wording, with the papers it was decided on.

Item18

Resolved

That Cabinet: 1. Approved a request for an additional £1.2m from WECA to fund additional NR costs and £0.2m for BCC costs. 2. Approved the request for up to £0.2m of revenue operating costs from WECA over three years. 3. Authorised the Executive Director Growth and Regeneration in consultation with the Cabinet Member Transport, to take all steps required to submit the requests for additional funding and if approved, negotiate and enter into any required grant agreements with WECA to enable this funding to be drawn down and spent on the project as outlined in this report. 4. Noted the completion of the Portway Park & Ride Rail Station, which will open to passengers by summer 2023.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Cabinet

Decision Pathway – Report

PURPOSE: Key decision

MEETING: Cabinet

DATE: 07 March 2023

TITLE Portway Park & Ride Rail Station

Ward(s) Avonmouth & Lawrence Weston Author: Andrew Davies Job title: Principal Transport Planner Cabinet lead: Cllr Don Alexander Executive Director lead: Stephen Peacock, Executive Director Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To provide an update on the progress of the Portway Park & Ride Rail Station project. 2. To highlight a significant cost increase to the project. 3. To seek approval to request additional funding from the West of England Combined Authority (the Combined Authority) to meet the funding shortfall Evidence Base:

1. The Portway Park & Ride Rail Station is now substantially complete and due to open by summer 2023. It will be the first new rail station to be delivered as part of the MetroWest rail enhancement programme. It will be the first new rail station to open in Bristol since Parson Street in 1927, and the first new rail station to open in the West of England area since Filton Abbey Wood in 1996.

2. Work is also progressing to deliver an upgrade to the Park & Ride site to increase its size and improve access and facilities. These works are expected to complete at the end of March in time for the station opening. A project is also underway to improve the public transport corridor that the P&R service uses currently to bring the corridor up to metrobus standard with enhanced stops, increased priority measures and walking and cycling enhancements. This scheme has carried out engagement and is currently in the process of drawing up designs and going through the business case process.

3. Taken together, when completed, these schemes will offer a step change in sustainable transport options for local residents and the wider community.

4. As a third party promoted and funded rail station, Bristol City Council has been responsible for setting out the case for the station, identifying funding to develop and deliver it and; takes overall responsibility for the delivery of the scheme. Funding has been awarded from the Department for Transport and the Combined Authority as well as funding from the City Council. As a part funder of the scheme and given that the station falls within the wider MetroWest rail programme, the Combined Authority is supporting its delivery.

5. The City Council has signed an ‘emerging cost’ contract with Network Rail to deliver the main civils / rail infrastructure works for the station. Network Rail has contracted the main building works to an external contractor and is supporting the work with its own internal resources. Construction commenced in January 2022 and was due to complete in September 2022. However, a number of issues and challenges have delayed the programme and increased the scope of works, which have driven a significant increase in costs

1 Version Feb 2022 and delayed the opening until summer 2023. The station is now substantially complete with the testing, commissioning and safety validation processes currently underway.

6. Network Rail advised in August 2022 that additional costs had been incurred and would need to be funded by the city council or other partners. The final cost figure has now been confirmed as £1.19m over and above previously agreed costs.

7. Reasons for the cost increase are due to additional works required for track works, signalling, certification costs, power and communications connections, reduced possession (track closure) access, personnel costs and allowances made for risk. Some redesign work and changes to construction methodology were required, due to challenging ground conditions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Portway Park & Ride Rail StationDecisions 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
MR
Marvin ReesCommittee Member, apologies
DA
Councillor Donald AlexanderCommittee Member, present
NB
Councillor Nicola BeechCommittee Member, present
CC
Councillor Craig CheneyCommittee Member, present
AC
Councillor Asher CraigCommittee Member, present
KD
Councillor Kye DuddCommittee Member, present
HH
Councillor Helen HollandCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
HE
Hugh EvansOfficer, expected
SP
Stephen PeacockOfficer, expected
LD
Louise deCordovaOfficer, expected

All 16 on the meeting page

On this subject at Bristol

Search all
  1. Portway Park & Ride Rail StationThis decision
  2. Portway Park and Ride Bus Access Improvements Full Business Case (FBC)Approved
  3. Portway Park & Ride Car Park ExpansionApproved
  4. Portway Park and Ride Rail Station bid proposalApproved

More from Bristol Cabinet

All decisions
MeetingDecisionOutcome
9 Apr 2024 Single Homelessness Accommodation Programme (SHAP) Funding BidThat Cabinet: 1. Authorised, the Executive Director of Growth and Regeneration, in consultation with the Cabinet Memb... Decided Open
9 Apr 2024 Temporary Accommodation UpdateThat Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capita... Approved Open
9 Apr 2024 Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix... Noted Open
9 Apr 2024 TIBCO Maintenance ContractThat Cabinet: 1. Approved the re-procurement of a compliant maintenance contract for TIBCO for a period of 3 years a ... Approved Open
9 Apr 2024 Hybrid Meeting Technology and Audio-Visual UpgradesThat Cabinet: 1. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finan... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies