That Cabinet: 1. Authorised the Executive Director Growth and Regeneration, in consultation with the Cabinet Member for Housing Delivery and Homelessness to take all steps required to procure and award the contracts necessary for the implementation of the Homelessness Pathways Commissioning Plan, for 3 years with an option to extend for a further 2 years, in-line with the procurement routes and maximum total budget envelope of £6,169,374 (subject to any annual uplift agreed that will be based on CPI and an appropriate Housing index) as outlined in this report. 2. Authorised the Executive Director Growth and Regeneration in consultation with the Cabinet Member for Housing Delivery and Homelessness to invoke any subsequent extensions or variations specifically defined in the contracts being awarded, up to the maximum budget envelope (subject to any annual uplift agreed that will be based on CPI and an appropriate Housing index) outlined in this report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE Recommissioning of adult homelessness supported accommodation pathways Ward(s) City Wide Author: Paul Sylvester Job title: Head of Service, Housing Options Cabinet lead: Cllr Tom Renhard, Cabinet Executive Director lead: John Smith, Interim Executive Director Member for Housing Delivery and Homelessness Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: To recommission the supported accommodation pathways services for single homeless adults aged 22+ from 28 October 2024 for up to five years.
Evidence Base:
1. Introduction Housing and Landlord Services commission 725 units of low, medium and high support accommodation for single homeless adults aged 22+ (Pathways 1-3) along with a Resettlement service which provides short-term support to Pathways’ clients who move on to independent accommodation. A further 140 units of Pathways accommodation are funded by Public Health specifically for people looking to address substance use support needs (Pathway 4). An overview of current services can be found in Appendix A.
The current contracts expire on 27 October 2024. This report seeks approval to recommission services to commence on 28 October 2024 for a period of 3 years with the option to extend for a further 2 years.
2. The Need for Supported Accommodation Demand for supported accommodation can be inferred from data showing the number of people rough sleeping and in Temporary or Emergency Accommodation, and those approaching the Bristol City Council (BCC) Homeless Prevention Team for advice and assistance.
Single night counts and monthly rough sleeping figures both show significant rises in average rough sleeping year- on-year, with a corresponding increase in demand for supported accommodation. Overall presentations for homeless individuals have similarly steadily increased annually, after a drop between 2020 and 2021. This has led to an increase in the number of people living in unsupported temporary accommodation provided by private landlords.
The majority of Pathway units are owned by Registered Providers and are therefore exempt accommodation, with rental costs recoverable from Housing Benefit. BCC is currently looking to extend this type of accommodation through the Supported Singles and Couples Accommodation Framework as it is much cheaper than unsupported temporary accommodation provided by private landlords.
1 Version Feb 2022 3. Commissioning Process and Timescales A high-level overview of the recommissioning process is as follows: • Early engagement with key stakeholders including clients, current providers, pathways referrers, Public Health and Adult Social Care – September and October 2023 • Needs and Gap Analysis - December 2023 • Draft Commissioning Plan – January 2024 • Engagement on Draft Commissioning Plan – January 2024 - February 2024 • “You said, we did” Document – end of February 2024 • Final Commissioning Plan - end of February 2024 • Procurement – March-April 2024 • Contract award – end of June 2024 • Implementation period – August-October 2024 • New contracts start – 28 October 2024
4. Commissioning Intentions A draft Commissioning Plan will be published on the Consultation and Engagement Hub. Based on early engagement sessions and the Needs and Gap Analysis, we will be proposing the following:
a. Better matching accommodation type to demand. In particular: o Increasing the amount of medium support accommodation to create a more balanced pathway that better facilitates throughput from high support services. o Reducing the amount of low support accommodation that we commission given the existence of similar forms of accommodation funded through the Rough Sleeping Accommodation Programme. As we don’t want to lose this low support pathway provision entirely, we will look to repurpose this as long-term move-on accommodation from Pathways.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.