Non-key Decision Committee Report
PURPOSE: Non-key decision update report
COMMITTEE: Strategy and Resources Committee
DATE: 15 July 2024
TITLE: Q1 2024/25 Corporate Risk Report Officer presenting the report: Joachim Adenusi Title: Senior Risk and Insurance Officer
Committee Chair: Cllr Tony Dyer Executive Director lead: Paul Martin: Chief Executive Officer
Purpose of Report: The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2022-2027 and summarises progress in managing the risks and actions being taken as at Quarter 1 of 2024-25.
Evidence Base / Context 1. The Corporate Risk Report (CRR) is a key document in the council’s approach to the management of risk; it captures strategic risks set out in the Corporate Strategy 2022-2027. It also provides a context through which Directorates construct their own high-level risk assessments and is used to inform decision making about business planning, budget setting, transformation, and service delivery.
2. The CRR provides assurance to management and Members that Bristol City Council’s significant risks have been identified and arrangements are in place to manage those risks within the tolerance levels agreed. It should be noted that ‘risk’, by definition, includes both threats and opportunities, which is reflected in the CRR.
3. Ensuring that the Service Risk Registers (SRR), Directorate Risk Reports (DRR) and the Corporate Risk Reports (CRR) are soundly based will help the council to ensure it is anticipating and managing key risks to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
4. The registers and reports are a management tool. They need regular review to ensure that the occurrence of obstacles or events that may put individual’s safety at harm, impact upon service delivery and the council’s reputation are minimised, opportunities are maximised and when risks happen, they are managed effectively to minimise the impact.
5. The CRR summary of risks is attached to this report at Appendix A1 and is the latest position following a review by managers and Directors. The risks in Appendix A1 are presented in the order of severity, starting with the highest scoring risks followed by lower scoring risks.
Summary of Corporate Risks: 6. Corporate Leadership Board (CLB) members noted the CRR as a working summary report of the critical
1 Version January 2024 and significant risks from the Service Risk Registers as of 31st May 2024.
7. The CRR sets out the critical, significant, and high rated threats and opportunity risks. All other business risks reside on the Service Risk Registers.
8. Further programme of work with clear instructions to colleagues was undertaken to review and revise each CRR/DRR risk description, internal controls and mitigation plans and governance. The scope of this work included where possible the identification of new risks and a fresh look to confirm ongoing risks are current along with the actions to mitigate the risks.
9. Members of each Directorate reviewed the current CRRs and the DRRs on the 5th of June 2024 to form the current CRR risks. On the 11 of June 2024, CLB members accepted the attached CRR as a working summary report of the critical and significant risks from the Service Risk Registers.
10. The Q1 24-25 Corporate Risk Report (CRR) as at June 2024 contains 21 risks: Threat Risks Opportunity Risks External / Contingency Risks 3 Critical 14 High Nil Nil 4 Medium
2 Improving Risks 1 Deteriorating Risks 1 Escalated Risks 0 De-escalated Risks A summary of risks (Threat and Opportunities) for this reporting period are set out below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8.2 Appendix A1Appendix | 718 KB | Download |
PDF |
8.3 Appendix A2Appendix | 225 KB | Download |
PDF |
8.4 Appendix A3Appendix | 101 KB | Download |
PDF |
Quarter 1, 2024/25 Corporate Risk ReportReport | 349 KB | DownloadRead as text |
Follow Strategy and Resources Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2026 | Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... | Noted | Open |
| 12 Oct 2026 | Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... | Noted | Open |
| 12 Oct 2026 | Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... | Approved | Open |
| 12 Oct 2026 | Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... | Approved | Open |
| 12 Oct 2026 | Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.