Underfall Yard Trust Reinstatement Project – Collaboration Agreement and Payment Plan
ApprovedCommittee4 papers
Strategy and Resources Policy Committee approved this item on Monday 20 January 2025. Below is the council's own wording, with the papers it was decided on.
The Committee RESOLVED (unanimous vote in favour): 1. To approve the Collaboration Agreement (Appendix A). 2. To authorise the Executive Director: Growth and Regeneration in consultation with the Chair of the Strategy and Resources Policy Committee to take all steps required to transfer all insurance proceeds received in relation to the fire to Underfall Yard Trust as set out in the Collaboration Agreement. 3. To authorise the Executive Director: Growth and Regeneration in consultation with the Chair of the Strategy and Resources Policy Committee to enter into the Collaboration Agreement.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
1. To seek approval of the new Collaboration Agreement and to provide delegated powers, to the Executive Director of Growth and Regeneration, to approve the transfers of Insurance proceeds from the insurer, Zurich Insurance Company Ltd., to the Underfall Yard Trust project account, through the Council accounts where necessary, throughout the duration of the project.
Evidence Base / Options to consider:
1. On 6 May 2023 the Underfall Yard Trust (UYT) suffered a devastating fire, destroying the Big Shed, multiple workshops and six boats.
2. On 7 September 2023 an officer decision was taken to release up to £499,000 and to enter into a Collaboration Agreement (dated 12 October 2023) to support the first phase (Phase 1) of the works which included making the site safe, mitigating further deterioration, reopening the Harbourside walk, plus professional fees for the initial design work for the rebuild. This is funded by the first tranche of insurance proceeds. To date, the project spend is £228k.
3. This Phase 1, managed by UYT, is now completed and has taken the project up to RIBA Stage 3 (project design aesthetics and functionality are now aligned ready to design the detail).
1 Version January 2024
OFFICIAL 4. The next phase requires a further Collaboration Agreement which is now finalised. Implementing this further Collaboration Agreement will see the rebuild progress into RIBA Stage 4 and beyond, eventually to project completion.
5. Below are the key elements of this new Collaboration Agreement:
1) This Collaboration Agreement supersedes the original Collaboration Agreement (12 October 2023). 2) A project board, consisting of members from both the UYT and Council, will be set up. 3) The UYT will manage the reinstatement project, as per the agreement within their lease. 4) The Council will claim the insurance proceeds and ensure these are passed swiftly to the UYT project account, to ensure no delay to the project progress. 5) The Collaboration Agreement will provide the necessary assurance around the use of the funds. 6) Any shortfall between the insurance sum and the project sum will be financed by the UYT’s own means.
6. The project programme currently estimates construction work commences in early Q3 2025 and completes early Q3 2026. The current estimated insurance proceeds are £2.1m and the current project total is £2.8m exc. VAT (July 2024 MDA estimate).
7. UYT are responsible for any shortfall in project funding and have commissioned a fundraising consultancy.
8. The council is keen to continue to progress this project and support the UYT to build its proposition back to a fully operational asset.
Officer Recommendations:
That the Committee for Strategy and Resource:
1. Approves the Collaboration Agreement (Appendix A) 2. Authorises the Executive Director for Growth and Regeneration in consultation with the Chair of the Strategy and Resources Committee to take all steps required to transfer all insurance proceeds received in relation to the fire to UYT as set out in the Collaboration Agreement.
Contractual:
3. Authorises the Executive Director for Growth and Regeneration in consultation with Chair of the Strategy and Resources Committee to enter into the Collaboration Agreement.
Notes: • N/A
Corporate Strategy alignment:
1. Supporting the UYT’s rebuild will assist numerous corporate strategy themes including; Children and
2 Version January 2024
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.