The Committee RESOLVED (unanimous vote in favour): 1. To approve the 2025/26 Building Practice Health and Safety Capital Budget allocation, as set out in the report and Appendix A. 2. To authorise the Executive Director: Growth and Regeneration, in consultation with the Chair of the Strategy and Resources Policy Committee, to take all steps required to implement the programme of works in Appendix A including procuring and awarding contracts which may be over the key decision threshold.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
TITLE: Building Practice Health and Safety Capital Plan Wards All
Officer presenting the report: Tom Hedges Job title: Head of Corporate Landlord
Committee Chair: Cllr Tony Dyer Executive Director lead: John Smith: Executive Director for Growth & Regeneration
Proposal origin: BCC Staff
Purpose of Report: To seek approval of the 2025/26 Building Practice H&S Capital Budget allocation.
Evidence Base:
1. This is a programme of essential building improvement works which ensures that our estate is safe and fit for purpose.
2. Appendix A details the sites which require work, and what type of work is needed, and is constructed using three streams of information:
a) Statutory Obligations b) Surveyor’s knowledge of their portfolio c) Unsighted emergency Health and Safety work
3. The Appendix details the different works that will be undertaken across the estate which covers the following areas –
• Works required to fulfil legal and statutory obligations • Works required to avoid possible litigation from statutory bodies • Works required to ensure acceptable Health and safety standards • Works required to ensure continued operation of buildings.
1 Version January 2024
OFFICIAL 4. Total, including contingency, is £1,560,000 plus £921,000 for BCC maintained school sites (where the £921,000 is funded through Department for Education grant funding), for 2025/26. Grand total of £2,481,000.
5. The formulation of the programme has been based on the knowledge of the Council’s senior building surveyors, along with dialogue and engagement with various teams, including Corporate Landlord Building Safety Board, Education Property, Statutory Registrations, Libraries and Procurement.
6. The programme also helps to improve the environmental performance of the estate, by installing more efficient heating approaches and improving insulation to some sites through repairs to roofs, windows and doors. The programme helps support the Council to move towards a carbon neutral estate, with City Leap being the delivery partner.
7. It is worth noting that the estate rationalisation programme may impact on some of the sites listed. The proposition is that any funds allocated to sites which are subsequently deemed surplus would be re- purposed to other assets / sites – based on a needs / priority assessment.
Officer Recommendations: That the Committee for Strategy and Resources:
1. Approves the 2025/26 Building Practice Health and Safety Capital Budget allocation, as set out in this report and Appendix A. 2. Authorises the Executive Director of Growth and Regeneration, in consultation with the Chair of the Strategy & Resources Committee, to take all steps required to implement the programme of works in Appendix A including procuring and awarding contracts which may be over the key decision threshold.
Corporate Strategy alignment:
Contributes to safer working environments and enhanced wellbeing for citizens, colleagues and service users of our buildings.
City Benefits:
The Council owns and occupies a large number of buildings used to deliver its services. The Council has a statutory duty to maintain and service the mechanical and electrical assets in these buildings. It is crucial the Council meets its legal obligation to maintain all assets to allow colleagues, partners and building users to operate in a safe and secure environment.
Consultation Details:
This has been discussed at DMT, EDM, CIB and has been circulated to internal teams.
Background Documents: Appendix A.
2 Version January 2024
OFFICIAL Revenue Cost £0 Source of Revenue N/A Funding Capital Cost £2,481,000 Source of Capital Funding Prudential Borrowing - £1,560,000 DfE Condition Grant - £921,000 One off cost ☒ Ongoing cost ☐ Saving Proposal ☐ If yes - existing or new saving? Choose an item. OR Income generation proposal ☐
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.