Homes and Housing Delivery Policy Committee decided this item on Friday 14 February 2025. Below is the council's own wording, with the papers it was decided on.
The Committee (unanimously) RESOLVED : 1. To authorise the Executive Director of Growth and Regeneration in consultation with Chair of the Homes and Housing Delivery Committee to procure and award the Fire Risk Assessment contract, and any subsequent extensions or variations, in-line with the procurement routes and maximum budget envelopes outlined in this report. 2. To authorise the Executive Director of Growth and Regeneration in consultation with Chair of the Homes and Housing Delivery Committee to extend the existing contract by up to 6 months.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Homes and Housing Delivery Policy Committee
Purpose of report
1. This paper seeks approval to procure a new fire risk assessment contract, this will be undertaken in line with the guidance from the procurement and contract management service.
Evidence Base / Options to consider:
1. The current contract to deliver fire risk assessments is due to expire on 31 March 2025. Under the Regulatory Reform (Fire Safety) Order 2005, the Council are required to undertake fire risk assessments on all residential buildings which contain two or more dwellings.
2. There is an option to extend for a further year, however owing to the number of assessments that are required, the council wishes to pursue additional providers to increase the rate at which assessments are completed, in addition to ensuring the highest competency and quality of assessment is completed for a high-profile area.
3. New fire safety and building safety legislation brought out by the Government over the course of the last few years requires an increased amount of demonstratable competence by those carrying out the risk assessments, particular in high rise/high risk premises.
4. It is proposed we procure a new contractor to deliver the fire risk assessment service for the Council, and by doing so, we can look to request the companies tendering for the contract are BAFE accredited, BAFE Fire Safety Register is an independent fire safety registration body, but also that
1 Version January 2024
OFFICIAL their risk assessors are directly employed and are members of the Tiered Fire Risk Assessors Register (TFRAR).
5. The TFRAR was set up by the Institute of Fire Safety Managers to help people locate registered competent professionals – this places a “Tier” of competency on those who have registered. The register ranges from entry level assessors just starting out in their career (Tier 1) through to nationally accredited, highly experienced professionals (Tier 3).
6. The Procurement for Housing (PfH) framework where the current FRA contractor was sourced from have a limited number of contractors available, therefore the proposal is to utilise an alternative route, as will be guided by the Procurement & Contract Management Service, that maximises the exposure of this procurement to a number of qualified contractors.
7. The Building Safety Team will work with the Procurement & Contract Management Service to ensure that any procurement process complies with both the Councils procurement rules and the relevant procurement legislation. The proposal is to contract with 2 providers to mitigate risk of one provider being short on capacity, and to maximise the number of assessments that can be undertaken. The contract will include suitable KPIs to ensure adequate delivery of services, and break clauses are to address any persistent non-performance.
8. It is proposed the Council procures a 2-year contract, with an option to extend for a further 2 years if contractor performance is acceptable.
Officer Recommendations: -
That the Committee for Homes and Housing Delivery approves:
1. Authorisation for the Executive Director of Growth and Regeneration in consultation with Chair of the Homes and Housing Delivery Committee to procure and award the Fire Risk Assessment contract, and any subsequent extensions or variations, in-line with the procurement routes and maximum budget envelopes outlined in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Homes and Housing Delivery Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.