Resolved
The Committee
AI summaryBristol City Council committee notes progress on cladding remediation programme for 24 high rise buildings, with pilot tranches running behind original schedule but still within overall 2029 deadline.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
The Committee
Committee Report
KEY DECISION OR FOR INFORMATION: For Information
COMMITTEE: Homes and Housing Delivery Committee
DATE: 18 September 2026
TITLE: Annual Cladding Remediation Update
Ward(s): All
Officer presenting the report: Ashley Lehous-Reuben (BCC) & Carol Mackley (Turner & Townsend)
Job title: Head of Capital Works and Specialist Projects & Project Director
Committee Chair: Councillor Barry Parsons
Executive Director lead: David McNulty, Executive Director: Housing
Proposal origin: BCC Staff
Purpose of Report: To provide Committee with a status report and update on progress during the first year of the Accelerated Cladding Remediation Programme, lessons learnt to date, and the successes and challenges in the delivery of Option 2 - that BCC act as Professional Client, which was approved by Committee on 18 July 2025.
Executive summary: The Committee is requested to note that the Professional Client Approach and the working relationship with Turner and Townsend (T&T) has overall been a success, although it has needed active management to bed in different ways of working. The Cladding Programme is moving at the accelerated pace required but we are currently in the process of recruiting three project managers, to help facilitate and coordinate the necessary interactions between the programme team and ‘business as usual’ teams.
Context: Bristol City Council (BCC) is implementing a programme of fire safety remediation works across its portfolio of eligible high-rise buildings, funded through the Homes England Cladding Safety Scheme (CSS). This UK Government initiative provides funding for the remediation of life-critical fire safety defects in residential buildings over eleven metres in height, known as HRBs – higher risk buildings. The deadline for remediation of cladding on these HRBs is end 2029.
1. The Role of Turner and Townsend Homes England (appointment 1 2025) initially appointed Turner & Townsend (T&T) to complete a ‘strategic review’ for BCC, including a review of BCC cladding remediation activity and plans and original affordable programmes. The output of this review was a recommendation to decouple cladding remediation from other refurbishment / maintenance programmes and treat this activity as a distinct programme. T&T also recommended the use of procurement frameworks – existing and new.
Under agreed delegated authority, BCC (appointment 2 2025) then appointed T&T to complete an ‘implementation review’ – how to deliver this separate programme faster. T&T provided programme management expertise and an output in the form of several reports – key of which were a procurement strategy and funding analysis. The strategic deliverables were translated into actionable solutions, focussing on key areas such as procurement, a business case and programme options analysis plus supporting analysis behind these reports. This suite of reports determined the delivery plan for the programme and led to the Cladding Remediation Pilot covering Tranches 1 and 2 (appointment 3 2025). Each of the three appointments summarised above was funded by the Homes England Cladding Safety Scheme.
2. The Cladding Remediation Pilot
The objective was to implement an optimised pilot programme, independent of other works in BCC, to remediate six priority Higher Risk Buildings (HRBs) faster than the block-by-block delivery approach taken to date. This pilot initiative was to include the introduction of a new delivery model and expansion of the supply chain, thereby developing a toolkit for accelerating the remediation programme. A key aim was to demonstrate that the toolkit can deliver the necessary acceleration. If successful, the approach would roll out to the remaining 18 blocks identified. Detailed aims below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Cladding Remediation UpdateReport | 203 KB | DownloadRead as text |
PDF |
BCC CSS TT Monthly Update (August 2026)Appendix A1 | 615 KB | Download |
PDF |
BCC CSS Tranche 1 Lessons Learned RIBA 3Appendix A2 | 93 KB | Download |
PDF |
Equality Impact AssessmentAppendix B | 141 KB | Download |
PDF |
Environmental Impact AssessmentAppendix C | 153 KB | Download |
PDF |
Item 11 Presentation: Annual update Accelerated Cladding Remediation Programme (Turner and Townsend)Report | 545 KB | Download |
Follow Homes and Housing Delivery Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2026 | Q1 (P03) Finance UpdateThe Committee | Decided | Open |
| 18 Sep 2026 | Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. | Noted | Open |
| 18 Sep 2026 | Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... | Noted | Open |
| 18 Sep 2026 | Asset Management StrategyThe Committee (unanimously) | Decided | Open |
| 18 Sep 2026 | Q2 Progress Update on the Housing Resident and Community PanelThe Committee | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.