Annual Cladding Remediation Update

Decided Committee 6 papers

AI summaryBristol City Council committee notes progress on cladding remediation programme for 24 high rise buildings, with pilot tranches running behind original schedule but still within overall 2029 deadline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCommittee noted the annual update on the Accelerated Cladding Remediation Programme for 24 high rise buildings. The pilot scheme covering 6 blocks and the remaining programme are progressing but behind original schedules.
Money£106mEstimated capital cost, funded by Homes England Cladding Safety Scheme grant
What happens nextBSR Gateway 2 approvals and construction funding applications. Following Building Safety Regulator approvals, applications for construction funding will be made to Homes England
Who it affectsResidents of 24 high rise buildings over 11 metres. Buildings include Barton House, Castlegate House, Polden House, Holroyd House, Barlands House, Brookridge House and 18 further blocks

What was decided

The Committee noted progress during 2025, 2026 and the report on the Accelerated Cladding Remediation Programme. Report P65

Why

The programme aims to remediate fire safety defects in high rise buildings over 11 metres by end of 2029, funded through the Homes England Cladding Safety Scheme. Report P14

Bristol City Council is acting as Professional Client, with Turner and Townsend providing programme and project management. The approach overall has been a success but has needed active management. Report P13, P25

Both pilot tranches are running behind the initial schedule but Homes England remain satisfied with progress. These delays will not impact overall programme timelines. Report P30

What happens next

Design and build contractors will be procured for tranches 3 to 5 to complete technical design and enable Gateway 2 applications for remaining blocks. Report P58

Once BSR approvals are received, applications for construction funding will be made to Homes England under the Cladding Safety Scheme. Report P59

Once funding is in place, resident and stakeholder communications will be issued and works will start on site. Report P61

The money

  • c.£106m Estimated capital cost for cladding remediation programme Report P76
  • £105m Budgetary provision over next 4 financial years Report P78
  • £98m Grant funding supported by Homes England Report P78

Options considered

  • Rejected: No alternatives considered. Programme was developed to meet central government deadline of 2029, therefore no alternative options were considered Report P55

Implications

  • Financial: Wider cladding remediation programme has budgetary provision of £105m over 4 financial years, supported by grant funding of £98m from Homes England Report P78
  • Risk: Pace of procurement approval governance does not match accelerated programme pace; Contract Awards can take 6-9 weeks to complete governance Report P45
  • Risk: Internal legal support allocated project by project; securing external legal support is time consuming and caused delays for Tranches 1 and 2 Report P48, P49, P50
  • Risk: Constellia framework provider used incorrect contract type (general goods and services instead of construction professional services) placing council at commercial risk Report P53
  • Risk: Adjacent mid-rise blocks may need to be brought into scope if dependencies for shared access and fire evacuation are validated Report P31

Who and where

  • Residents of Barton House, Castlegate House, Polden House and Holroyd House (Tranche 1) Report P21, P27
  • Residents of Barlands House and Brookridge House (Tranche 2) Report P21, P29
  • Residents of 18 further blocks in Tranches 3-5 Report P18, P30
  • Building Safety Regulator Report P27, P42, P43

Timeline

  • Early 2025: Turner and Townsend initially appointed for strategic review Report P15
  • 2025: T&T appointed for implementation review Report P16
  • 18 July 2025: Committee approved Option 2 - BCC acting as Professional Client Report P12
  • 2025: Cladding Remediation Pilot covering Tranches 1 and 2 commenced Report P16
  • End November 2025: Homes England agreed re-baselined schedule Report P30
  • March 2026: T&T appointed as Programme and Project Manager for Tranches 3,4 and 5 Report P25
  • May 2026: BSR Gateway 2 application submitted for Barton House Report P27
  • 22 June 2026: BSR Gateway 2 application submitted for Castlegate House Report P27
  • 22 July 2026: BSR Gateway 2 applications submitted for Polden and Holroyd Houses Report P27
  • 23 July 2026: Pre-construction contract with Lawtech signed for Tranche 2 Report P29
  • End 2029: Deadline for remediation of cladding on high rise buildings Report P14
  • 18 September 2026: Committee meeting - progress update noted Report P4

Plain English for the jargon

  • HRB: Higher Risk Building - residential building over 11 metres in height
  • BSR Gateway 2: Building Safety Regulator approval stage for building designs before construction
  • RIBA: Royal Institute of British Architects; stages 2-4 refer to design development phases
  • SCAPE framework: Public sector procurement framework for construction services
  • Constellia framework: Consultancy procurement framework
  • CHIC framework: Community Housing Improvement Consortium procurement framework for construction
  • CSS: Cladding Safety Scheme - Homes England funding programme for cladding remediation
  • PSC: Pre-construction Services Contract
  • PCSA: Pre-construction Services Agreement
  • ITT: Invitation to Tender
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

The Committee
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Committee Report

KEY DECISION OR FOR INFORMATION: For Information

COMMITTEE: Homes and Housing Delivery Committee

DATE: 18 September 2026

TITLE: Annual Cladding Remediation Update

Ward(s): All

Officer presenting the report: Ashley Lehous-Reuben (BCC) & Carol Mackley (Turner & Townsend)

Job title: Head of Capital Works and Specialist Projects & Project Director

Committee Chair: Councillor Barry Parsons

Executive Director lead: David McNulty, Executive Director: Housing

Proposal origin: BCC Staff

Purpose of Report: To provide Committee with a status report and update on progress during the first year of the Accelerated Cladding Remediation Programme, lessons learnt to date, and the successes and challenges in the delivery of Option 2 - that BCC act as Professional Client, which was approved by Committee on 18 July 2025.

Executive summary: The Committee is requested to note that the Professional Client Approach and the working relationship with Turner and Townsend (T&T) has overall been a success, although it has needed active management to bed in different ways of working. The Cladding Programme is moving at the accelerated pace required but we are currently in the process of recruiting three project managers, to help facilitate and coordinate the necessary interactions between the programme team and ‘business as usual’ teams.

Context: Bristol City Council (BCC) is implementing a programme of fire safety remediation works across its portfolio of eligible high-rise buildings, funded through the Homes England Cladding Safety Scheme (CSS). This UK Government initiative provides funding for the remediation of life-critical fire safety defects in residential buildings over eleven metres in height, known as HRBs – higher risk buildings. The deadline for remediation of cladding on these HRBs is end 2029.

1. The Role of Turner and Townsend Homes England (appointment 1 2025) initially appointed Turner & Townsend (T&T) to complete a ‘strategic review’ for BCC, including a review of BCC cladding remediation activity and plans and original affordable programmes. The output of this review was a recommendation to decouple cladding remediation from other refurbishment / maintenance programmes and treat this activity as a distinct programme. T&T also recommended the use of procurement frameworks – existing and new.

Under agreed delegated authority, BCC (appointment 2 2025) then appointed T&T to complete an ‘implementation review’ – how to deliver this separate programme faster. T&T provided programme management expertise and an output in the form of several reports – key of which were a procurement strategy and funding analysis. The strategic deliverables were translated into actionable solutions, focussing on key areas such as procurement, a business case and programme options analysis plus supporting analysis behind these reports. This suite of reports determined the delivery plan for the programme and led to the Cladding Remediation Pilot covering Tranches 1 and 2 (appointment 3 2025). Each of the three appointments summarised above was funded by the Homes England Cladding Safety Scheme.

2. The Cladding Remediation Pilot

The objective was to implement an optimised pilot programme, independent of other works in BCC, to remediate six priority Higher Risk Buildings (HRBs) faster than the block-by-block delivery approach taken to date. This pilot initiative was to include the introduction of a new delivery model and expansion of the supply chain, thereby developing a toolkit for accelerating the remediation programme. A key aim was to demonstrate that the toolkit can deliver the necessary acceleration. If successful, the approach would roll out to the remaining 18 blocks identified. Detailed aims below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Annual Cladding Remediation UpdateReport 203 KB DownloadRead as text
PDF
BCC CSS TT Monthly Update (August 2026)Appendix A1 615 KB Download
PDF
BCC CSS Tranche 1 Lessons Learned RIBA 3Appendix A2 93 KB Download
PDF
Equality Impact AssessmentAppendix B 141 KB Download
PDF
Environmental Impact AssessmentAppendix C 153 KB Download
PDF
Item 11 Presentation: Annual update Accelerated Cladding Remediation Programme (Turner and Townsend)Report 545 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
KB
Councillor Kerry BailesCommittee Member, present
PG
Councillor Paul GogginCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
JS
John SmithOfficer, expected
CG
Clare GibbOfficer, expected
FL
Fiona LesterOfficer, expected

All 15 on the meeting page

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open
18 Sep 2026 Q2 Progress Update on the Housing Resident and Community PanelThe Committee Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies