It was agreed to provide commentary in the next quarter to this affect; 3. Policy determined the criteria for inclusion on the register. It was not an automatic decision to remove from the register but to seek assurance the risk will be sustainable; It was confirmed that there would be a deep dive report at the July Committee on CRR60 Housing Standards; 5. CRR43 – The Council continued to be very engaged with WECA regarding grants to ensure that funding stayed within the region. It was also about whether the outcome of the government’s comprehensive spending review continued to invest in transport; 6. It was confirmed that there would be a deep dive report at the July Committee on Housing Standards; 7. CRR64 – this risk was not being expressed through the lens of risk previously and was now on an enhanced Risk Register for Q4; 8. Audit Committee should focus on how risk was managed rather than individual risks as they were considered at each Policy Committee. Resolved – That the Q4 2024/25 Corporate Risk Report be noted.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
▪ The Audit Committee review and comment the Q4 2024/25 Corporate Risk Report.
Summary
This report presents the Corporate Risk Report as at 17 March 2025.
The significant issues in the report are:
• The Corporate Risk Report (CRR) is an important tool in managing risk. It aims to provide an overview of the significant risks facing the council and how they are being managed. The CRR attached to this report as Appendix A1 and is the latest formal iteration following a review by members of the council’s Corporate Leadership Board (CLB) and the Strategy and Resources Policy Committee. The Q4 2024/25 risk review included managers’ review from across the Council. Appendix A2 – Static Risks Q4 202/25 Corporate Risk Report. Appendix A3 – Risks Scoring 20 to 28 but not in Corporate Risk Register Q3 2024/25.
1 1 Policy
1.1The Accounts and Audit Regulations 2015 require the council to have in place effective arrangements for the management of risk. These arrangements are reviewed each year and reported as part of the Annual Governance Statement (AGS). The Council is required to comment on the effectiveness of its arrangements in this regard. The statement must also identify any significant governance issues that may have resulted from failures in governance and risk management.
1.2Risk Management is an integral part of good governance to which the Council is committed. Risk Management provides the framework and processes that enables the Council to manage uncertainty in a systematic way. As part of the Risk Management arrangements the Council reviews the Risk Management Assurance Policy on an annual basis.
1.3It is considered good practice to regularly review and update the Risk Management Assurance Policy to ensure it strengthens the Council's approach to its risk management and assurance arrangements.
1.4Ensuring that the Corporate Risk Report (CRR) is soundly based will help the council to ensure it is anticipating and managing key risks to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
1.5The CRR provides assurance to management and Members that Bristol City Council’s significant risks have been identified and arrangements are in place to manage those risks within the tolerance levels agreed.
1.6The CRR is a management tool and needs regular review to ensure that the occurrence of obstacles or events that may put individual’s safety at harm, impact upon service delivery and the council’s reputation are minimised, opportunities are maximised and when risks happen, they are managed and communicated to minimise the impact.
1.7The CRR has been prepared and presented in line with the Risk Management Assurance Policy that was approved by Cabinet in January 2019.
Consultation
Internal - First to fourth tier managers, Extended Leadership Team, Corporate Leadership Team, Strategy and Resources Policy Committee.
External – None
3. Context - Corporate Risk Report 3.1. The Accounts and Audit Regulations 2015 require the council to have in place effective arrangements for the management of risk. These arrangements are reviewed each year and reported as part of the Annual Governance Statement (AGS).
3.2Ensuring that the Service Risk Registers (SRR), Directorate Risk Reports (DRR) and the Corporate Risk Reports (CRR) are soundly based will help the council to ensure it is anticipating and managing key risks to optimise the achievement of the council’s objectives and prioritise actions for managing those risks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Annual Report 2025/26Decision Notices would be subject to reaudit in the first half of 2026/27. ACTION: Officersto (1)improve accessibilit...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.