Strategy and Resources Policy Committee, Tuesday 20 January 2026 at 2.30pm

Finance Report: P8/Q3

Noted Committee 6 papers

AI summaryBristol City Council's Strategy and Resources Committee noted a £16.5 million General Fund revenue overspend against a £571.4 million budget at P8 2025/26, and approved earmarked reserve movements and budget revisions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedIncluding reserve movements and budget revisions
Money£16.5m General Fund overspendAgainst £571.4m approved budget at P8 2025/26
What happens nextBudget recovery measures continueEarmarked reserve transfer at year end
Who it affectsGeneral Fund, HRA, schoolsPlus council tax and business rate collection

What was decided

The Committee noted the General Fund forecast outturn revenue overspend of £16.5 million against the approved budget of £571.4 million, plus a £40.0 million net overspend on the Dedicated Schools Grant.

The Committee approved the release of £1.3 million of corporate held inflation and pay inflation budget, initially unallocated to directorates' cash limits.

The Committee approved a revision to the DSG gross budget reflecting a £2.1 million reduction in the budget allocation since Period 5, and approved movements on Earmarked Reserves.

Why

The report presents the council's financial performance against its approved budget and forecast use of resources for 2025/26, as part of standard budget management.

The DSG position is governed by the DfE Safety Valve agreement, under which the General Fund budget includes a planned £11.7 million transfer to an earmarked reserve at year end.

The HRA overspend of £0.5 million is to be contained by the HRA general reserve at year end.

What happens next

Continue progress on budget recovery measures and actions in accordance with Budget Management Principles.

Transfer £11.7 million from the General Fund to an earmarked reserve at year end under the DfE Safety Valve agreement.

Use £20.7 million of capital receipts as planned, and contain the £0.5 million HRA overspend via the HRA general reserve.

The money

  • £16.5 million General Fund forecast outturn revenue overspend at P8 2025/26
  • £571.4 million Council approved General Fund budget
  • £3.5 million Additional weighted net opportunity to the General Fund per risks and opportunities register
  • £0.5 million HRA outturn overspend to be contained by HRA general reserve
  • £0.7 million Additional weighted net risk to the HRA per risks and opportunities register
  • £40.0 million Net overspend in the Dedicated Schools Grant
  • £11.7 million Transfer to earmarked reserve at year end under DfE Safety Valve agreement
  • £22.3 million Forecast underspend against Capital Programme revised budget 2025/26
  • £11.8 million Underspend on General Fund within Capital Programme
  • £10.5 million Underspend on HRA within Capital Programme
  • £20.7 million Planned use of capital receipts
  • £1.3 million Release of corporate held inflation and pay inflation budget
  • £2.1 million Reduction in DSG budget allocation since Period 5

Options considered

  • Chosen: Note the financial outturn positions and risks across General Fund, HRA, DSG, Public Health and Bristol Harbour Fund. Part of standard budget management and reporting to committee
  • Chosen: Release £1.3 million corporate held inflation and pay inflation budget. Budget was approved in 2025/26 but not initially allocated to directorates' cash limits
  • Chosen: Revise the DSG gross budget to reflect a £2.1 million reduction in budget allocation since Period 5. To align with the latest advised allocation following Period 8 reporting
  • Chosen: Approve movements on Earmarked Reserves per Appendix A1a Table 11

Implications

  • Financial: General Fund revenue overspend of £16.5 million against approved budget of £571.4 million at P8 2025/26.
  • Financial: DSG net overspend of £40.0 million, with £11.7 million planned transfer to an earmarked reserve at year end under the DfE Safety Valve agreement.
  • Financial: HRA overspend of £0.5 million to be contained by the HRA general reserve at year end; additional weighted net risk of £0.7 million.
  • Financial: Capital Programme forecast underspend of £22.3 million, split £11.8 million General Fund and £10.5 million HRA.
  • Financial: Public Health services and the Bristol Harbour Fund reported a breakeven position.
  • Risk: Risks and opportunities register shows additional weighted net opportunity of £3.5 million for the General Fund and additional weighted net risk of £0.7 million for the HRA.
  • Other: Progress update on budget recovery measures and actions in accordance with Budget Management Principles, plus latest position on balance sheet risks.
  • Other: In-year collection levels for Council Tax and Business Rates reported, with aged debt levels as at 30 November 2025.

Who and where

  • General Fund services and directorates
  • HRA tenants and landlord services
  • Schools and education providers funded via the Dedicated Schools Grant
  • Council Tax and Business Rates payers
  • Public Health service users
  • Bristol Harbour users and operators

Timeline

  • 9 September 2025: S151 Review sign off by Andy Rothery Report P11
  • 19 September 2025: Committee Chair sign off (Cllr Dyer, PCCB) Report P11
  • 13 October 2025: Committee date shown on the report cover Report P9
  • 30 November 2025: Date of aged debt position reported
  • P8 2025/26: Period 8 financial monitoring position reported (current report period)
  • Year end 2025/26: Planned transfer of £11.7 million to earmarked reserve under DfE Safety Valve agreement

Plain English for the jargon

  • DSG: Dedicated Schools Grant, the main ring-fenced funding for schools.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing landlord services.
  • General Fund: The council's main revenue account for non-housing services.
  • P8: Period 8, a monthly financial monitoring point in the local government budget cycle.
  • S151 Officer: The local authority's statutory chief finance officer, responsible for proper financial administration.
  • DfE Safety Valve: A Department for Education programme for councils with high deficits on the Dedicated Schools Grant.
  • Earmarked Reserves: Council reserves set aside for a specific planned purpose.
  • Capital Receipts: Income from the sale of capital assets, which can be used to fund new capital spending.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the Committee noted: 1. The council’s General Fund forecast outturn revenue overspend of £16.5 million at P8 2025/26 against the council approved budget of £571.4 million. 2. The additional weighted net opportunity to the General Fund of £3.5 million per the risks and opportunities register (Appendix A1a, Section 4, Tables 4a and 4b) 3. The performance on delivery of savings (Appendix A1a, Section 5, Tables 5a and 5b). 4. The council’s outturn position of £0.5 million overspend within the Housing Revenue Account to be contained by the HRA general reserve at the year end (Appendix A1a, Section 7.3). 5. The additional weighted net risk to the HRA of £0.7 million per the risks and opportunities register (Appendix A1a, Section 4, Tables 4a and 4b) 6. The council’s outturn position of a £40.0 million net overspend in the Dedicated Schools Grant and that, as part of the DfE Safety Valve agreement, the General Fund approved budget for 2025/26 includes the transfer of £11.7 million to an earmarked reserve at year end (Appendix A1a, Section 7.4). 7. The breakeven position on Public Health services (Appendix A1a, Section 7.5). 8. The breakeven position on the Bristol Harbour Fund. (Appendix A1a, Section 7.6). 9. The progress update on budget recovery measures and actions in accordance with Budget Management Principles. (Appendix A1a, Section 6). 10. The latest position on balance sheet risks. 11. The council’s forecast underspend of £22.3 million against the Capital Programme revised budget 2025/26, comprised of £11.8 million underspend on the General Fund and £10.5 million underspend on the HRA. (Appendix A1b, Section 1). 12. The planned use of capital receipts of £20.7 million. 13. The in-year collection levels for Council Tax and Business Rates as set out in the reports (Appendix A1a section 8) 14. The levels of aged debt as at 30 November 2025 (Appendix A1a, section 8.9) 15. Balances on the General Fund and Earmarked Reserves at P8 and movements from P5 to P8 close (Appendix A1a, section 10). That the Committee approved (unanimous vote in favour): 1. Movements on Earmarked Reserves (Appendix A1a, Table 11). 2. The release of £1.3 million corporate held inflation and pay inflation budget as approved in the 2025/26 budget but not initially allocated to directorates’ cash limits (see Appendix A1a, Table 3a and 3b) 3. Revision to the DSG gross budget following Period 8 reporting to reflect advised £2.1 million reduction in the budget allocation since Period 5.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Committee Report

PURPOSE: Final Decision Report Key or non-key decision: Key decision affects 2 or more wards

COMMITTEE: Strategy and Resources Committee

DATE: 20 January 2026

TITLE: Period 8 Finance Outturn Report 2025/26 Ward(s) City Wide

Officer presenting the report: Andy Rothery Job title: S151 Officer

Committee Chair: Cllr Tony Dyer Executive Director lead: Nick Hibberd: Chief Executive Officer

Proposal origin: Other

Purpose of Report: 1. The council’s Revenue and Capital budgets for 2025/26 were agreed by Full Council on 25 February 2025. This report presents information and analysis to the Strategy and Resources Committee on the council’s financial performance against the approved budget and its forecast use of resources for the financial year 2025/26.

2. Finance reports are to be presented to the Strategy and Resources Committee at periods 2, 5, 8, 10 (summary level) and 12. Other periods constitute exception reporting periods so that a full detailed report will be published when the movement in forecast outturn meets previously agreed criteria or when it is necessary to report finance key decisions which have been made in the intervening period.

3. In addition, this report informs the Strategy and Resources Committee on the delivery of planned savings for the financial year 2025/26.

4. This report also serves as a mechanism for any finance approvals or adjustments that are required on the council’s approved budget.

Evidence Base: 1. The council’s annual revenue and capital budget is managed across a number of areas and at Period 8 (P8) the 2025/26 full year financial forecast is as follows:

1.1General Fund Revenue Budget The original Revenue budget for 2025/26 as approved by Full Council was £571.4 million. The P8 total forecast service variation from its part of the budget is £16.9 million. The corporate directorate is forecasting a £0.4 million favourable variance to budget so that the General Fund’s total net forecast revenue overspend at P8 is £16.5 million (2.9% of the original approved budget). 1 Version January 2024

OFFICIAL This represents an improvement in forecast of £2.2 million since Period 5.

The Budget Management Framework (as noted and supported by Strategy and Resources Committee 19 May 2025) sets out the principle that it is the responsibility of Executive Directors to control income and expenditure within their area and within the cash limited budget allocation delegated to them.

Budget mitigations developed during the first quarter of the year have been built into forecasts. In addition, Directorate level financial recovery plans were implemented following Period 5 reporting. Progress to date against these recovery actions is included in this report (at Appendix A1a, Section 6).

1.2General Fund Risk and Opportunities An underlying additional £3.9 million weighted net opportunity is assessed across the directorates’ logs of outstanding risks and opportunities. These risks and opportunities are a combination of costs, savings delivery, income generation and other funding opportunities. This position has improved by £7.4 million since Period 5 reflecting the progress being made in recovery activity in the past 3 months.

1.3General Fund Savings The total approved budget for 25/26 was a net £42.9 million. This net budget plus undelivered savings carried forward and further business case savings identified and committed to date produce an overall General Fund savings plan target for 2025/26 of £51.3 million. Of this General Fund target, £43.2 million (84%) is currently forecast to be delivered with £8.1 million (16%) at risk of non-delivery in year. Forecast savings delivery has improved by £0.8 million since Period 5.

1.4Housing Revenue Account The Housing Revenue Account (HRA) revised gross expenditure budget of £154.7 million is reporting a net outturn overspend of £0.5 million (0.3%). This position has improved by £0.8 million since Period 5.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Finance Report: P8/Q3Report 145 KB DownloadRead as text
PDF
P08 Appendix A1a: Revenue Budget MonitoringAppendix 343 KB Download
PDF
P08 Appendix A1b: Capital Budget MonitoringAppendix 229 KB Download
PDF
P08 Appendix A2: Children & Young People CommitteeAppendix 211 KB Download
PDF
P08 Appendix A3: Adult Social Care CommitteeAppendix 1.2 MB Download
PDF
P08 Appendix A4: Public Health & Communities CommitteeAppendix 169 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, present
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
NH
Nick HibberdOfficer, in attendance
JS
John SmithOfficer, in attendance
AR
Andy RotheryOfficer, in attendance

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Finance Report: P8/Q3This decision
  2. Q1/P3 Finance update reportNoted
  3. 2026/27 Quarterly Finance Report: P3/Q1Noted
  4. Q1 (P03) Finance UpdateDecided
  5. 2026/27 Quarterly Finance Report: P3/Q1Noted
  6. Finance report updateNoted

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open