Strategy and Resources Policy Committee, Tuesday 20 January 2026 at 2.30pm

Building Practice Health and Safety Capital Programme 2026-27

Approved Committee 4 papers

AI summaryBristol City Council Strategy and Resources Committee unanimously approves £2,527,000 capital budget for 2026-27 building health and safety works, pending full council sign-off in February 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStrategy and Resources Policy Committee, 20 January 2026
Money£2,527,000Capital, funded by prudential borrowing
What happens nextFull Council approvalScheduled for February 2026
Who it affectsCouncil corporate estateBuildings owned and occupied by Bristol City Council

What was decided

Approved the 2026-27 Building Practice Health and Safety Capital Budget allocation of £2,527,000, subject to full council approval in February 2026. Report P7, P12

Authorised the Executive Director of Growth and Regeneration, in consultation with the committee chair, to procure and award contracts, including those over the key decision threshold, to deliver the programme. Report P12

Authorised the Executive Director of Growth and Regeneration, in consultation with the committee chair, to amend scheme budget allocations within the overall approved limit to meet operational need. Report P12

Why

The programme funds essential building repair and maintenance so the corporate estate remains safe and fit for purpose, and the council meets its legal and statutory obligations. Report P3, P5, P19

It helps avoid possible litigation from statutory bodies and meet acceptable health and safety standards for colleagues, partners, building users and visitors. Report P5, P19

The works support corporate priorities including creating safe, healthy neighbourhoods (Priority 3) and accelerating climate action and nature recovery (Priority 5), by improving heating efficiency and insulation, with City Leap as the delivery partner for the carbon neutral estate aim. Report P10, P16, P17

What happens next

Seek full council approval of the £2,527,000 capital allocation in February 2026. Report P12

The Executive Director of Growth and Regeneration, with the committee chair, will procure and award contracts in line with the Procurement Act 2023 and the council's own procurement rules, with legal services advising. Report P29

If assets listed in Appendix A are no longer required, or their use changes, the funds allocated to them will return to the contingency for reallocation to the next priority. Report P11

The money

  • £2,527,000 Total 2026-27 Building Practice Health and Safety Capital Programme including contingency, funded by prudential borrowing Report P7, P25

Implications

  • Legal: Programme supports the council's statutory duty to maintain corporate assets in a safe state and meet legal obligations; any procurement must comply with the Procurement Act 2023 and the council's own procurement rules. Report P5, P19, P29
  • Financial: Funded entirely by £2,527,000 of prudential borrowing; no revenue cost; expenditure is ongoing rather than one-off. Report P25
  • Equalities: An Equality Impact Assessment (Appendix B) accompanies the report; HR advice notes that accessibility, safety, health and wellbeing of workforce and workspace users should be appropriately prioritised. Report P33, P34, P38
  • Climate: Works include more efficient heating technology and improved thermal insulation (roofs, windows, doors, fabric), supporting the council's move toward a carbon neutral estate, with City Leap as delivery partner. Report P10
  • Risk: Ongoing estate rationalisation and future strategic work may change the assets listed; unspent funds on affected assets would return to contingency. No Decision Risk Assessment appendix was provided. Report P11, P40
  • Other: No IT implications identified. Report P31

Who and where

  • Bristol City Council colleagues, partners, building users and visitors using corporate estate buildings Report P19
  • Property, Assets and Infrastructure (PAI) Building Safety Board, PAI DMT, G&R EDM, and CIB members who have been consulted Report P22
  • Senior building surveyors within the Corporate Landlord function Report P6, P9

Timeline

  • 20 January 2026: Strategy and Resources Policy Committee approved the budget allocation unanimously
  • February 2026: Full Council to consider capital budget approval Report P12
  • 2026-27: Programme of essential building repair and maintenance works to be delivered Report P3, P7

Plain English for the jargon

  • Corporate estate: Buildings owned and occupied by Bristol City Council to deliver its services.
  • Prudential borrowing: Borrowing by a local authority to fund capital investment, undertaken under the prudential framework.
  • Key decision threshold: The financial level above which a council decision is treated as a key decision.
  • City Leap: Bristol City Council's delivery partner for work toward a carbon neutral estate.
  • PAI / DMT / EDM / CIB: Internal council forums consulted: Property, Assets and Infrastructure; Directorate Management Team; Growth & Regeneration Executive Director Meeting; Capital Investment Board.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the Committee for Strategy and Resources (unanimous vote in favour): 1. Approved the 2026-27 Building Practice Health and Safety Capital Budget allocation, as set out in this report and Appendix A, subject to Full Council budget approval in February 2026. 2. Authorised the Executive Director of Growth and Regeneration, in consultation with the Chair of the Strategy and Resources Committee, to take all steps required to spend the budget to implement the programme of works in Appendix A including procuring and awarding contracts which may be over the key decision threshold. 3. Authorised the Executive Director of Growth and Regeneration, in consultation with the Chair of the Strategy and Resources Committee, to make amendments to the scheme budget allocations (which may be above the key decision threshold) to meet operational need, providing the programme operates within its approved budget limit.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Purpose of report

1. To seek approval of the 2026-27 Building Practice Health and Safety Capital Programme budget allocation and associated spend.

Evidence Base

1. This budget request is to facilitate an identified programme of essential building repair and maintenance work that ensures our corporate estate remains safe and fit for purpose.

2. Appendix A details the assets and locations which require work, and the type of work and activity required.

3. Appendix A is compiled by focussing on ensuring the council: 1. fulfils legal and statutory obligations, 2. avoids possible litigation from statutory bodies, 3. meets acceptable Health and Safety Standards, 4. provides continued and safe operations of buildings.

4. Appendix A is compiled using three streams of information: 1. Statutory Obligations, 2. Corporate Landlord senior building surveyors’ portfolio knowledge, and 3. Previously unsighted emergency Health and Safety work.

5. The total sum for 2026-27, including contingency, is £2,527,000.

Template approved March 25

OFFICIAL 6. The creation of the programme is based on the knowledge of our senior building surveyors, along with dialogue and engagement with various teams, including the Corporate Landlord Building Safety Board, Statutory Registrations and colleagues across the wider council service areas.

7. The programme aids continuous improvement of the environmental performance of the estate by installing more efficient heating technology and improved thermal insulation to sites through repairs to fabric, roofs, windows and doors. The programme assists supporting the council moving toward a carbon neutral estate, with City Leap as the delivery partner.

8. It is worth noting that the ongoing estate rationalisation programme, and current and future strategic work, may impact on some of the assets listed and, at this moment in time, it is intended that any funds allocated to assets which are subsequently no longer required, or their future use changes, and the Health and Safety action is no longer required, would return to the contingency for reallocation to the next priority.

Officer Recommendations: That the Committee for Strategy and Resources: 1. Approves the 2026-27 Building Practice Health and Safety Capital Budget allocation, as set out in this report and Appendix A, subject to Full Council budget approval in February 2026. 2. Authorises the Executive Director of Growth and Regeneration, in consultation with the Chair of the Strategy and Resources Committee, to take all steps required to spend the budget to implement the programme of works in Appendix A including procuring and awarding contracts which may be over the key decision threshold. 3. Authorises the Executive Director of Growth and Regeneration, in consultation with the Chair of the Strategy and Resources Committee, to make amendments to the scheme budget allocations (which may be above the key decision threshold) to meet operational need, providing the programme operates within its approved budget limit.

Corporate Strategy alignment:

Priority 1: Improving equity of outcomes in education and employment,

Priority 2: Supporting children's, families' and adults' health and wellbeing,

Priority 3: Creating safe, healthy neighbourhoods, and affordable, safe and good quality homes,

Priority 5: Accelerating climate action and nature recovery.

City Benefits:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draft Programme 26-27Appendix A 152 KB Download
PDF
Equality Impact AssessmentAppendix B 103 KB Download
PDF
Environmental Impact AssessmentAppendix C 149 KB Download
PDF
Building Practice Health and Safety Capital Programme 2026-27Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
TD
Councillor Tony DyerChair, present
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, present
HM
Councillor Heather MackCommittee Member, present
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
NH
Nick HibberdOfficer, in attendance
JS
John SmithOfficer, in attendance
AR
Andy RotheryOfficer, in attendance

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Building Practice Health and Safety Capital Programme 2026-27This decision
  2. Building Practice Health and Safety Capital PlanApproved
  3. Building Practice Capital Programme Budget Allocation 2023-2028Approved
  4. Building Practice Capital Programme Budget Allocation 2022-2026Approved
  5. Building Practice Capital Programme Budget Allocation 2021/22Approved
  6. Building Practice Capital Programme Budget 2020/21Approved

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies