Watercourse Maintenance Contract

Approved Committee 6 papers

AI summaryBristol City Council approves eight-year watercourse maintenance contract worth up to £1 million to reduce flood risk, with the Economy and Skills Policy Committee acting unanimously.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEight-year watercourse maintenance contract authorised
MoneyUp to £1 million total£125,000 per year, eight-year term
What happens nextProcurement and award by Executive DirectorIn consultation with committee chair
Who it affectsProperties at flood risk citywideIncluding deprived communities most at risk

What was decided

The committee unanimously approved procuring and awarding an eight-year watercourse maintenance contract, with a maximum budget envelope of £1 million. Report P7, P24

Authority to procure, award and invoke any contract extensions or variations was delegated to the Executive Director of Growth and Regeneration, in consultation with the committee chair. Report P13

All procurement steps must follow the routes and budget limits set out in the report. Report P13

Why

Bristol City Council acts as Lead Local Flood Authority under the Flood and Water Management Act 2010 and has riparian landowner duties under the Land Drainage Act 1991, requiring regular upkeep of watercourses to manage flood risk. Report P3, P4

Internal records show flooding incidents caused by blocked drainage infrastructure, and a lack of maintenance would worsen the problem and increase recovery costs. Report P5

The current contract, valued at £400,000 and running from 04 July 2022 to 03 July 2026, needs replacement with a longer deal to attract bidders, cut officer time on repeated procurement, and reflect rising costs, additional assets, and reduced Environment Agency maintenance. Report P7

What happens next

The Executive Director of Growth and Regeneration will run the procurement and award the contract, following the Procurement Act 2023 and the council's own procurement rules, with legal services advising. Report P13, P28

The contract must include requirements to carry out in-channel vegetation cutbacks outside bird nesting season and to dispose of waste at licensed facilities. Report P9

Any future cost increases must be managed within the approved £1 million budget envelope to avoid budget pressures. Report P25

The money

  • £1M Total contract value sought over eight years Report P7, P24
  • £125,000 Estimated annual cost for watercourse maintenance Report P7, P24
  • £100,000 Annual revenue funding from Flood and Water Management budget (10450) Report P22, P24
  • £25,000 Annual capital funding from existing approved provision (P13520-1001) Report P22, P24
  • £400k Value of the current contract that began 04 July 2022 Report P7

Options considered

  • Chosen: Outsource watercourse maintenance to an external contractor for eight years. Council is not set up with the staff, equipment or training to carry out the work in-house Report P11, P12
  • Rejected: Bring the service in-house. Lack of appropriate staff resources, equipment and training Report P11

Implications

  • Financial: The £1 million total is funded from existing approved revenue and capital budgets, with no savings or income generation. Any future inflationary or other cost increases must be absorbed within the envelope. Report P24, P25, P26
  • Legal: Procurement must follow the Procurement Act 2023 and the council's own procurement rules, with legal services advising on the process and contract. Report P28
  • Equalities: Some of the most frequently maintained areas are within the most deprived communities, where flood risk is higher. Report P17
  • Climate: The proposal supports Corporate Priority 5 on accelerating climate action and nature recovery, by improving resilience to climate impacts and managing land and water for nature. Report P15, P17
  • Staffing: No HR implications identified. Report P31, P32
  • Other: No IT implications identified. Report P30, P31

Who and where

  • Bristol residents and properties at risk of flooding from ordinary watercourses citywide Report P3, P4, P5
  • Residents in the most deprived communities, which include areas with the most frequent maintenance activity Report P17
  • Bristol City Council as Lead Local Flood Authority and riparian landowner Report P3, P4
  • Potential bidders for the maintenance contract Report P7

Timeline

  • 04 July 2022: Current watercourse maintenance contract commenced, valued at £400k Report P7
  • 15 December 2025: Transport Management Team divisional management team meeting Report P19
  • 23 December 2025: Legal and HR advice provided on the report Report P29, P32
  • 6 January 2026: IT advice provided confirming no IT implications Report P31
  • 23 January 2026: Finance business partner comments provided Report P27
  • 4 February 2026: Growth and Regeneration Directorate Management Team meeting Report P19
  • 11 February 2026: Executive Director meeting Report P19
  • 23 February 2026: Policy Committee Chair briefing Report P19
  • 30 March 2026: Economy and Skills Policy Committee approved the proposal unanimously Report P19
  • 03 July 2026: Current contract end date (with scope to extend) Report P7

Plain English for the jargon

  • Lead Local Flood Authority: The council body responsible for managing local flood risk, here Bristol City Council under the Flood and Water Management Act 2010.
  • Ordinary watercourse: A river, stream, drain or ditch that is not designated as a main river, managed by the Lead Local Flood Authority.
  • Riparian landowner: An owner of land next to a watercourse, with responsibilities for the stretch that flows through or under their land, up to the centre line.
  • EqIA: Equality Impact Assessment, an appendix to the report.
  • EIA: Environmental Impact Assessment, an appendix to the report.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

It was RESOLVED that the Committee for Economy and Skills (Unanimously FOR): Approved the proposal. Contractual: Authorised the Executive Director of Growth & Regeneration in consultation with the Chair of the Economy and Skill Committee to take all steps required to procure and award the Watercourse maintenance contract, in-line with the procurement routes and maximum budget envelopes outlined in this report. Authorised the Executive Director of Growth & Regeneration, to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Economy and Skills Policy Committee

Purpose of report

1. To seek approval to procure and award an eight-year contract for conducting routine watercourse maintenance works.

Evidence Base

1. BCC as the Lead Local Flood Authority for its administrative area has responsibilities for managing flood risk and Ordinary watercourses in Bristol under the Flood and Water Management Act (2010). The regular watercourse maintenance works help manage that risk effectively by reducing the chance of flooding. The powers that BCC has under the Land Drainage Act (1991) to carry out works to manage flood risk from surface water and Ordinary watercourses helps fulfil the duties outlined in the Bristol Local Flood Risk Management Strategy (detailed in Background Documents) and specifically Actions 3.0 and 3.1.

2. BCC owns land and property next to watercourses such as rivers, streams, drainage ditches, and over pipes and culverts that makes them a ‘riparian landowner’. As a riparian owner, BCC has certain responsibilities for watercourses flowing through or under council owned land, and up to its centre point where it is on its land boundary. The responsibilities include letting water flow naturally, relieving blockages and obstructions and keeping structures such as debris screens clear. The watercourse maintenance works help cover these riparian responsibilities by regularly maintaining critical flood risk assets, structures and open channel sections. These are required on a weekly to annual basis dependant on the frequency need of that specific feature. The work includes vegetation cutbacks and channel clearances. This is vitally important for the purpose of flood risk management by avoiding blockages, ensuring watercourses are free flowing, and so that flood risk assets continue to fulfil their function properly.

3. There is numerous flooding incidents recorded on our internal BCC records that reported the cause of flooding as down to blockages of drainage infrastructure. This management of watercourses and drainage channels, that is separate to the highway drainage network, is a vitally important pro- active approach to help prevent this occurring. A lack of maintenance will otherwise exacerbate these types of flooding problems even further still. The cost of regular maintenance avoids larger recovery costs and associated repercussions if assets are to fail or if places become flooded. These works help prevent flooding problems occurring throughout the city including offering protection to many properties for Bristol residents.

4. The Bristol Flood Risk Asset Register (referred to in the Background Documents) gives details of the asset locations. Their maintenance needs, with an estimated cost breakdown for undertaking this function, are based on the existing schedule of rates (not to be viewed publicly as they are commercially sensitive) which have been uplifted plus additional features identified. The Strategic Flood Risk Assessment (see also in the Background Documents) and Bristol Local Flood Risk Management Strategy describe the risk of flooding in Bristol and methods for managing this, including watercourse maintenance activities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Watercourse maintenanceAppendix A 5.9 MB Download
PDF
Equality Impact AssessmentAppendix B 186 KB Download
PDF
Environmental Impact AssessmentAppendix C 287 KB Download
PDF
Decision Risk Assessment TemplateAppendix D 271 KB Download
PDF
Options appraisal matrixAppendix G 98 KB Download
PDF
Watercourse Maintenance ContractReport 319 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
AB
Councillor Andrew BrownChair, present
JB
Councillor Jenny BartleVice-Chair, present
DA
Councillor Donald AlexanderCommittee Member, present
FB
Councillor Fabian BreckelsCommittee Member, present
RE
Councillor Richard EddyCommittee Member, present
CH
Councillor Cam HaywardCommittee Member, present
SK
Councillor Susan KollarCommittee Member, present
SR
Councillor Serena RalstonCommittee Member, present
TW
Councillor Toby WellsCommittee Member, present
JS
John SmithOfficer, apologies
AH
Alex HearnOfficer, in attendance
VV
Vik VermaOfficer, apologies

All 14 on the meeting page

More from Bristol Economy and Skills Policy Committee

All decisions
MeetingDecisionOutcome
27 Jul 2026 Minutes of the Previous MeetingRESOLVED; To approve the minutes of the meeting on the 30th March 2026. On the motion of the Chair, seconded by Counc... Approved Open
27 Jul 2026 High Streets Strategy Task and Finish Closure ReportThe Committee for Economy and Skills RESOLVED to: Approve the content of this report and agrees it reflects the findi... Approved Open
27 Jul 2026 Update on funding for the Night Time Economy Advisor positionThe Committee for Economy and Skills noted this report. Noted Open
27 Jul 2026 BNET Business Plan Outline ProposalThe Committee for Economy and Skills RESOLVED to: Note the BNET business plan framework and the continued development... Noted Open
27 Jul 2026 Q1 Corporate Risk Report 26/27The Committee for Economy and Skills noted this report. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies