AI summaryBristol City Council's Economy and Skills Committee has unanimously agreed to negotiate and accept a £5.704m grant from the BNSSG Integrated Care Board to continue as Lead Delivery Partner for the WorkWell West employment support service, Phase 2.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedOfficers to negotiate and accept £5.704m BNSSG funding
Money£5.704m revenue grantFrom BNSSG Integrated Care Board, no capital cost
What happens nextNegotiate, accept and spend the grantLead regional delivery of WorkWell West Phase 2
Who it affectsPeople with health conditions seeking work14 council staff at risk of redundancy if not accepted
What was decided
The committee unanimously authorised the Head of Service Employment, Skills and Learning and the Employment Support Manager to negotiate with BNSSG and, if successful, accept and spend the funding offered, leading on the regional implementation and delivery of the Employment support element of the Work Well West Phase 2 Service. Report P3
Why
Improving employment for people with health conditions supports Bristol's Corporate Strategy commitments on equity of outcomes in education and employment and on health and wellbeing, and fits with the new Neighbourhood Prevention model. Report P5
Accepting the funding allows the council to demonstrate positive action on employing and supporting people with health conditions and to work with other employers on the same agenda. Report P7
What happens next
Officers will negotiate with BNSSG and, if successful, accept the grant and lead regional delivery of the WorkWell West Phase 2 employment support element. Report P3
Any procurement required must follow the 2015 Procurement Regulations and the council's own procurement rules, with legal services advising. Report P15
The money
£5.704m Revenue grant from BNSSG ICB for WorkWell West Phase 2; capital cost nil Report P12
£5.7m Inward investment to the council that would be lost if the grant were not accepted Report P1
Options considered
Rejected: Do not accept the grant. Would cause significant reputational damage, risk redundancy of 14 council staff, and lose £5.7m of inward investment, with BNSSG unable to deliver Phase 2 within DWP timescales Report P1
Implications
Financial: Grant is managed, monitored, reported and claimed quarterly under a defined cost centre; finance sees no issues from the three-year extension. Report P13, P14
Legal: Grant bids raise no particular legal issues, but any procurement must comply with the 2015 Procurement Regulations and the council's own procurement rules. Report P15, P16
Staffing: If the grant is accepted, the existing WorkWell workforce continues and no Management of Change process is needed; if rejected, a Management of Change process would be required. Report P18, P19
Other: No IT implications identified for the activity. Report P17
Who and where
Bristol City Council Employment, Skills and Learning staff delivering WorkWell (14 posts at risk if funding not accepted) Report P1, P18
People with health conditions across Bristol, North Somerset and South Gloucestershire needing employment support Report P5, P9
Partner authorities and VCSE providers working on employment support for people with health conditions Report P9
BNSSG Integrated Care Board and the Department for Work and Pensions (DWP) Report P1, P9
West of England Combined Authority (WECA) Report P9
Timeline
6 February 2026: Legal advice provided by Husinara Jones, Team Manager/Solicitor Report P16
6 February 2026: HR advice provided by Matt Harmer, HR Business Partner Report P19
10 February 2026: IT comment provided by Alex Simpson, Lead Enterprise Architect Report P18
17 February 2026: Finance advice provided by Ben Hegarty, Finance Business Partner Report P14
30 March 2026: Decision taken by Economy and Skills Policy Committee, unanimously
Plain English for the jargon
BNSSG ICB: Bristol, North Somerset and South Gloucestershire Integrated Care Board, the NHS body offering the grant.
WorkWell West: A programme supporting people with health conditions into employment; Phase 1 has run and Phase 2 is the proposed extension.
Lead Delivery Partner: The organisation (here Bristol City Council) responsible for coordinating and delivering the programme regionally.
DWP: Department for Work and Pensions, the UK government department that sets the timescales for the programme.
WECA: West of England Combined Authority, a regional authority partner.
VCSE: Voluntary, Community and Social Enterprise organisations working as delivery partners.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
It was RESOLVED that the Committee for Economy and Skills (Unanimously FOR): 1. Authorised the Head of Service Employment, Skills and Learning and the Employment Support Manager to negotiate with BNSSG and, if successful, to accept and spend the funding offered and lead on the regional implementation and delivery of the Employment support element of the Work Well West Phase 2 Service.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
KEY DECISION OR FOR INFORMATION: Key decision over £500k
COMMITTEE: Economy and Skills Committee
DATE: 30 March 2026
TITLE: WorkWell West Extension Funding
Ward(s): Citywide
Officer presenting the report: Paul Gaunt Job Title: Employment Support Manager
Committee Chair: Councillor Andrew Brown
Executive Director lead: Hannah Woodhouse: Executive Director for Childrens and Education
Proposal origin: BCC Staff
Purpose of Report: To approve the acceptance of a grant from the Bristol, North Somerset and South Gloucestershire Integrated Care Board (BNSSG ICB) of £5.704m for activities relating to the role of Lead Delivery Partner for the WorkWell West service.
Evidence Base
1. WorkWell West is a service that supports people 18+ with recent health conditions who have either lost their job or are at risk of losing it due to their health maintain and thrive in work whilst managing their condition. It provides personalised, early help for people struggling with their health — connecting them to local services such as physiotherapy, counselling and workplace adjustments.
2. WorkWell is a key strand of the Governments Get Britain Working Strategy and Pathways to Work offer, created to help Disabled people and those with health conditions move from welfare into work and provide a joined-up support system for residents. The WorkWell Programme is jointly funded by the Department of Work and Pensions (DWP) and the Department for Health and Social Care (DHSC). Funding flows from DWP and DHSC to NHS Integrated Care Systems in England.
3. The BNSSG ICB and Bristol City Council are working closely with the Combined Authority to ensure that WorkWell West is fully aligned with the regional employment service. WorkWell services are included in the Get West of England Working Plan. They are being developed as part of a strong work and health menu that also includes Skills Connect, Connect to Work and WE Work for Everyone. 4. In May 2024, the Bristol, North Somerset and South Gloucestershire Integrated Care Board, (BNSSG ICB, Lead Accountable Body) and Bristol City Council, (Lead Delivery Partner) successfully applied to the DWP for a grant of £2.3m to become one of the 15 WorkWell Pilot areas within the country. This phase of the programme was to run until 31st March 2026
5. Service delivery commenced October 2024 and to Quarter 3 2025, WorkWell West has supported 1,750 participants across the Bristol, North Somerset and South Gloucestershire ICB area.
6. WorkWell West has been nationally, regionally and locally recognised for the collaborative approach that BNSSG ICB, Bristol City Council and the VCSE supply chain has undertaken to integrate the work and health ecosystems. In November 2025 WorkWell West won the Collaboration category of the South West Regional Personalised Care Awards.
7. BNSSG ICB has received notification from the DWP that WorkWell West will be extended for a further 3 years and we have agreed that Bristol City Council’s Employment Support Team will remain in place as Lead Delivery Partner. BCC will deliver the service on a full cost recovery basis.
8. According to the latest ONS figures, (mid 2022) the BNSSG area has a working age population, (16- 64) of 646,200. In the 23/24 financial year, 44,661 fit notes were written. 6.1% of these individuals were identified as “may be fit for work”. This number is an 1% increase on the 22/23 financial years. Furthermore, 31.6% of fit notes were awarded for a duration of 5 to 12 weeks, the highest of all identified durations. This figure has reduced by percentage point from the previous year. 9. The most prevalent diagnosis was Mental Health Disorder followed by musculoskeletal, diseases of the respiratory system, symptoms signs and abnormal clinical / laboratory findings, injury, poisoning and certain other consequences of external causes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingRESOLVED; To approve the minutes of the meeting on the 30th March 2026. On the motion of the Chair, seconded by Counc...
BNET Business Plan Outline ProposalThe Committee for Economy and Skills RESOLVED to: Note the BNET business plan framework and the continued development...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.