Strategy and Resources Policy Committee, Monday 13 April 2026 at 2.00pm

Q4 Corporate Risk Report

Noted Committee 1 paper

AI summaryBristol City Council's Strategy and Resources Committee noted the Q4 2025/26 Corporate Risk Report, which lists 14 strategic risks and identifies two as critical: housing stock condition and highways infrastructure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQ4 2025/26 Corporate Risk Report
MoneyNot stated
What happens nextQ1 2026/27 review of static risksCLB to sign off revised Risk Management Assurance Policy
Who it affectsBristol City Council and residentsRisks cover housing, highways, safeguarding, finance

What was decided

The Committee noted the Q4 2025/26 Corporate Risk Report, which summarises significant strategic risks to the Council's objectives. Report P57

Why

The Council's Risk and Assurance Policy requires the Corporate Leadership Board and relevant Policy Committees to carry out quarterly reviews of corporate risks. Report P26

The report provides assurance that significant risks have been identified and arrangements are in place to mitigate them to agreed tolerance levels. Report P28

What happens next

In Q1, risk owners will be challenged on the static nature of 10 risks that have not changed score for three or more reporting periods. Report P45

The revised Risk Management Assurance Policy is ready for sign-off by the Corporate Leadership Board in Q4. Report P47

A new online risk management training course for officers and managers is due to go live in March 2026. Report P50

Options considered

  • Chosen: Note the Q4 Corporate Risk Report. Recommended by officers; standard quarterly review under the Risk and Assurance Policy. Report P57, P26

Implications

  • Risk: Two critical risks (score 28): HRA stock failing landlord and consumer standards, and inability to maintain highway, traffic, parking and docks infrastructure. Report P39, P20, P18
  • Risk: Five high-scoring risks (score 21) include safeguarding for children and adults, adult social care financial sustainability, Building Safety Act compliance, and Dedicated Schools Grant statutory instrument ending after March 2028. Report P10, P11, P16, P17, P19
  • Risk: One risk improved in Q4: emergency planning response team capacity reduced from 21 to 15. Report P40
  • Risk: One risk de-escalated: CRR63 on insurance and risk arrangements (score 10) removed from the corporate register after agreement it had been managed to an acceptable level. Report P42
  • Other: A proof-of-concept programme is underway to move towards enterprise risk management, with engagement of Pentana/Ideagen to improve the risk management system. Report P48, P49
  • Other: No risks were recommended for escalation to the Corporate Risk Register and no materialised risks were identified during Q4. Report P41, P43

Who and where

  • Bristol City Council tenants (HRA stock condition and Building Safety Act compliance risks) Report P20, P17
  • Road, traffic, parking and docks users (highways infrastructure risk) Report P18
  • Vulnerable children and adults (safeguarding risks) Report P10, P11
  • Adult social care service users and council taxpayers (ASC financial sustainability risk) Report P16
  • Schools and pupils (DSG statutory instrument risk after March 2028) Report P19

Timeline

  • 9 December 2025: Date of last CLB risk review before this report Report P26
  • March 2026: New online risk management training course due to go live Report P50
  • Q1 2026/27: Risk owners to be challenged on the static nature of unchanged risks Report P45
  • 5 March 2026: Executive Directorate members reviewed all risks to form the current CRR Report P34
  • 9 March 2026: Resources EDM noted the CRR; date of the Q4 Corporate Risk Report Report P35, P46

Plain English for the jargon

  • CRR: Corporate Risk Report, the council's record of significant strategic risks
  • CLB: Corporate Leadership Board, the council's senior management team
  • HRA: Housing Revenue Account, the council's landlord housing finances
  • DSG: Dedicated Schools Grant, government funding for schools
  • ASC: Adult Social Care
  • MTFP: Medium Term Financial Plan
  • EDM: Executive Director Meeting, a directorate-level governance forum
  • SRR / DRR: Service Risk Register and Directorate Risk Report, lower-level risk records feeding into the CRR
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

That the Strategy and Resources Committee noted the report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Strategy and Resources Policy Committee

Non-key Decision Committee Report

PURPOSE: Non-key decision update report

COMMITTEE: Strategy and Resources Committee

DATE: 13 April 2026

TITLE: Q4 2025/26 Corporate Risk Report Officer presenting the report: Aldo Zanetti Title: Risk Manager

Executive Director lead: Andy Rothery, Executive Director Resources (S151)

Purpose of Report: The report provides an update on current significant strategic risks to achieving the Council’s objectives as set in the Corporate Strategy 2025-2030 and summarises progress in managing the risks and actions being taken as at Q4 2025-26.

Fig1 – Q4 Corporate Risk Register

Q3 Q4 Corporate Risk Owner Score Direction Score Direction CRR7 Potential Cyber Security Incident Director - Legal & 15 15 Democratic Services

CRR9 Possible failure of Safeguarding vulnerable Director - Children and 21 21 children Families

CRR10 Possible failure to apply effective Adult Director - Adult Social 21 21 Safeguarding Care

CRR12 Emergency Planning Response Team ability to Director - Management 21 15 prepare for and respond to emergencies / incidents of Place could be overwhelmed

CRR13 Possible Financial Framework and Medium Director - Finance 15 15 Term Financial Plan (MTFP) Failure

CRR15 Possible In-Year Financial Deficit Director - Finance 15 15 CRR37 Failure to successfully implement the Tackling Director - Housing & 15 15 Homelessness Programme Landlord Services

CRR43 Possible failure to deliver City Regional Director - Economy of 15 15 Sustainable Transport Settlement 1 by March 2027 Place

CRR51 ASC may be financially unsustainable due to Director - Adult Social 21 21 national and local pressures, leading to a failure to Care deliver statutory duties

CRR52 Failure to manage and evidence compliance Director - Housing & 21 21 with the Building Safety Act 2022 obligations in HRA Landlord Services stock

CRR58 Unable to adequately maintain and replace the Director - Management 28 28 Highway, Traffic, Parking and Docks infrastructure of Place assets

CRR62 Risk that the Statutory Instrument (2020/1212 Director - Education 21 21 and 2022/1328) related to the Dedicated Schools Grant and Skills (DSG), which ringfences the deficit to the DSG is not extended beyond March 2028

CRR60 Failure of HRA stock to meet landlord statutory Director - Housing & 28 28 obligations, the decent homes standard and consumer Landlord Services standards

CRR61 Failure to manage the requirements set out Director - Workforce & 10 15 under the Construction Design Management framework Change

Fig 2 Risk Direction Key

1 Direction Description The risk rating has improved from the previous quarter, having reduced in its severity. The risk rating has deteriorated from the previous quarter, having increased in its severity.

The risk rating has not changed from the previous quarter.

Evidence Base / Context

1. Council’s Risk and Assurance Policy requires the Corporate Leadership Board (CLB) and relevant Policy Committee(s) to perform quarterly reviews of our Corporate Risks. Where possible, quarterly reporting periods are aligned with financial year calendar, however it is not always possible to achieve this alignment. The risk review for Q4 2025/26 reports on risk activity since the 9 December 2025, being the date of the last CLB risk review.

2. The Corporate Risk Report (CRR) is a key document in the council’s approach to the management of risk; it captures strategic risks set out in the Corporate Strategy 2025-2030. It also provides a context on how Directorates perform their high-level risk assessments and is used to inform business planning, budget setting, transformation, and service delivery.

3. The CRR provides assurance to management and Members that Bristol City Council’s significant risks have been identified, and arrangements are in place to mitigate risks to agreed tolerance levels. It should be noted that ‘risk,’ by definition, includes both threats and opportunities, which is reflected in the CRR.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q4 Corporate Risk ReportReport 326 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
TD
Councillor Tony DyerChair, apologies, sent representative
SC
Councillor Sarah ClassickVice-Chair, present
KB
Councillor Kelvin BlakeCommittee Member, present
TB
Councillor Tom BlenkinsopCommittee Member, present
JG
Councillor John GoulandrisCommittee Member, present
EK
Councillor Ellie KingCommittee Member, apologies, sent representative
HM
Councillor Heather MackCommittee Member, present
PM
Councillor Patrick McAllisterCommittee Member, present
AT
Councillor Ani TownsendCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present as substitute
SJ
Councillor Shona JemphreyCommittee Member, present as substitute
NH
Nick HibberdOfficer, expected

All 18 on the meeting page

On this subject at Bristol

Search all
  1. Q4 Corporate Risk ReportThis decision
  2. Q2 Corporate Risk Report 26/27Noted
  3. Q2 Corporate Risk Report 26/27Noted
  4. Q1 Corporate Risk Report 2026/27Noted
  5. Corporate Risk Report Q1 26/27Noted
  6. Q1 Corporate Risk Report 26/27Noted

More from Bristol Strategy and Resources Policy Committee

All decisions
MeetingDecisionOutcome
12 Oct 2026 Medium Term Financial Strategy and Capital Strategy 2027-28That the Committee for Strategy and Resources: 1. Noted the outlook and projections within the Medium Term Financial ... Noted Open
12 Oct 2026 Social Value Task and Finish GroupThat the Strategy and Resources Policy Committee noted the report and approved the recommended approach in the Terms ... Noted Open
12 Oct 2026 Private Water DistributionThat the Committee for Strategy and Resources: 1. Approved the approach taken to manage this area of emerging risk. 2... Approved Open
12 Oct 2026 Procurement of Display, Exhibition and Signage ServicesThat the Committee for Strategy and Resources: 1. Approved the procurement of a multi-supplier framework for Display,... Approved Open
12 Oct 2026 Arts Council England’s National Portfolio Organisation Funding Round 2028 – 2033That the Committee for Strategy and Resources: 1. Approved the proposal for Bristol Museums and Museum Development So... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies