Bristol City Council
Harbour Committee, Tuesday 15 September 2026

Harbour Asset Management Plan 2026 - 2031

Approved Committee 4 papers

AI summaryBristol Harbour Committee approved the 2026-2031 Asset Management Plan, committing to planned maintenance and seeking £6.36 million per annum capital investment to replace reactive upkeep of harbour infrastructure.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThe Committee approved the Harbour Asset Management Plan, the Asset Stabilisation Programme, and endorsed developing a 5-year and 20-year capital investment strategy
Money£6.36m per annum capital, £651k rising to £1.03m revenue. Capital cost of £6,355,000 per annum plus revenue costs from £651,000 increasing to £1,029,000, against a long-term lifecycle requirement of £8.0 to £10.0 million per annum
What happens nextCouncil approval neededThe plan is subject to Bristol City Council approval and funding; future business cases required to secure investment
Who it affectsHarbour infrastructure users and commercial tenantsNavigation, transport, tourism and commercial income streams from harbour estate assets

What was decided

The Committee approved the Harbour Asset Management Plan 2026 to 2031.

The Committee approved the continued delivery of the Asset Stabilisation Programme 2026 to 2028.

The Committee authorised the Executive Director Growth and Regeneration, in consultation with the Committee Chair, to develop and bring forward a 5-year and 20-year capital investment strategy.

Why

The do nothing option and continued reactive approach was rejected because of escalating safety risks, increased failure rates, and higher long-term costs. Report P1

Full immediate capital investment was not recommended due to funding constraints and duplication risk where Environment Agency investment is planned. Report P3

The preferred option of targeted stabilisation with strategic alignment balances affordability, risk management and alignment with external flood defence investment. Report P4

What happens next

Implementation of the Harbour Asset Management Plan is subject to Bristol City Council approval and Council funding.

Future business cases will be required to secure an estimated £6 to £10 million per annum of capital investment together with ongoing revenue funding requirements.

The transition from reactive to planned maintenance and implementation of the Confirm asset management system will be progressed.

The money

  • £651,000 Initial revenue cost increasing to £1,029,000 Report P15
  • £6,355,000 Capital cost per annum Report P16
  • £6 to £10 million per annum Estimated capital investment requirement
  • £8.0 to £10.0 million per annum Long-term lifecycle requirement Report P19
  • circa £1.0 billion Harbour asset base replacement value Report P22

Options considered

  • Rejected: Do nothing / continue reactive approach. Escalating safety risks, increased failure rates, and higher long-term costs Report P1
  • Rejected: Full immediate capital investment. Funding constraints and duplication risk where Environment Agency investment is planned Report P3
  • Chosen: Targeted stabilisation with strategic alignment. Balances affordability, risk management and alignment with external flood defence investment Report P4

Implications

  • Financial: Significant affordability gap exists between current maintenance funding and estimated long-term lifecycle requirement of £8.0 to £10.0 million per annum, presenting a key financial risk Report P19
  • Financial: Finance advises the report does not currently provide detailed financial appraisal of estimated £8.0 to £10.0 million future capital requirement, affordability assessment, cashflow profile, funding strategy, or quantified income protection benefits Report P21
  • Financial: Delivery of the HAMP remains dependent on future council approvals, availability of capital resources and successful development of robust business cases Report P20
  • IT: Implementation of Confirm asset management system will require governance, asset data onboarding, migration of legacy records, user training, operational support arrangements, and consideration of licensing and support costs Report P30
  • Legal: Ongoing contracts associated with continued delivery of Asset Stabilisation Programme should be managed in accordance with terms and conditions; new works or services should be procured in compliance with the Procurement Act 2023 Report P27
  • Risk: Finance recommends the 5-year and 20-year investment strategies include comprehensive asset investment model, prioritised programme of works, funding options appraisal, sensitivity analysis, and assessment of consequences of deferred maintenance Report P22

Who and where

  • Harbour infrastructure users including navigation, transport and tourism Report P9
  • Commercial tenants of harbour estate assets Report P9
  • Environment Agency Report P10
  • Bristol Port Company Report P10
  • Historic England and statutory regulators Report P10

Timeline

  • 2026 to 2031: Harbour Asset Management Plan period
  • 2026 to 2028: Asset Stabilisation Programme delivery
  • 26 June 2026: Legal Team Manager report date Report P28
  • 27 July 2026: Finance Business Partner report date Report P25

Plain English for the jargon

  • HAMP: Harbour Asset Management Plan
  • ASP: Asset Stabilisation Programme
  • AMP: Asset Management Plan
  • Confirm: Asset management system used by the council for asset information and maintenance management
  • EA: Environment Agency
  • Corporate Investment Board: Council body that approves capital funding bids
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10

Resolved

At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso Tshabalala The Committee RESOLVED unanmously: That the Harbour Committee: 1. To Approve the Harbour Asset Management Plan (2026–2031). To Approve the continued delivery of the Asset Stabilisation Programme (2026–2028). To Authorise the Executive Director Growth and Regeneration, in consultation with the Committee Chair, to develop and bring forward a 5-year and 20-year capital investment strategy. To Note that implementation of the Harbour Asset Management Plan is subject to Bristol City Council approval and Council funding, and that future business cases will be required to secure an estimated £6–10 million per annum of capital investment together with ongoing revenue funding requirements. To Endorse the transition from reactive to planned maintenance and implementation of the Confirm asset management system.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Alternative options considered

1. Do nothing / continue reactive approach – Rejected due to escalating safety risks, increased failure rates, and higher long-term costs.

Template approved October 25

OFFICIAL 2. Full immediate capital investment – Not recommended due to funding constraints and duplication risk where Environment Agency investment is planned.

3. Targeted stabilisation with strategic alignment (preferred option) – Balances affordability, risk management and alignment with external flood defence investment.

Officer Recommendations: That the Harbour Committee: 1. Approves the Harbour Asset Management Plan (2026–2031). 2. Approves the continued delivery of the Asset Stabilisation Programme (2026–2028). 3. Authorises the Executive Director Growth and Regeneration, in consultation with the Committee Chair, to develop and bring forward a 5-year and 20-year capital investment strategy. 4. Notes that implementation of the Harbour Asset Management Plan is subject to Bristol City Council approval and Council funding, and that future business cases will be required to secure an estimated £6–10 million per annum of capital investment together with ongoing revenue funding requirements. 5. Endorses the transition from reactive to planned maintenance and implementation of the Confirm asset management system.

Corporate Strategy alignment:

1. Supports safe, sustainable and resilient infrastructure across the city. 2. Contributes to economic growth by maintaining navigation and protecting harbour-related commercial activity. 3. Aligns with climate resilience objectives through coordination with the Environment Agency Flood Risk Programme

City Benefits:

1. Improved public safety through reduced asset failure and enhanced inspection regimes. 2. Enhanced resilience of critical infrastructure supporting transport, navigation and tourism. 3. Protection and growth of commercial income streams from harbour estate assets. 4. Positive impacts on sustainability through lifecycle planning and alignment with flood risk management. 5. Supports equalities by maintaining access to safe public waterfront and infrastructure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Harbour Asset Mngt Plan 2026Appendix A 649 KB Download
PDF
Equality Impact Assessment: Asset Mngt Plan: (completed)Appendix B 131 KB Download
PDF
Environmental Impact Assessment: Asset Mngt Plan: (completed)Appendix C 153 KB Download
PDF
Harbour Asset Management Plan 2026: 2031Report 133 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AB
Councillor Andrew BrownChair, present
ST
Councillor Sibusiso TshabalalaVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, apologies
KD
Councillor Kye DuddCommittee Member, present
RE
Councillor Richard EddyCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
PM
Councillor Patrick McAllisterCommittee Member, present
KD
Kathryn DavisCo-Optee, apologies
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
CB
Cliff BrandCo-Optee, present
JS
John SmithOfficer, expected

All 18 on the meeting page

On this subject at Bristol

Search all
  1. Harbour Asset Management Plan 2026 - 2031This decision
  2. Critical Assets Harbour River Wall Asset - Remedial WorksNoted

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Harbour Master ReportAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open