Harbour Committee, Tuesday 15 September 2026

Harbour Master Report

Noted Committee 3 papers

AI summaryBristol Harbour Committee notes quarterly report on operations and infrastructure, with aging assets requiring significant future capital investment

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe Harbour Committee noted the contents of the Harbour Master Report covering April to June 2026
MoneyNo expenditure or funding was approved; the report was for information only
What happens nextAsset Management Policy and PlanAn Asset Management Policy and Plan covering April 2026 to April 2031 has been submitted for approval
Who it affectsHarbour users and residentsInfrastructure issues including Pero's Bridge closure, Bathurst Basin pontoon defects and lock gate deterioration affect navigation, mooring capacity and flood protection

What was decided

The Harbour Committee noted the Harbour Master's Report including operational performance, risks and mitigation measures. Report P60

The Committee endorsed the continued delivery of the Harbour Authority's risk-based asset management and capital investment programme. Report P61

The Committee supported ongoing engagement with partners including the Environment Agency and Bristol Water in relation to infrastructure resilience and regulatory compliance. Report P61

Why

The report provides an update on operational activity, marine safety, engineering, capital projects, moorings and performance across Bristol Harbour for the period April to June 2026. Report P1

The Harbour Authority's activities support the Corporate Strategy by maintaining safe, resilient and sustainable infrastructure, enabling economic activity and supporting regeneration across the city's waterfront. Report P63

The report highlights increasing financial risks associated with the condition of critical harbour infrastructure including locks, sluices, bridges and flood defence assets which will require significant future capital investment. Report P72

What happens next

Contract award for Underfall Yard sluice repairs is targeted for October 2026 with completion forecast December 2027. Report P46

A programme of work is being developed to action the recommendations from the Water Safety Review. Report P56

Strategic partners are being appointed to support long-term asset management planning with a risk-based approach. Report P49

Options considered

  • Rejected: No alternative options were presented. The report states N/A for alternative options considered as the report was for information only and did not seek approval for expenditure or funding. Report P58, P72

Implications

  • Financial: Increasing financial risks are associated with the condition of critical harbour infrastructure, including locks, sluices, bridges and flood defence assets, which will require significant future capital investment and remain subject to funding uncertainty. Report P72
  • Risk: Operational resilience remains under pressure due to ageing infrastructure, with resources focused on maintaining safe operation while progressing longer-term investment plans. Report P42
  • Risk: A restricted operating regime remains in place for the Entrance Lock including reduced speeds to manage risk until a long-term solution is confirmed. Report P42
  • Legal: New contracts should be procured in accordance with the Procurement Act 2023 and the council's procurement rules, with legal consulted if contracts require variation. Report P74
  • Risk: Pero's Bridge will remain closed to both pedestrians and navigation vessels until the span is recovered and assessed following the incident on 13th August 2026. Report P46
  • Staffing: The Project Manager working with the Harbour Team, David Towns, will retire at the end of July, and recruitment has continued including appointment of two full time Marine Services Officers. Report P41

Who and where

  • Berth holders at Bathurst Basin Report P10
  • Mariners affected by Pero's Bridge closure Report P46
  • Ferry passengers using the City Centre ferry landing by the Cascade Steps Report P47
  • Approximately 39 vessels on the mooring waiting list Report P38
  • Over 100 properties protected by Underfall Yard flood defences Report P46

Timeline

  • 17 December 2025: Aids to navigation at Portishead Dock and Cumberland Basin were last inspected by Trinity House and found to be in good and efficient order. Report P14
  • April 2026: A failure of a sluice pin during April resulted in significantly reduced operational capacity at the Entrance Lock, with intensive engineering works over a 48 hour period restoring two sluices. Report P16
  • April 2026 to April 2031: The Asset Management Policy and Plan covers this five-year period. Report P49
  • 13 August 2026: During preparatory work for planned maintenance, an incident occurred with Pero's Bridge resulting in the span being unable to return to its normal operating position. Report P46
  • October 2026: Contract award for Underfall Yard sluice repairs is targeted, with works programmed to commence at Netham Lock. Report P46, P47
  • December 2027: Underfall Yard sluice and culvert repairs are forecast for completion.
  • 2027/28: Capital funding is anticipated for Netham Weir and Sluices inspection and repair works, and for Junction Lock and Bridge inspection and repair works. Report P46, P49

Plain English for the jargon

  • MEICA: Mechanical, Electrical, Instrumentation, Control and Automation systems used in harbour infrastructure
  • MSMS: Marine Safety Management System implemented in accordance with the Port Marine Safety Code
  • MAIB: Marine Accident Investigation Branch
  • HSE: Health and Safety Executive
  • AtoN: Aids to Navigation
  • CAPEX: Capital Expenditure
  • OPEX: Operational Expenditure
  • CAT 5 protection: Category 5 level protection for water supply to prevent backflow in harbour environments
  • Western Harbour: A programme identifying infrastructure investment needs including Netham Weir, Sluices and Junction Lock
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

At the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the contents of the report.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Harbour Committee

Purpose of report

To provide the Harbour Committee with an update on operational activity, marine safety, engineering, capital projects, moorings and performance across Bristol Harbour for the period April 2026 – June 2026.

Evidence Base

Template approved October 25

OFFICIAL 1. Harbour Operations 1.1 Marine Safety Management System (MSMS)

The Marine Safety Management System continues to be implemented in accordance with the Port Marine Safety Code, with a focus on risk control, assurance and continuous improvement.

1.2Marine Risk Assessment

The following marine risk assessments were reviewed during this period, Large Towage Risk Assessment and Ship Assist Tow Risk Assessment. No new hazards were identified, the existing controls were found to be effective and no changes were required.

1.3Incident Reporting & Investigation

Operational incidents during the period were typical of a busy harbour environment and were managed in accordance with MSMS procedures. These included minor vessel collisions, persons entering the water, and small craft incidents, all of which were investigated with learning points captured. None were reportable to either the MAIB or the HSE.

Bathurst Basin Pontoon The Bathurst Basin spine pontoon was taken out of service following an inspection which identified structural defects requiring further repair and replacement. Working with the Cabot Cruising Club and other stakeholders, all berth holders were safely relocated to safe moorings. However, this reduced available berthing capacity and has required careful coordination and communication. With the completion of “Harbour-fest” , the ponttons used for the event have been re-purposed to refit Bathurst Basin. Work continues with Procurement Process to replace these pontoons prior to next event.

Bathurst Basin Pontoons being replaced.

1.4Conservancy Duty Template approved October 25

OFFICIAL Hydrography & Dredging Dredging of the Feeder Canal has been completed, with operations progressing into the Floating Harbour and Cumberland Basin, with our contractor Baylo Marine.

Aids to Navigation Aids to navigation remained operational and subject to routine inspection, as per Merchant Shipping Act, 1995, Section 198(1). Trinity House as the Lighthouse Authority, advise that the local aids to navigation under the management of Bristol City Docks at Portishead Dock & Cumberland Basin were last inspected on 17/12/2025 by an Officer of Trinity House and were found to be in good and efficient order. Please see the list of active AtoN below: -

The next table details the availability for the last 3 years: -

Entrance Lock & Sluices – Operational Event A failure of a sluice pin during April resulted in significantly reduced operational capacity, with only one sluice initially operational, this caused constrained operations, particularly during neap tides. Contingency arrangements were considered for whilst waiting for long term replacement but were not sustainable for routine operations. Therefore, following intensive engineering works over a 48hr period, Two sluices were restored, enabling a return to operational service levels and further works were scheduled to increase resilience ahead of peak periods.

This was only achieved due to the hard work and ability to produce quick, safe technical solutions by the Harbour Engineer team.

1.5Management of Navigation

Template approved October 25

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Agenda item 7: additional information: Harbour Stakeholder Group updateAgenda 94 KB Download
PDF
Equality Impact Assessment: Harbour Master rpt Sept 26Appendix B 98 KB Download
PDF
Harbour Master ReportReport 6.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 18 attended
AB
Councillor Andrew BrownChair, present
ST
Councillor Sibusiso TshabalalaVice-Chair, present
AT
Councillor Ani TownsendCommittee Member, apologies
KD
Councillor Kye DuddCommittee Member, present
RE
Councillor Richard EddyCommittee Member, present
TR
Councillor Tim RippingtonCommittee Member, present
PM
Councillor Patrick McAllisterCommittee Member, present
KD
Kathryn DavisCo-Optee, apologies
AB
Andy BrigdenCo-Optee, present
KM
Kevin MowatCo-Optee, present
CB
Cliff BrandCo-Optee, present
JS
John SmithOfficer, expected

All 18 on the meeting page

On this subject at Bristol

Search all
  1. Harbour Master ReportThis decision
  2. Harbour Master ReportNoted
  3. Harbour Master reportNoted
  4. Harbour Master ReportDecided
  5. Harbour Master ReportNoted
  6. Western Harbour Master Plan and Infrastructure Delivery PlanAgreed

More from Bristol Harbour Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Ports & Marine Facilities Safety Code, Bristol City Docks - Audit 2025At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Noted Open
15 Sep 2026 Harbour Asset Management Plan 2026 - 2031At the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Bristol City Docks Marine Safety PlanAt the conclusion of the discussion, the Chair moved the report recommendations. This was seconded by Cllr Sibusiso T... Approved Open
15 Sep 2026 Finance report updateAt the conclusion of the discussion, the Chair moved the report recommendations. The Harbour Committee noted the cont... Noted Open