Procurement of Highway Condition and AI Digital Safety Inspections Contracts
DecidedCommittee3 papers
AI summaryBristol Transport Committee approved procurement of a £1,000,000 four-year Highway Condition and Digital Safety Inspections contract to replace two existing contracts expiring in 2027.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedProcurement and award of Highway Condition and Digital Safety Inspections Contract authorised
Money£1,000,000 over 4 yearsApproximately £250,000 per year from July 2027 to July 2031
What happens nextContract awardedExisting contracts expire in 2027; new contract expected to start July 2027
Who it affectsHighway maintenanceRoad and footway condition surveys, safety inspections, lifecycle modelling and streetworks monitoring
What was decided
Authorised the Executive Director for Growth and Regeneration in consultation with the Chair of the Transport and Connectivity Committee to procure and award the Highway Condition and Digital Safety Inspections Contract within the maximum budget envelopes. Report P29
Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions or variations specifically defined in the contract, up to the maximum budget envelope. Report P30
Why
Two existing contracts, both with Gaist as the supplier, expire in 2027 and need replacing. Combining them into a single contract will improve value for money and provide more accurate information on road and footway condition. Report P4, P7, P11
The contract is required to meet statutory duties under Section 41 of the Highways Act 1980, provide data for Department for Transport annual reporting, and support lifecycle modelling and preventative maintenance programmes. Report P2, P18, P49
Failure to procure could result in Bristol being unable to secure full Department for Transport funding and would increase the risk of litigation. Without suitable inspection processes the authority could not rely on its statutory S.58 defence. Report P18, P23
What happens next
Proceed with procurement in line with the procurement routes and maximum budget envelopes outlined in the report, engaging with IT and Equalities and Inclusion teams. Report P19, P29
Manage any assumptions regarding future income recovery associated with Streetworks monitoring separately; such income should not be relied upon to fund the core contract unless evidenced and realised. Report P45
The money
£1,000,000 Total estimated contract value over 4 years Report P9, P43
£250,000 per year Approximate annual cost Report P9, P43
£107,500 per year Condition Survey, Lifecycle Modelling and Scheme Identification Element Report P9, P43
£67,500 per year SafetyView Driven Inspection Element Report P9, P43
£75,000 per year Streetworks Inspection development Report P9, P43
Options considered
Chosen: Approve the procurement. Meets statutory requirements, replaces expiring contracts, improves value for money, and supports DfT funding Report P1, P11, P18
Rejected: Do not approve the procurement. Existing contracts expire in 2027; failure would result in inability to meet statutory obligations, loss of DfT funding up to 25% of Integrated Transport Block, and inability to rely on statutory S.58 defence against third party claims Report P22, P23, P24
Implications
Financial: Estimated £1.0 million over four years from existing approved highways budgets. Financial risks include inflationary pressures, implementation costs, supplier performance, and changes in funding availability. Report P43, P46
Legal: Contract necessary to meet statutory reporting requirements to the Department for Transport and duties under Section 41 of the Highways Act. Should be procured via compliant Public Contract Regulations 2015 or Procurement Act 2023 framework. Report P49
Risk: Failure to procure could result in loss of DfT funding and increased risk of litigation. Driven inspections reduce risk to highway staff by minimising direct exposure to traffic. Report P18, P23
Other: Proposal supports Corporate Strategy Priority 4: Making it easier, greener and safer to travel into and around Bristol. Uses data-led asset management and innovative technologies. Report P32, P34
Who and where
Highway maintenance teams and operational staff Report P23
Department for Transport (funding allocation) Report P18, P24
Residents and highway users (road and footway safety) Report P2, P34
2019: Bristol City Council transitioned from SCANNER survey technology to Gaist survey technology Report P4
2027: Two existing contracts with Gaist expire; new contract expected to start Report P7, P43
July 2027 to July 2031: Duration of new four-year contract Report P43
Plain English for the jargon
PAS2161: DfT standard for road condition surveys enabling reliable benchmarking across local authority highway networks
SCANNER: Previous survey technology replaced due to reliability concerns in urban environments with 20mph speed limits
Gaist: Current survey technology supplier; provides carriageway and footway condition surveys
Lifecycle modelling: Forecasting of network condition over 25 years to model various funding scenarios and support maintenance planning
S.41 Highways Act 1980: Statutory duty requiring councils to maintain highways at public expense
S.58 Highways Act: Statutory defence against third party claims requiring suitable inspection processes and systems
Fixed Penalty Notices (FPNs): Penalties issued to statutory undertakers who overrun authorised works duration or fail to comply with requirements
Streetworks: Works carried out by statutory undertakers on the highway
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in consultation with Chair of the Transport and Connectivity Committee to procure and award the Highway Condition and Digital Safety Inspections Contract, in-line with the procurement routes and maximum budget envelopes outlined in the report. 2. Authorised the Executive Director for Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract being awarded, up to the maximum budget envelope outlined in the report.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Transport & Connectivity Policy Committee
Purpose of report
1. To seek approval to procure and award a new Highway Condition and Digital Safety Inspections Contract to carry out three functions:
a) Annual surveys of the carriageway and footway condition to inform our preventative maintenance and surfacing programmes meet statutory reporting requirements from the Department for Transport (DfT) b) Using the annual condition survey data alongside other metrics to undertake lifecycle modelling of highway assets. c) Monthly driven surveys of the highway network to identify safety critical defects so we can meet our statutory requirements under Section 41 of the Highways Act and keep the travelling public safe.
Evidence Base
This report sets out the need to procure a new digital highway survey and inspection contract to replace two existing contracts due to expire in 2027. Combining these two existing contracts into a single contract will improve value for money, provide more accurate information on road and footway condition, support effective maintenance planning, and help secure government funding. Bristol City Council moved from SCANNER survey technology to our current Gaist survey technology in 2019 following concerns about SCANNER's reliability in urban environments. We ran comparative studies identifying inconsistencies that highlighted SCANNER could both overstate and understate network condition in an urban environment with a majority 20mph speed limit. The transition to Gaist improved the accuracy of condition assessments, although it reduced comparability with authorities using different methodologies. The forthcoming adoption of PAS2161 by the DfT is therefore
Template approved October 25
OFFICIAL welcomed as a consistent national standard that will enable more reliable benchmarking and analysis across local authority highway networks.
1. Replace the two existing contracts, both with Gaist as the supplier, for Road and Footway Condition Survey and Safety View Driven Inspections, both of which expire in 2027, under a single contract.
2. Current arrangement is a direct award using the external Blackpool RAMS framework
3. The estimated value of the contract is approximately £1,000,000 over 4 years, approx. £250,000 per year, broken down as: a. Condition Survey, LifeCycle Modelling and Scheme Identification Element: £107,500 per year b. SafetyView Driven Inspection Element: £67,500 per year c. Streetworks Inspection development: £75,000 per year
4. Estimated costs are based on the existing 2022/2023 contract rates plus inflation with contingency for development projects. All estimated costs include IT hosting and system access, support and development.
5. We wish to procure the existing two contracts together to maximise value for money and secure savings. The monthly driven survey imagery can be used to inform the annual condition survey creating a more accurate representation of the network condition.
6. Lifecycle modelling provides us with an accurate forecast of the network into the next 25 years and can model various funding scenarios. This has been essential in securing additional highway funding and demonstrating to decision makers the situation of our highway network.
7. Scheme identification using the condition surveys and lifecycle modelling helps to inform us of the best sites for preventative and surfacing in our maintenance annual programme. Data shows us this informative method of selecting sites has slowed the overall decline in condition of the network over recent years and ensures we spend funding where it is needed the most.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Transport & Connectivity Policy Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.