CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bristol City Council
Transport & Connectivity Policy Committee, Thursday 17 September 2026

Supported Bus Services Task and Finish Group

Agreed Committee 2 papers

AI summaryBristol council committee sets up task force to plan how to spend up to £4M of Clean Air Zone income and future Workplace Parking Levy funds on supported bus services.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNine councillors will examine how to spend available funding on enhanced bus services, reduced fares and infrastructure improvements
MoneyUp to £4M from Clean Air Zone income, plus similar annual amount potentially from Workplace Parking Levy. CAZ funding awaits February 2027 committee approval; WPL funds depend on consultation outcome
What happens nextGroup to report by September 2027First recommendations needed by December 2026 for April 2027 service changes
Who it affectsBus passengers in BristolDecisions will shape supported bus services across the city region, potentially including new routes, higher frequencies and lower fares

What was decided

The committee agreed to establish a Task and Finish Group on Supported Bus Services in line with the draft Terms of Reference Report P23

The committee noted the membership as Councillors Coombes, Hayward, Lavan, Plowden, Renhard, Rippington, Self, Weston and Wilcox Report P24

The committee agreed that Councillor Rippington would be the Chair of the Task and Finish Group Report P25

Why

The commercial bus network is complemented by additional supported bus services funded through the levy of constituent councils or other dedicated sources Report P3

In July 2026 the committee approved a proposal to allocate up to £4M of Clean Air Zone income to public transport improvements, with final confirmation delayed until February 2027 Report P4

The proposed group would assess and recommend the best way of spending these funds to enhance the public transport network through additional supported services, enhancements or other network improvements Report P6

What happens next

The group will examine initial options for investment should finance become available in time for April 2027 service changes, including identifying strategic priorities such as providing a service to the new South Bristol Youth Zone Report P7

Agreement on new services for April 2027 will need to be reached by December 2026, with contracts awarded by mid-January 2027, to allow sufficient time for procurement and registration Report P20

The group will conclude its work no later than September 2027 Report P21

The money

  • Up to £4M Clean Air Zone income allocated to public transport improvements, pending February 2027 committee approval Report P4
  • Similar annual amount Potential funding from Workplace Parking Levy proposals, dependent on public consultation outcome Report P5

Options considered

  • Under consideration: Increased frequencies on existing bus services. One of the options the group may recommend for CAZ funding from September 2027 Report P9
  • Under consideration: New services to fill existing gaps in the current network. One of the options the group may recommend for CAZ funding from September 2027 Report P10
  • Under consideration: Reduced fares for day rider tickets or similar fare proposals including a one-hour ticket to encourage interchange use. One of the options the group may recommend for CAZ funding from September 2027 Report P11
  • Under consideration: Yellow route circular service to take advantage of City Centre Framework infrastructure changes. One of the options the group may recommend for CAZ funding from September 2027 Report P12
  • Under consideration: Minor bus stop infrastructure works to support new services or community safety improvements. One of the options the group may recommend for CAZ funding from September 2027 Report P14
  • Under consideration: Contribution to delivery of a mass transit system. Potential use for WPL funding should the levy be implemented Report P16
  • Under consideration: Developing options for a franchise model. Potential use for WPL funding should the levy be implemented Report P17
  • Under consideration: Setting up of a municipal bus company. Potential use for WPL funding should the levy be implemented Report P18

Implications

  • Financial: Up to £4M of CAZ income is available for public transport improvements, with potential additional annual funding from WPL Report P4, P5
  • Transport: Decisions will shape supported bus services across Bristol city region including routes, frequencies and fares Report P6, P7
  • Environment: Better public transport will support decarbonisation of the city and improve air quality by reducing reliance on private vehicles Report P28, P30
  • Equalities: Enhanced bus services will assist lower income groups with accessing the jobs market and help tackle poverty by improving access to transport and employment Report P28

Who and where

  • Bus passengers across Bristol city region Report P3, P30
  • West of England Combined Authority as Transport Authority Report P3
  • Local bus operators Report P32
  • Young people, particularly those who would use a service to the South Bristol Youth Zone Report P7

Timeline

  • July 2026: Transport and Connectivity Committee approved allocation of up to £4M CAZ income to public transport improvements Report P4
  • Immediately: Task and Finish Group work commences to understand options and costs Report P6
  • December 2026: Agreement needed on new services to be tendered for April 2027 changes Report P20
  • Mid-January 2027: Contracts to be awarded for April 2027 service changes Report P20
  • February 2027: Final confirmation of CAZ funding investment following wider CRSTS Programme budget consideration Report P4
  • April 2027: Agreement needed on new services to be tendered for September 2027 changes Report P21
  • Mid-May 2027: Contracts to be awarded for September 2027 service changes Report P21
  • September 2027: Task and Finish Group concludes; September 2027 service enhancements and fares initiatives launch Report P21

Plain English for the jargon

  • Supported bus services: Bus services procured and managed by West of England Combined Authority to complement the commercial network, funded through council levy or dedicated sources
  • Clean Air Zone (CAZ) income: Revenue generated from the Clean Air Zone charge applied to certain vehicles entering the city centre area
  • CRSTS Programme: City Region Sustainable Transport Settlement programme of funding
  • Workplace Parking Levy (WPL): A proposed charge on employers who provide workplace parking, with revenue potentially directed to sustainable transport
  • Task and Finish Group: A committee of councillors appointed to examine a specific issue and report back within a set timeframe
  • Yellow route: A circular bus service identified in the BCC City Centre Framework using city centre infrastructure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That the Committee for Transport and Connectivity 1. Agreed to establish a task and finish group on Supported Bus Services, noting the above, and in line with the draft Terms of Reference. 2. Noted the membership of the Task and Finish Group as Councillors Coombes, Hayward, Lavan, Plowden, Renhard, Rippington, Self, Weston and Wilcox. 3. That the Chair of the Task and Finish Group be agreed as Councillor Rippington.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Transport & Connectivity Policy Committee

Purpose of report

1. To seek approval to set up a Task and Finish Group for Supported Bus Services, and associated Terms of Reference.

Evidence Base / Context

1. The commercial bus network in Bristol and the wider city region is complemented by additional ‘supported’ bus services, procured and managed by West of England Combined Authority, acting as the Transport Authority. These supported services are funded through the levy of its constituent councils, or from other dedicated funding sources.

2. In July 2026, the Transport and Connectivity Committee approved a proposal to allocate up to £4M of Clean Air Zone (CAZ) income to a mix of public transport improvements. Final confirmation of this investment will be delayed until further committee approval is given in February 2027, following consideration of the wider CRSTS Programme budget and associated priorities.

3. In addition to the proposed allocation of funding from CAZ, funding may also become available from the emerging Workplace Parking Levy (WPL) proposals. This could see a similar level of funding provided, on an annual basis, to support sustainable transport initiatives including strategic enhancements to the local bus network in Bristol.

4. The proposed Task and Finish Group would assess and recommend the best way of spending these funds, in order to enhance the public transport network through additional supported services, enhancements, or other network improvements. Whilst final approval for the CAZ funding would be sought in February 2027, the Task and Finish Group work would commence straight away, in order to better understand the options available and associated costs.

5. The work of the Task and Finish Group will be divided into three sections: 1 OFFICIAL a) Examining initial options for investment should any finance become available in time for inclusion in the April 2027 service changes. This could include looking at any recent changes in the Bristol region, as well as identifying new strategic priorities such as providing a service to the new South Bristol Youth Zone.

b) Recommending how to spend the remaining CAZ funding available for bus services from September 2027. This may require a range of options to be produced, which will be implemented in priority order once the amount of funding is confirmed. These options could include, but are not limited to:

I. Increased frequencies on existing bus services.

II. New services to fill existing gaps in the current network.

III. Reduced fares for day rider tickets or similar fare proposals, such as a one-hour ticket that would enable and encourage the use of interchanges, to promote the bus network as a whole.

IV. New services to take advantage of infrastructure changes within the City Centre such as a “yellow route” circular service, as identified in the BCC City Centre Framework.

V. Other forms of investment in the bus network, as developed by committee members.

VI. Minor bus stop infrastructure works that may be necessary to support any new services, or to support improvements to any identified community safety issues.

c) Examine and recommend uses for the funding which will become available should a Workplace Parking Levy be implemented following public consultation. These could include, but are not limited to:

I. Contributing to the delivery of a mass transit system for the city

II. Developing options for a franchise model

III. The setting up of a municipal bus company

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
DRAFT_ToR Scope Bus ServicesAppendix A 94 KB Download
PDF
Supported Bus Services Task and Finish GroupReport 97 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
EP
Councillor Ed PlowdenChair, present
TR
Councillor Tim RippingtonVice-Chair, present
NC
Councillor Nicholas CoombesCommittee Member, present
EE
Councillor Emma EdwardsCommittee Member, present
SR
Councillor Serena RalstonCommittee Member, present
TR
Councillor Tom RenhardCommittee Member, present
KS
Councillor Kaz SelfCommittee Member, present
TW
Councillor Toby WellsCommittee Member, present
MW
Councillor Mark WestonCommittee Member, present

On this subject at Bristol

Search all
  1. Supported Bus Services Task and Finish GroupThis decision
  2. Funding for Supported Bus Services Task and Finish Group Update reportApproved
  3. Funding for Supported Bus ServicesDecided
  4. Supported Bus Services Priorities Task and Finish GroupApproved
  5. Supported Bus Services ReviewAgreed

More from Bristol Transport & Connectivity Policy Committee

All decisions
MeetingDecisionOutcome
17 Sep 2026 Supply and maintenance of Urban Traffic Management and Control systemsThat the Committee for Transport and Connectivity: 1. Approved the proposal for the procurement of a new contract for... Approved Open
17 Sep 2026 Procurement of Highway Condition and AI Digital Safety Inspections ContractsThat the Committee for Transport and Connectivity 1. Authorised the Executive Director for Growth and Regeneration in... Decided Open
17 Sep 2026 Q1 Corporate Risk Report 2026/27The Transport and Connectivity Committee noted the report. Noted Open
17 Sep 2026 2026/27 Quarterly Finance Report: P3/Q1The Committee for Transport and Connectivity noted the contents of the report on the Q1 (P3) forecast. Noted Open
9 Jul 2026 Chair's AnnouncementsDecision Notices have been published on the Council’s website. The Blue Badge Parking Survey was live until the 21 Ju... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies