AI summaryBristol committee approves accepting and spending grant funding worth at least £13.4 million for supported housing and rough sleeping services from 2026 to 2029.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee authorised the Executive Director for Housing to accept and spend the funding, procure contracts over £500,000, and enter into grant agreements for three linked funding streams
Money£13.4 million minimumSupported Housing Grant £10.96 million plus Long-term Rough Sleeping Innovation Programme £375,000 plus Rough Sleeping Programme revenue £2.06 million for 2026/27, with total Rough Sleeping Programme £12.29 million over programme period
What happens nextProcurement and commissioningExecutive Director will procure and award contracts and invoke any extensions within the budget envelopes
Who it affectsPeople at risk of or experiencing homelessness. Single homeless people, rough sleepers, domestic abuse victims and their children in Bristol

What was decided

The Committee noted the additional funding awards linked to the Homelessness, Rough Sleeping and Domestic Abuse Grant and noted the additional Rough Sleeping Programme funding announced on 19 August 2026.

The Committee authorised the Executive Director for Housing in consultation with the Chair to accept and spend the 2026-2029 funding, including procuring and awarding contracts which may be over £500,000 in line with the procurement routes and maximum budget envelopes set out in the report.

The Committee authorised the Executive Director of Housing to invoke any subsequent extensions or variations specifically defined in the contracts being awarded, up to the maximum budget envelope outlined in the report.

Why

Bristol has seen an 18% increase in homelessness since the pandemic, and the number of households in temporary accommodation has more than doubled since before the pandemic. Report P3

Without the income provided by these grants, Bristol City Council would not have the resources available to deliver the initiatives, which would lead to a further significant increase in homelessness and financial pressures to the Council. Report P61

The grant funding enables the council to fund services in a whole systems approach to tackle homelessness and rough sleeping, focusing on early intervention and maximising prevention activities. Report P16, P19

What happens next

The Executive Director for Housing will procure and award contracts in line with the procurement routes and maximum budget envelopes set out in the report. Report P44

A Local Supported Housing Strategy will be published in March 2027 in conjunction with adult social care and children's services. Report P28

The first new homes from the Rough Sleeping Programme are expected to be delivered from 2027/28, with support commencing from winter 2026 to prepare individuals for transition into settled housing. Report P32

The money

  • £10,963,948 Supported Housing Support Services revenue funding 2026-2029 (£2,755,398 in 26/27, £3,585,476 in 27/28, £4,623,074 in 28/29) Report P30
  • £375,000 Long-term Rough Sleeping Innovation Programme total funding 2026-2029 (£125,000 per annum) Report P25
  • £2,065,562 Bristol Rough Sleeping Programme revenue funding for 2026/27 (immediate off the streets offer) Report P34
  • £12,292,000 WECA Rough Sleeping Programme total over programme period (revenue £6,795,477, capital £5,496,523) Report P35
  • £10.04 million Housing Benefit subsidy loss spent on temporary accommodation in 25/26 Report P7
  • £13,404,510 Total revenue cost across funding streams Report P56

Options considered

  • Rejected: Not to spend the funding. Discounted due to the significant impact that this funding can bring to the city to prevent and relieve rough sleeping Report P39

Implications

  • Financial: Without this grant funding, the council would not have the resources to deliver the initiatives, leading to further significant increases in homelessness and financial pressures Report P61
  • Financial: Unit costs will not necessarily be cheaper within additional supported housing units compared to temporary accommodation due to the levels of need in the client group, so savings cannot be confirmed at this stage Report P66
  • Legal: There are no subsidy control issues arising from this grant funding, and Legal Services will provide advice on grant conditions and procurement considerations Report P68
  • Risk: IT implications will be surfaced by the projects enabled through this funding, requiring early engagement to ensure resources are available at required junctures Report P70

Who and where

  • People at risk of or experiencing homelessness in Bristol Report P3, P4, P17
  • People rough sleeping in Bristol Report P4, P12, P13
  • Domestic abuse victims and their children Report P21
  • Mayoral Strategic Authorities including WECA Report P22, P23
  • Voluntary sector organisations Report P34

Timeline

  • 2026-2029: Supported Housing Support Services funding period Report P13, P28
  • 2026-2029: Long-term Rough Sleeping Innovation Programme funding period Report P25
  • 19 August 2026: Rough Sleeping Programme announced by government Report P31
  • Winter 2026: Rough Sleeping Programme support expected to commence Report P32
  • 2027/28 onwards: First new homes from Rough Sleeping Programme expected to be delivered Report P32
  • March 2027: Local Supported Housing Strategy to be published Report P28

Plain English for the jargon

  • HRSDAG: Homelessness, Rough Sleeping and Domestic Abuse Grant
  • LRSIP: Long-term Rough Sleeping Innovation Programme
  • SHSS: Supported Housing Support Services
  • TA: Temporary Accommodation
  • WECA: West of England Mayoral Combined Authority
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

The Committee RESOLVED : To note the additional funding awards linked to the Homelessness, Rough Sleeping and Domestic Abuse Grant. To note the additional funding stream announced on 19 August 2026 (Rough Sleeping Programme). Contractual: The Committee (unnanimously) RESOLVED : To authorise the Executive Director for Housing in consultation with Chair of the Homes and Housing Delivery Committee to take all steps required to accept and spend the 26-29 funding, as outlined in the report, including procuring and awarding contracts (which may be over £500k) in line with the procurement routes and maximum budget envelopes set out in this report. To authorise the Executive Director of Housing in consultation with the Chair of the Homes and Housing Delivery Committee to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report. To authorise the Executive Director of Housing in consultation with Chair of the Homes and Housing Delivery Committee to enter into a grant agreement/ Memorandum of Understanding and to take all steps required to accept and spend the new Rough Sleeping Programme funding for 2026/29 – the amount is unknown at present aside from revenue funding for 2026/27 - as outlined in point 14; including procuring and awarding contracts (which may be over £500k) in line with the procurement routes.
Word for word from the decision Bristol published for this meeting. Source: democracy.bristol.gov.uk

Follow this further

Built from Bristol's papers

What the report saysPro

Report to Homes and Housing Delivery Policy Committee

Purpose of report

To seek approval to accept and spend Bristol’s funding for Supported Housing Support Services (SHSS) 2026-2029, the Long-Term Rough Sleeping Innovation Programme (LRSIP) and the new Rough Sleeping Programme funding, all of which form part of the Homelessness, Rough Sleeping and Domestic Abuse Grant.

Evidence Base

1. Bristol has experienced rising rates of homelessness. Since the pandemic we have seen a 18% increase in households approaching Bristol City Council because of homelessness related issues. The number of households in temporary accommodation (TA) has more than doubled since before the pandemic.

2. During the pandemic and “Everyone in” (the "Everyone In" campaign was an emergency initiative launched by the UK government in March 2020 requiring local councils to house rough sleepers to protect them from the COVID-19 pandemic), the number of single people accommodated increased significantly. Family homelessness has increased since the end of lockdowns and the removal of protections like the eviction ban; similarly, single homelessness and number of people coming onto the streets has increased, as has the proportion of people who have been rough sleeping longer term.

Template approved October 25

OFFICIAL 3. The cost-of-living crisis and continuing challenges around supply and affordability of both homes for sale and private renting are contributing to high levels of homelessness presentations, against a backdrop of diminishing social housing lettings each year.

4. TA is a significant financial pressure for the council and £10.04 million was spent in 25/26 on Housing Benefit subsidy loss.

The graphs below illustrate the increasing levels of homelessness and rough sleeping in the city:

Graph 1: Number of households presenting as homeless to Bristol City Council per quarter.

Graph 2: Number of families and singles placed in TA each quarter. n.b. TA figures not fully up to date due to issues with data extrapolation due to issues with the new system

Template approved October 25

OFFICIAL Graph 3: Number of people per month found to be rough sleeping in Bristol

Graph 4: Number of people per month found to be rough sleeping in Bristol divided into cohorts (new to the streets, long term and returning to the streets)

Template approved October 25

OFFICIAL Note for graph 4: There has been an increase in people reported rough sleeping in June, particularly people who are longer term rough sleeping. This is due to the heat wave and increased engagement on the streets to ensure that more vulnerable clients are safe.

5. Grant funding from the government – previously the Homelessness Prevention Grant (HPG), the Rough Sleeping Accommodation Programme (RSAP), the Single Homelessness Accommodation Programme (SHAP), and the Rough Sleeping Prevention and Recovery Grant (RSPARG) – now the Homelessness, Rough Sleeping and Domestic Abuse Grant (HRSDAG) have enabled us to fund services in a whole systems approach to tackle homelessness and rough sleeping in the city.

6. In spite of challenging housing context in the city – particularly in relation to a lack of supply of affordable homes and increasing rents – these services have contributed to:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Supported Housing Funding ProposalAppendix A 115 KB Download
PDF
Equality Impact Assessment: Supported Housing FundingAppendix B 573 KB Download
PDF
Environmental Impact Assessment: Supported Housing Funding FinalAppendix C 120 KB Download
PDF
Funding for supported housing support services 2026-2029Report 303 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
BP
Councillor Barry ParsonsChair, present
RE
Councillor Richard EddyVice-Chair, present
KB
Councillor Kerry BailesCommittee Member, present
PG
Councillor Paul GogginCommittee Member, present
RL
Councillor Rob LoganCommittee Member, present
ZP
Councillor Zoë PeatCommittee Member, present
LS
Councillor Lisa StoneCommittee Member, present
JT
Councillor Jerome ThomasCommittee Member, present
ST
Councillor Sibusiso TshabalalaCommittee Member, present
JS
John SmithOfficer, expected
CG
Clare GibbOfficer, expected
FL
Fiona LesterOfficer, expected

All 15 on the meeting page

On this subject at Bristol

Search all
  1. Funding for supported housing support services 2026-2029This decision
  2. Funding for Supported Bus Services Task and Finish Group Update reportApproved
  3. Funding for Supported Bus ServicesDecided

More from Bristol Homes and Housing Delivery Policy Committee

All decisions
MeetingDecisionOutcome
18 Sep 2026 Q1 (P03) Finance UpdateThe Committee Decided Open
18 Sep 2026 Q1 Corporate Performance UpdateThe Committee RESOLVED : To note the Performance progress report. Noted Open
18 Sep 2026 Housing & Consumer Standards Programme and Compliance UpdateThe Committee RESOLVED : To note the Housing Consumer Standards Programme update (see section 1). To note the July 26... Noted Open
18 Sep 2026 Asset Management StrategyThe Committee (unanimously) Decided Open