GATEWAY REVIEW 0, 1 & 2: APPROVAL OF 2011/2012 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTION

Approved Executive 1 paper

Executive approved this item on Wednesday 2 February 2011. Below is the council's own wording, with the papers it was decided on.

Item166

Resolved

RESOLVED that 1) the overall expenditure for the Maintenance Budget for CYP Properties in 2011/2012 of £7,387,000 be approved; 2) the criteria used to assemble the planned maintenance programmes (Gateway review 0 & 1) be noted; 3) the initial CYP planned maintenance programme, a full copy of which had been made available in the Members room, be noted; 4) authority be delegated to the Chief Property Officer to vary the planned programmes where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources; 5) the preferred procurement option and method be used (Gateway review 2); 6) authority be delegated to the Chief Property Officer to select the most economically advantageous tender for any individual item of expenditure under the approved programmes referred to at (1) – (4) above; and 7) the Director of Renewal & Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in this report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley Agenda DRR10/00129 Item No. PART 1 - PUBLIC

<Please select>

Decision Maker: Executive

Date: 2 February 2011 Decision Type: Non-Urgent Executive Key

Title: GATEWAY REVIEW 0, 1 & 2. APPROVAL OF 2011/2012 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTION

Contact Officer: John Turner, Chief Property Officer Tel: 020 8461 4404 E-mail: [email protected]

Chief Officer: Marc Hume - Director of Renewal & Recreation

Ward: Borough Wide

1. Reason for report

Property Division is responsible for carrying out planned maintenance works to the Council’s portfolio of CYP buildings.

This report sets out the budget for the proposed programmes and the criteria used to assemble them. Once agreed the programmes will be circulated to all schools and education properties for comment.

The report also addresses the strategic assessment and business justification for the programmes and the preferred procurement option for completing them.

A summary of the Gateway Process is given in Appendix A.

A copy of the proposed CYP planned maintenance programme is available within the Members room.

________________________________________________________________________________

2. RECOMMENDATION(S)

Members are asked to:

(i) Approve overall expenditure for the Maintenance Budget for CYP Properties in 2011/2012 of £7,387,000.

1 (ii) Consider the criteria used to assemble the planned maintenance programmes. (Gateway review 0 & 1)

(iii) Consider the initial CYP planned maintenance programme. A copy is available in the Members room.

(iv) Delegate authority to the Chief Property Officer to vary the planned programmes where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources.

(v) Approve the preferred procurement option and method to be used. (Gateway review 2)

(vi) Delegate authority to the Chief Property Officer to select the most economically advantageous tender for any individual item of expenditure under the approved programmes referred to at (i) – (iv) above.

(vii) Agree that the Director of Renewal & Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in this report.

2 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £7,387,000 2. Ongoing costs: Recurring cost. 3. Budget head/performance centre: Property Division, Renewal & Recreation Department 4. Total current budget for this head: £7,387,000 5. Source of funding: Funded from capital budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): Not applicable 2. If from existing staff resources, number of staff hours: Not applicable ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Borough Wide ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A. 2. Summary of Ward Councillors comments: N/A

3 3. COMMENTARY

Property Division is responsible for delivering the planned maintenance of the Council’s portfolio of CYP buildings. The Council has a five year maintenance programme of CYP properties that is reviewed by officers each year. It is based on available funding, condition and priority and urgent items that arise inter-year. As part of this process schools are formally consulted on the priorities for support during the year ahead.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GATEWAY REVIEW 0, 1 & 2: APPROVAL OF 2011/2012 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTIONReport 125 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. GATEWAY REVIEW 0, 1 & 2: APPROVAL OF 2011/2012 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTIONThis decision
  2. Gateway report for the provision of statutory homelessness reviewsNoted
  3. Gateway report for the provision of statutory homelessness reviewsNoted
  4. Gateway 1 members report: high needs strategic planning fund review: special educational needs and disability - procurement of short term contractNoted
  5. Gateway review 1/2 approval of 2016/2017 education building maintenance budgets, education planned maintenance programme and preferred procurement optionsApproved
  6. Gateway review of health visiting and national child measurement programmeDecided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies