CAPITAL PROGRAMME MONITORING - 3rd QUARTER 2010/11

Approved Executive 2 papers

Executive approved this item on Wednesday 2 February 2011. Below is the council's own wording, with the papers it was decided on.

Item164

Resolved

RESOLVED that approval be given to the following amendments to the Capital Programme: (i) the addition of £1,500,000 in 2010/11 in respect of additional funding from Bromley PCT for the LD reprovision scheme (as referred to in paragraph 3.2 of the Director’s report); (ii) the addition of £7,255,000 over the two years 2011/12 to 2012/13 in respect of government grant allocations announced in the December Settlement (as referred to in paragraph 3.3 of the Director’s report); (iii) the addition of £485,000 in 2011/12 in respect of external funding for London private sector renewal schemes (as referred to in paragraph 3.4 of the Director’s report); (iv) the addition of £100,000 in 2011/12 in respect of new Capital Ambition funding for Efficiency and Transformation (as referred to in paragraph 3.5 of the Director’s report); (v) a reduction of £4,340,000 over the four years 2010/11 to 2013/14 to reflect reduced Transport for London support for highways schemes (as referred to in paragraph 3.6 of the Director’s report); (vi) a reduction of £2,690,000 in 2010/11 to reflect reduced Formula Devolved Capital support (as referred to in paragraph 3.7 of the Director’s report); (vii) a net addition of £100,000 in 2010/11 for the Farnborough Primary School extension scheme (as referred to in paragraph 3.8 of the Director’s report); (viii) the addition of £230,000 in 2010/11 in respect of the balance of short breaks capital funding (as referred to in paragraph 3.9 of the Director’s report); and (ix) the addition of £112,000 in 2010/11 to reflect additional Extended Services grant (as referred to in paragraph 3.10 of the Director’s report).
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley Agenda DR10114 Item No. PART 1 - PUBLIC

<Please select>

Decision Maker: Executive

Date: 2nd February 2011 Decision Type: Non-Urgent Executive Key

Title: CAPITAL PROGRAMME MONITORING-3rd QUARTER 2010/11

Contact Officer: Martin Reeves, Group Accountant (Technical) Tel: 020 8313 4291 E-mail: [email protected]

Chief Officer: Director of Resources

Ward: All

1. Reason for report

This report summarises the current position on capital expenditure and receipts following the 3rd quarter of 2010/11 and seeks the Executive‟s approval to a revised Capital Programme. The Capital Review report elsewhere on the agenda seeks approval to new schemes over the years 2011/12 to 2014/15.

____________________________________________________________________________

2. RECOMMENDATION(S)

The Executive is asked to: 2.1 Note the report and to agree a revised Capital Programme. 2.2 Approve the following amendments to the Capital Programme: (i) Addition of £1,500,000 in 2010/11 in respect of additional funding from Bromley PCT for the LD reprovision scheme (see para 3.2);

(ii) Addition of £7,255,000 over the two years 2011/12 to 2012/13 in respect of government grant allocations announced in the December Settlement (see para 3.3);

(iii) Addition of £485,000 in 2011/12 in respect of external funding for London private sector renewal schemes (see para 3.4);

(iv) Addition of £100,000 in 2011/12 in respect of new Capital Ambition funding for Efficiency and Transformation (see para 3.5);

(v) Reduction of £4,340,000 over the four years 2010/11 to 2013/14 to reflect reduced Transport for London support for highways schemes (see para 3.6);

1 (vi) Reduction of £2,690,000 in 2010/11 to reflect reduced Formula Devolved Capital support (see para 3.7);

(vii) Net addition of £100,000 in 2010/11 for Farnborough Primary School extension scheme (see para 3.8);

(viii) Addition of £230,000 in 2010/11 in respect of the balance of short breaks capital funding (see para 3.9);

(ix) Addition of £112,000 in 2010/11 to reflect additional Extended Services grant (see para 3.10).

2 Corporate Policy 1. Policy Status: Existing policy. Capital Programme monitoring and review is part of the planning and review process for all services. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost Total increase of £2.8m over the 4 years 2010/11 to 2013/14, mainly due to net increases in external funding 2. Ongoing costs: Non-recurring cost. 3. Budget head/performance centre: N/A (Capital Programme) 4. Total current budget for this head: £Total £150.2m over 4 years 2010/11 to 2013/14 5. Source of funding: Capital grants, capital receipts and revenue contributions ________________________________________________________________________________ Staff 1. Number of staff (current and additional): N/A 2. If from existing staff resources, number of staff hours: N/A ________________________________________________________________________________ Legal 1. Legal Requirement: No statutory requirement or Government guidance. 2. Call-in: Call-in is not applicable. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): N/A ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments: N/A

3 3. COMMENTARY

Capital Expenditure

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING: 3rd QUARTER 2010/11Report 111 KB DownloadRead as text
PDF
Exec-020211CapPropAppAReport 40 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING - 3rd QUARTER 2010/11This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. Capital programme monitoring - quarter 1 2026/27Decided
  4. 2026/27 q1 capital programme monitoringNoted
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 1 2026/27Decided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies