PRIVATE STREET WORKS - RAVENSBOURNE AVENUE, BECKENHAM (UNADOPTED SECTION) - SECOND RESOLUTION
ApprovedScrutiny3 papers
Environment and Community Services Policy Development and Scrutiny Committee approved this item on Tuesday 1 March 2011. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Portfolio Holder be recommended to: (1) approve without modification the specification, plan, sections and typical details, estimate and provisional apportionment submitted by the Director of Environmental Services, in respect of the scheme approved by the Environment Portfolio Holder following the Environment PDS Committee meeting on 21 September 2009; (2) resolve that the Council bears the whole of the cost of the street works, under the provisions of s. 236(1) of the Highways Act 1980 (the proposal is to fund this cost from external TfL funding); and (3) approve the allocation of funding from the 2011/12 Neighbourhoods and Corridors allocation, subject to officers identifying the funding from within the TfL LIP allocation for 2011/12 and subject to the approval of Transport for London.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report to Environment and Community Services Policy Development and Scrutiny Committee
Recommendations
2.1The specification, plan, sections and typical details, estimate and provisional apportionment submitted by the Director of Environmental Services, in respect of the scheme approved by the Environment Portfolio Holder following the Environment PDS committee on 21 September 2009, be approved without modification.
2.2The Portfolio Holder further resolves that the Council bears the whole of the cost of the street works, under the provisions of s. 236(1) of the Highways Act 1980. It is proposed to fund this cost from external TfL funding.
2.3The Portfolio Holder approves the allocation of funding from the 2011/12 Neighbourhoods and Corridors allocation, subject to officers identifying the funding from within the TfL LIP allocation for 2011/12 and subject to the approval of Transport for London.
3. Budget head/performance centre: TfL, Neighbourhoods, Corridors and Supporting Measures
4. Total current budget for this head: £2.949m
5. Source of funding: TfL Funding for 2011/12 ________________________________________________________________________________
Staff
1. Number of staff (current and additional): 1
2. If from existing staff resources, number of staff hours: The staff time involved with this scheme will depend entirely upon whether or not objections are raised at provisional and final apportionment stages. However, the superintendence charge shown in the report is considered sufficient to meet the cost of officers time. ________________________________________________________________________________
Legal
1. Legal Requirement: Statutory requirement. The Resolution of Approval is to be made under the provisions of the Private Street Works Code, comprising s.205 - 218 of the Highways Act 1980. The authority for the Council to adopt the street following street works is contained in s.228 of the Act and for the Council to meet the cost of the works, s.263 (1)
2. Call-in: Call-in is applicable ________________________________________________________________________________
Customer Impact
1. Estimated number of users/beneficiaries (current and projected): Difficult to quantify because of the various new paths this could connect with.There are the new footways in Crab Hill and Ravensbourne Aveune, the new path built in Lewisham Park and also the new path built in Warren Avenue Sports Ground in 2010. However, the number could easly go to 500 pedestrians and cyclists per day, because of the nearby railway station. ________________________________________________________________________________
Ward Councillor Views
1. Have Ward Councillors been asked for comments? Yes. 2. Summary of Ward Councillors comments: To be reported on the night
2 3. COMMENTARY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Community Services Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding...
Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.