PRIVATE STREET WORKS - KENT HOUSE STATION APPROACH - SECOND RESOLUTION
ApprovedScrutiny2 papers
Environment and Community Services Policy Development and Scrutiny Committee approved this item on Tuesday 28 February 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the recommendations to the Portfolio Holder be supported namely that: (1) the specification, as detailed in plan No. ESD-10935-1 revision A, sections, estimate and provisional apportionment, now submitted by the Director of Environmental Services, in respect of the scheme approved by the Environment Portfolio Holder on 26 th October 2011, be approved without modification; and (2) the Council bears the whole of the cost of the street works, which will be met from funding provided by Transport for London, under the provisions of s. 236(1) of the Highways Act 1980.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Chief Officer: Nigel Davies, Director of Environmental Services
Ward: Penge and Cator
1. Reason for report
To obtain a Resolution of Approval under the Private Street Works Code, in respect of the unadopted section of Kent House Station Approach. This will enable the street to be made-up and adopted as a highway maintainable at the public expense
2.1That the specification, as detailed in plan No. ESD-10935-1 revision A, sections, estimate and provisional apportionment, which will be on display on the evening of committee, now submitted by the Director of Environmental Services, in respect of the scheme approved by the Environment Portfolio Holder on 26th October 2011, be approved without modification.
2.2That the Portfolio Holder further resolves that the Council bears the whole of the cost of the street works, which will be met from funding provided by Transport for London, under the provisions of s. 236(1) of the Highways Act 1980.
1 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Quality Environment. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £225k 2. Ongoing costs: N/A. 3. Budget head/performance centre: TfL LIP funding for Network Infrastructure for 2012/13 & 2013/14 4. Total current budget for this head: £205k is allocated to implement this scheme in 2012/13 with a further £20k for 2013/14. Both these sums have been agreed in principle by TfL. 5. Source of funding: Transport for London LIP funding ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 1 2. If from existing staff resources, number of staff hours: estimated at 20 hours depending on whether or not objections are raised at provisional and final apportionment stages ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Surveys taken on 16/1/12 indicated 492 pedestrain, 9 cyclist and 34 car movements between 07:00 and 10:00 with 445 pedestrain, 12 cyclist and 43 car movements between 15:00 and 19:00. Projected use is double the cyclist and pedestrian movements, with car movements increasing considerably. ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Yes. 2. Summary of Ward Councillors comments: Ward Members have expressed support for this scheme.
2 3. COMMENTARY
3.1On 4th October 2011, the Environment Portfolio Holder received a report regarding the use and condition of the part of Kent House Station Approach, Beckenham that has not been made up and adopted as a highway maintainable at the public expense.
3.2The north east section of footway of Kent House Station Approach was adopted in 2003, as part of another scheme.
3.3Complaints about the condition of the unmade section of Kent House Station Approach have been received from residents and users. On several occasions, the Council has been asked to exercise its discretionary powers to carry out urgent repairs to the street at its own expense, under S.230(7) of the Highways Act 1980, but currently there is no budget to enable such repairs to be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Community Services Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding...
Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.