RESOLVED that 1) subject to Council agreeing the budget to approve an overall expenditure profile for Building Maintenance Budgets in 2012/2013 of £2,240,190 made up as follows: Planned Maintenance £600,985 Reactive Maintenance £883,297 Cyclical Maintenance £346,442 Asbestos Management £153,080 Water Treatment Works £122,411 Disability Discrimination Act Works £66,439 External Decorations £67,536 Minor Improvements £0 TOTAL £2,240,190 2) the criteria used to assemble the planned maintenance programme (Gateway review 0 & 1) be endorsed; 3) the planned maintenance programme be approved; 4) authority be delegated to the Director of Resources in consultation with the Portfolio Holder to vary the planned programme to accommodate any change in the approved budget or where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources; 5) the preferred procurement option and method to be used (Gateway review 2) be approved; 6) authority be delegated to the Director of Resources to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at ( i ) – (v) above; 7) the Director of Renewal & Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in the report .
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report No. London Borough of Bromley DRR 12/009 PART 1 - PUBLIC
<Please select>
Decision Maker: Executive
Date: 1 February 2012 Decision Type: Non-Urgent Executive Key
Title: GATEWAY REVIEW 0, 1 & 2 APPROVAL OF 2012/2013 OPERATIONAL BUILDING MAINTENANCE BUDGETS, PLANNED MAINTENANCE PROGRAMMES AND PREFERRED PROCUREMENT OPTION
Contact Officer: Marcus Perry, Interim Head of Property Tel: 020 8461 7582 E-mail: [email protected]
Chief Officer: Marc Hume - Director of Renewal & Recreation
Ward: Borough Wide
1. Reason for report
This report sets out the criteria used to assemble each programme based on the draft budget proposals.
The report also addresses the strategic assessment and business justification for the programmes and the preferred procurement option for completing them.
A copy of the proposed planned maintenance programme for operational properties is within the Members’ room.
(i) Subject to Council agreeing the budget to approve an overall expenditure profile for Building Maintenance Budgets in 2012/2013 of £2,240,190 made up as:
Planned Maintenance £600,985
Reactive Maintenance £883,297
Cyclical Maintenance £346,442
1 Asbestos Management £153,080
Water Treatment Works £122,411
Disability Discrimination Act Works £66,439
External Decorations £67,536
Minor Improvements £0
TOTAL £2,240,190
(ii) Endorse the criteria used to assemble the planned maintenance programme. (Gateway review 0 & 1).
(iii) Approve the planned maintenance programme. Copies are available in the Members’ room.
(iv) Delegate authority to the Director of Resources to vary the planned programme to accommodate any change in the approved budget or where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources.
(v) Approve the preferred procurement option and method to be used. (Gateway review 2).
(vi) Delegate authority to the Director of Resources to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at (i) – (v) above.
(vii) Agree that the Director of Renewal & Recreation be authorised to submit planning applications where appropriate in respect of schemes set out in this report.
2 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £2,240,190 2. Ongoing costs: Recurring cost. 3. Budget head/performance centre: Property Division, Renewal & Recreation Department 4. Total current budget for this head: £3,967,240 2011/12 Original budget 5. Source of funding: Funded from revenue budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): Not applicable 2. If from existing staff resources, number of staff hours: Not applicable ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Borough wide ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A. 2. Summary of Ward Councillors comments: N/A
3 3. COMMENTARY
3.1The Property Division is responsible for a range of maintenance and improvements to the Council’s portfolio of operational buildings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.