GATEWAY REVIEW 0, 1 & 2 APPROVAL OF 2012/2013 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTION

Approved Executive 1 paper

Executive approved this item on Wednesday 1 February 2012. Below is the council's own wording, with the papers it was decided on.

Item141

Resolved

RESOLVED that 1) the overall expenditure for the Maintenance Budget for CYP properties in 2012/2013 of £2,576,170 be approved; 2) the criteria used to assemble the planned maintenance programme (Gateway review 0 & 1) be endorsed; 3) the proposed CYP planned maintenance programme be approved; 4) authority be delegated to the Director of Resources in consultation with the Portfolio Holder to vary the planned programme where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources; 5) the preferred procurement option and method to be used (Gateway review 2) be approved; 6) authority be delegated to the Director of Resources to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at ( i ) – (iv) above; and 7 the Director of Resources be authorised to submit planning applications where appropriate in respect of schemes identified in the report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Report No. London Borough of Bromley DRR 12/010 PART 1 - PUBLIC

Decision Maker: Executive

Date: 1 February 2012 Decision Type: Non-Urgent Executive Key

Title: GATEWAY REVIEW 0, 1 & 2 APPROVAL OF 2012/2013 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTION

Contact Officer: Marcus Perry, Interim Head of Property Tel: 020 8461 7582 E-mail: [email protected]

Chief Officer: Marc Hume - Director of Renewal & Recreation

Ward: Borough Wide

1. Reason for report

Property Division is responsible for carrying out planned maintenance works to the Council’s portfolio of CYP buildings.

This report sets out the budget for the proposed programme and the criteria used to assemble it. Once agreed the programme will be circulated to all Bromley maintained schools and education properties.

The report also addresses the strategic assessment and business justification for the programme and the preferred procurement option for completing it.

A summary of the Gateway Process is given in Appendix A.

A copy of the proposed CYP planned maintenance programme is available within the Members’ room.

________________________________________________________________________________

2. RECOMMENDATION(S)

2.1Members are asked to:

(i) Approve overall expenditure for the Maintenance Budget for CYP properties in 2012/2013 of £2,576,170.

1 (ii) Consider the criteria used to assemble the planned maintenance programme. (Gateway review 0 & 1)

(iii) Consider the proposed CYP planned maintenance programme. A copy is available in the Members room.

(iv) Delegate authority to the Director of Resources to vary the planned programme where such action is considered necessary to either protect the Council’s assets or make the most effective use of resources.

(v) Approve the preferred procurement option and method to be used. (Gateway review 2)

(vi) Delegate authority to the Director of Resources to select the most economically advantageous tender for any individual item of expenditure under the approved programme referred to at (i) – (iv) above.

(vii) Agree that the Director of Resources be authorised to submit planning applications where appropriate in respect of schemes identified in this report.

2 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £2,576,170 2. Ongoing costs: Recurring cost. 3. Budget head/performance centre: Property Division, Renewal & Recreation Department 4. Total current budget for this head: £2,576,170 5. Source of funding: Funded from capital budgets ________________________________________________________________________________ Staff 1. Number of staff (current and additional): Not applicable 2. If from existing staff resources, number of staff hours: Not applicable ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Borough Wide ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? N/A. 2. Summary of Ward Councillors comments: N/A

3 3. COMMENTARY

3.1Proposed Contract Period (including extension options) 1 April 2012 – 31 March 2013.

3.2The Property Division is responsible for delivering the planned maintenance of the Council’s portfolio of CYP buildings. The Council has a five year planned maintenance programme for CYP properties that is reviewed by officers each year. It is based on available funding, condition, priority and urgent items that arise during the year. As part of this process schools are consulted on the priorities for support during the year ahead.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GATEWAY REVIEW 0, 1 & 2 APPROVAL OF 2012/2013 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTIONReport 119 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. GATEWAY REVIEW 0, 1 & 2 APPROVAL OF 2012/2013 CYP BUILDING MAINTENANCE BUDGETS, CYP PLANNED MAINTENANCE PROGRAMME AND PREFERRED PROCUREMENT OPTIONThis decision
  2. Gateway report for the provision of statutory homelessness reviewsNoted
  3. Gateway report for the provision of statutory homelessness reviewsNoted
  4. Gateway 1 members report: high needs strategic planning fund review: special educational needs and disability - procurement of short term contractNoted
  5. Gateway review 1/2 approval of 2016/2017 education building maintenance budgets, education planned maintenance programme and preferred procurement optionsApproved
  6. Gateway review of health visiting and national child measurement programmeDecided

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies