UPDATE ON THE IMPLEMENTATION OF THE FLOODING AND WATER ACT 2010

Approved Executive 2 papers

Executive approved this item on Wednesday 11 April 2012. Below is the council's own wording, with the papers it was decided on.

Item169

Resolved

RESOLVED that approval be given for the release of £220,000 from the 2012/13 Central contingency Sum to implement the proposals detailed in the report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive

Draft Minute Environment PDS Committee meeting on 28th February 2012 UPDATE ON THE IMPLEMENTATION OF THE FLOODING AND WATER ACT 2010

Report ES12031

Members received a report: (i) reviewing progress of the Council’s first year of operation as a Lead Local Flood Authority (LLFA); (ii) considering responsibilities and work streams for the coming year; and (iii) advising of the DEFRA consultation on the implementation of the LLFA role of the Sustainable Urban Drainage Systems (SUDS) Approving Body.

The Government had provided grant monies for the remainder of the Comprehensive Spending Review (CSR) period to cover the cost of implementing the Flooding and Water Act 2010.

The Environment Portfolio Holder was asked to (i) approve the proposals for Sustainable Urban Drainage and the SUDS Approval Body (SAB) and (ii) approve the draft response to the DEFRA Consultation on the implementation of the Sustainable Drainage Systems provisions of the Flooding and Water Management Act. The Executive was also asked to release a sum of £220,000 from the 2012/13 Central Contingency Sum to implement the proposals detailed in Report ES12031.

In discussion and concerning increased staff resource necessary for the work of the SUDS Approving Body, the Chairman suggested that a joint team of varying grades be set up with neighbouring authorities. It was indicated to Members that officers were already working with the London Boroughs of Croydon, Bexley, Lewisham and Greenwich.

Concerning a retrofitting of SUDs and a proposal of using £10k to subsidise the provision of water butts to residents, it was indicated that the use of water butts could help prevent flooding and officers were looking to procure the butts at the same time as compost bins. It was also explained that officers were looking to take in the water butts for storage at the central depot and then sell them on to residents. The Chairman highlighted a scenario of a number of water butts ordered but not sold on; however, Members were advised that there should be sufficient demand for the butts.

RESOLVED that:

(1) the Environment Portfolio Holder be recommended to –

(a) approve the proposals for Sustainable Urban Drainage and the SUDS Approval Body (SAB); and

(b) approve the draft response to the DEFRA Consultation on the implementation of the Sustainable Drainage Systems provisions of the Flooding and Water Management Act. (2) the Executive be recommended to release a sum of £220,000 from the 2012/13 Central Contingency Sum to implement the proposals detailed in Report ES12031.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Exec-110412 Flooding and Water Act 2010: DraftPDS MinuteReport 101 KB DownloadRead as text
PDF
UPDATE ON THE IMPLEMENTATION OF THE FLOODING AND WATER ACT 2010Report 234 KB Download

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. UPDATE ON THE IMPLEMENTATION OF THE FLOODING AND WATER ACT 2010This decision
  2. Update on the implementation of the flooding and water act 2010Approved

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies