UPDATE ON THE IMPLEMENTATION OF THE FLOODING AND WATER ACT 2010
ApprovedScrutiny2 papers
Environment and Community Services Policy Development and Scrutiny Committee approved this item on Tuesday 28 February 2012. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: (1) the Environment Portfolio Holder be recommended to – (a) approve the proposals for Sustainable Urban Drainage and the SUDS Approval Body (SAB); and (b) approve the draft response to the DEFRA Consultation on the implementation of the Sustainable Drainage Systems provisions of the Flooding and Water Management Act. (2) the Executive be recommended to release a sum of £220,000 from the 2012/13 Central Contingency Sum to implement the proposals detailed in Report ES12031.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report to Environment and Community Services Policy Development and Scrutiny Committee
Recommendations
2.1That the Environment Portfolio Holder:
(i) approves the proposals for Sustainable Urban Drainage and SUDS Approval Body (SAB) and
(ii) approves the draft response to the DEFRA Consultation on the implementation of the Sustainable Drainage Systems provisions of the Flooding and Water Management Act.
1 2.2 That the Executive release a sum of £220,000 from the 2012/13 Central Contingency Sum to implement the proposals detailed in the report.
2 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Quality Environment. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £220k 2. Ongoing costs: Recurring cost. £220k in 2012/13 3. Budget head/performance centre: DEFRA grant held in central contingency for Flooding & Water Management Act 4. Total current budget for this head: £253k 5. Source of funding: Grant funding from DEFRA for Flooding & Water Management Act ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory requirement. Flooding and Water Management Act 2010 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Borough wide ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments: n/a
3 3. COMMENTARY
Background
3.1The Flooding and Water Management Act 2010 (FWMA) requires the London Borough of Bromley, as a Lead Local Flood Authority (LLFA), to develop, maintain, apply and monitor a strategy for local flood risk management in its area. A report was considered by the Environment Portfolio Holder in April 2011, when all responsibilities for the FWMA where delegated to the Director of Environmental Services.
3.2The initial requirement of the FWMA was the production of a Preliminary Flood Risk Assessment for the borough. This was achieved in association with the Drain London Project and Bromley’s PRFA was published on the Environment Agency Web site in December 2011.
3.3The LLFA has a duty to identify the causes of surface water flooding and determine those organisations or Authorities that have a role in mitigating the flood risk. The report reviews progress in the role of LLFA and considers responsibilities and work stream for the coming year.
3.4During the last year good progress has been made on implementing the FWMA;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Community Services Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding...
Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.