Resolved
RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted.
Improvement and Efficiency Sub-Committee noted this item on Tuesday 19 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted.
Report No. London Borough of Bromley ES12036 PART 1 - PUBLIC
Decision Maker: Environment PDS Committee
Date: 28 February 2012 Decision Type: Non-Urgent Non-Executive Non-Key
Title: ENVIRONMENT IMPROVEMENT POST COMPLETION REPORT (LPSA REWARD GRANT)
Contact Officer: Kevin Munnelly, Head of Town Centre Renewal Tel: 020 8313 4582 E-mail: kevin.munnelly @bromley.gov.uk
Chief Officer: Marc Hume, Director of Renewal & Recreation
Ward: Brough Wide
1. Reason for report
This completion report is a requirement of the LPSA funding agreement. This report updates Members on the measured outcome of the Environmental Improvements carried out over two years in areas outside of the Borough’s main town centres.
________________________________________________________________________________
2. RECOMMENDATION(S)
Members note the outcome of the LPSA 1 funded Environmental Improvement project.
1 Corporate Policy 1. Policy Status: Existing policy. 2. BBB Priority: Quality Environment. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost £250k 2. Ongoing costs: N/A. 3. Budget head/performance centre: Environmental Improvements LPSA funded scheme 4. Total current budget for this head: £250k 5. Source of funding: LPSA 1 Reward Fund ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 0 2. If from existing staff resources, number of staff hours: 0 ________________________________________________________________________________ Legal 1. Legal Requirement: Non-statutory - Government guidance. 2. Call-in: Call-in is not applicable. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Main body of the report ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments:
2 3. COMMENTARY
3.1As part of the LPSA 1 Reward Fund allocation, £250k was allocated by the Executive in 2006 for Environmental Improvements. The purpose of allocation was to carry out highly visible improvements to the street scene in public areas as examples of good stewardship. Public safety, attractiveness and accessibility were identified as primary goals.
3.2The bid aimed to bring together and enhance a variety of different initiatives – cleansing, repair of street furniture, graffiti and fly-poster removal, new planting and footway repairs – which together have a significant impact on the street scene.
3.3The desire for more attractive street scene with less evidence of enviro-crime and less clutter was well established from surveys of local residents and business community. Value for money was to be demonstrated by an increase in satisfaction of the public and business community with their local area.
3.4The scheme focused on the following areas:
Local Shopping parades e.g. Kimmeridge Road, Cotmandene Crescent, Chatterton Road and Penge High Street.
3.5From a review of the evidence currently available, it is considered that the series of focused environmental improvements, funded through the LPSA 1 allocation, were well received by the recipient communities. The scheme had a notable impact in successfully delivering, often in partnership with local groups, a number of bespoke town signs. Other notable successes included an improvement scheme outside Penge East station. It is considered that the improvement scheme successfully delivered on meeting the Council’s Key Performance Indicators and Portfolio outcomes.
3.6A breakdown of the project spend is set out below:
LPSA Spending (2006 - 2008) £
Chatterton Project Village sign purchase and installation 3,025 Purchase & installation of heritage style lighting columns 58,000 Chatterton parking scheme 20,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ENVIRONMENT IMPROVEMENT POST COMPLETION REPORT (LPSA REWARD GRANT)Report | 88 KB | DownloadRead as text |
Follow Improvement and Efficiency Sub-Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2013 | Minutes of the meeting held on 3rd october 2012RESOLVED that the minutes of the meeting held on 3 rd October 2012 be agreed. | Agreed | Open |
| 19 Feb 2013 | Matters arising from previous meetingsRESOLVED that matters arising be noted. | Noted | Open |
| 19 Feb 2013 | Analysis of staff leaversRESOLVED that the analysis of staff leavers be noted. | Noted | Open |
| 19 Feb 2013 | Invest to saveRESOLVED that the progress of Invest to Save Schemes be noted. | Noted | Open |
| 19 Feb 2013 | Local government 1972 as amended by the local government (access to information) (variation) order 2006, and the freedom of information act 2000RESOLVED that the press and public be excluded during consideration of the items of business listed below as it was l... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.