Resolved
RESOLVED that the progress of Invest to Save Schemes be noted.
Report No. London Borough of Bromley Agenda RES13047 Item No. PART 1 - PUBLIC
<Please select>
Decision Maker: Improvement & Efficiency Sub-Committee
Date: 19th February 2013 Decision Type: Non-Urgent Non-Executive Non-Key
Title: INVEST TO SAVE
Contact Officer: Martin Reeves, Principal Accountant (Technical & Control) Tel: 020 8313 4291 E-mail: [email protected]
Chief Officer: Director of Resources
Ward: All
1. Reason for report
At the May meeting of the Executive, it was agreed that this Sub-Committee should monitor the Invest to Save scheme and should receive details in the form of a spreadsheet listing all the approved schemes and progress with savings achieved. This report includes a spreadsheet updating Members on schemes and progress.
____________________________________________________________________________
2. RECOMMENDATION(S)
The Sub-Committee is asked to note and comment on the report.
1 Corporate Policy 1. Policy Status: Existing policy. Monitoring and review is part of the planning and review process for all services. Invest to Save is an established and key part of the financial process. 2. BBB Priority: Excellent Council. ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated cost N/A 2. Ongoing costs: N/A. 3. Budget head/performance centre: Capital Programme, LPSA/LAA Reward Grant, Invest to Save Fund 4. Total current budget for this head: £5.7m LPSA Reward Grant; £2.3m LAA Reward Grant; £14.1m Invest to Save Fund 5. Source of funding: LPSA/LAA Reward Grant Reserve and Invest to Save Fund ________________________________________________________________________________ Staff 1. Number of staff (current and additional): n/a 2. If from existing staff resources, number of staff hours: n/a ________________________________________________________________________________ Legal 1. Legal Requirement: Non-statutory - Government guidance. 2. Call-in: Call-in is not applicable. ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): N/A ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? No. 2. Summary of Ward Councillors comments: N/A
2 3. COMMENTARY
General
3.1Invest to Save schemes were discussed at the Executive in May 2012 and this Sub-Committee was given delegated authority to determine schemes requiring an advance of up to £200k from the Invest to Save Fund, subject to a total expenditure cap of £1m and a maximum of 10 schemes. The Executive agreed that the Sub-Committee should monitor all Invest to Save schemes and should receive details in the form of a spreadsheet listing all the approved schemes and progress with savings achieved. This report includes a spreadsheet updating Members on schemes and progress.
Capital bidding process
3.2Invest to Save was introduced in 2003/04, when a formal capital scheme bidding process was agreed by the Executive with the aim of delivering key service priorities as part of the 2004/05 budget and of budgets in subsequent years. Since 2004, the annual capital review has specifically encouraged bids of an Invest to Save nature and all bids had to include a robust business plan and satisfy criteria agreed by the Executive. A number of bids have come forward since the introduction of the scheme and these are included in Appendix 1.
LPSA/LAA Reward Grant
3.3In 2005/06 and 2006/07, the Council received Reward Grant totalling £5.7m from the government in recognition of the achievement of targets set in the Council Local Public Service Agreement, signed in January 2002. In 2010/11, a further £2.3m was received from the government as Local Area Agreement Reward Grant. In the years following receipt of these grants, a number of schemes have received Executive approval and these are also included in Appendix 1.
Invest to Save Fund
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INVEST TO SAVEReport | 106 KB | DownloadRead as text |
Follow Improvement and Efficiency Sub-Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Feb 2013 | Minutes of the meeting held on 3rd october 2012RESOLVED that the minutes of the meeting held on 3 rd October 2012 be agreed. | Agreed | Open |
| 19 Feb 2013 | Matters arising from previous meetingsRESOLVED that matters arising be noted. | Noted | Open |
| 19 Feb 2013 | Analysis of staff leaversRESOLVED that the analysis of staff leavers be noted. | Noted | Open |
| 19 Feb 2013 | Environment improvement post completion report (lpsa reward grant)RESOLVED that the Environment Improvement Post Completion Report (LPSA Reward Grant) be noted. | Noted | Open |
| 19 Feb 2013 | Local government 1972 as amended by the local government (access to information) (variation) order 2006, and the freedom of information act 2000RESOLVED that the press and public be excluded during consideration of the items of business listed below as it was l... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.