Norman Park Update

Noted Scrutiny 1 paper

Renewal, Recreation and Housing Policy Development and Scrutiny Committee noted this item on Tuesday 26 February 2013. Below is the council's own wording, with the papers it was decided on.

Item68f

Resolved

RESOLVED that the report be noted and that the Portfolio Holder be recommended to agree that:- (1) Officers undertake a tendering exercise to identify suitable organisations that would:- (a) manage the athletics track from 1 April 2014 for a period of up to 25 years under arrangements similar to the current operational model whereby the Council has responsibility for the repair and replacement of the track, floodlights and pavilion; and (b) manage the athletics track from 1 April 2014 for a period of up to 25 years under a full repair and maintain lease whereby the operator has responsibility for the repair and replacement of the track, floodlights and pavilion. (2) Officers submit a further report to the Renewal and Recreation PDS meeting in June updating Members on the outcome of the tendering exercise.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Renewal, Recreation and Housing Policy Development and Scrutiny Committee

Report No. London Borough of Bromley DRR13/037 PART 1 - PUBLIC

Decision Maker: Renewal and Recreation Portfolio Holder For pre-decision scrutiny by the Renewal and Recreation PDS Committee

Date: 26th February 2013

Decision Type: Non-Urgent Executive Non-Key

Title: NORMAN PARK UPDATE

Contact Officer: John Gledhill, Head of Cultural Business Development Tel: 020 8461 7527 E-mail: [email protected]

Chief Officer: Marc Hume, Director of Renewal and Recreation

Ward: All

1. Reason for report

1.1This report provides Members with an up date on the soft tendering exercise that Officers have undertaken to identify potential leisure investment opportunities from companies wishing to develop new sports or recreation facilities in Norman Park. ________________________________________________________________________________

2. RECOMMENDATION(S)

2.1That the Renewal and Recreation PDS, and the Environment PDS, note the contents of the report and the soft tender exercise undertaken to identify a suitable leisure investment company for a commercial operation at Norman Park; and

The Renewal and Recreation Portfolio Holder is requested to agree that:

2.1Officers now undertake a tendering exercise to identify suitable organisations that would:

2.1.1 Manage the athletics track from 1st April 2014 for a period of up to 25 years, under arrangements that are similar to the current operational model, whereby the Council has responsibility for the repair and replacement of the track, floodlights and pavilion. And / or 2.1.2 Manage the athletics track from 1st April 2014 for a period of up to 25 years, under a full repair and maintain lease, whereby the operator has responsibility for the repair and replacement of the track, floodlights and pavilion.

2.2Officers bring back a further Report to Members Renewal and Recreation PDS in July updating them on the outcome of the tendering exercise described in 2.1. 1 Corporate Policy 1. Policy Status: N/A. Existing Policy 2. BBB Priority: Vibrant Thriving Town Centres. ________________________________________________________________________________ Financial 1. Cost of proposal: N/A 2. Ongoing costs: N/A. 3. Budget head/performance centre: Norman Park Track Management fee 4. Total current budget for this head: £42.3k 5. Source of funding: Existing revenue budget 2013/14

________________________________________________________________________________ Staff 1. Number of staff (current and additional): 2. If from existing staff resources, number of staff hours: N/A ________________________________________________________________________________ Legal 1. Legal Requirement: No statutory requirement or Government guidance. 2. Call-in: Call-in is applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): 51,000 ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Yes. 2. Summary of Ward Councillors comments: Ward Members were initially consulted on the proposals as detailed within the Report to the Executive on 20 th July 2011. Ward Members views on the outcome of the tender exercise have not been sought.

2 3. COMMENTARY

3.1At the Renewal and Recreation Portfolio Holder Committee meeting and the PDS Committee meeting on 17 November 2012, Officers reported that the tendering exercise undertaken to identify a leisure investment and management company that would build and operate a new multi sport hub site at Norman Park at no cost to the Council, had not resulted in any suitable companies being identified.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Norman Park UpdateReport 76 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. Norman Park UpdateThis decision
  2. Norman parkApproved
  3. Norman parkApproved
  4. Norman park athletics track - future proposalsDecided

More from Bromley Renewal, Recreation and Housing Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Minutes of the renewal, recreation and housing pds committee meeting held on 9 june 2026That the minutes of the meeting held on 9 June 2026 be agreed and signed as a correct record. Agreed Open
1 Sep 2026 Matters outstanding and forward work programmethat the report be noted. Noted Open
1 Sep 2026 Housing, planning and regeneration portfolio plan update 2026/27 q1 updateThat progress on the actions associated with the Housing, Planning and Regeneration Portfolio Plan for Quarter 1 of t... Noted Open
1 Sep 2026 Budget monitoring reportThat the recommendations in the report be supported. Decided Open
1 Sep 2026 Capital programme monitoring - quarter 1 2026/27That the recommendations in the report be supported. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies