PROCUREMENT STRATEGY FOR NON-PROGRAMMED PARKS WORKS EXPENDITURE AND SOFT LANDSCAPING PROCUREMENT

Agreed Scrutiny 1 paper

Environment and Community Services Policy Development and Scrutiny Committee agreed this item on Wednesday 29 January 2014. Below is the council's own wording, with the papers it was decided on.

Item36e

Resolved

RESOLVED that the Portfolio Holder be recommended to: (1) agree that all the non-programmed works for parks outlined in Report ES13128 , be subjected to market testing rather than offered to existing term contractors, in order to obtain favourable costs at competitive rates for the works; and (2) approve the tendering timetable for the works as outlined in Report ES13128 and Appendix C to the report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Environment and Community Services Policy Development and Scrutiny Committee

Report No. London Borough of Bromley ES13128 PART ONE - PUBLIC

Decision Maker: Environment Portfolio Holder

For Pre-Decision Scrutiny by the Environment PDS Committee on Date: 29th January 2014 Decision Type: Non-Urgent Executive Non-Key

Title: PROCUREMENT STRATEGY FOR NON-PROGRAMMED PARKS WORKS EXPENDITURE

Contact Officer: Dan Jones, Assistant Director Street Scene and Green Space Tel: 0208 313 4211 E-mail: [email protected]

Chief Officer: Nigel Davies, Executive Director of Environment & Community Services

Ward: All

1. Reason for report

This Gateway Report seeks approval for the proposed procurement strategy for Parks Works Expenditure not already captured in the Term Contracts.

________________________________________________________________________________

2. RECOMMENDATION(S)

That the Environment Portfolio Holder:

2.1Approves the Procurement strategy for the different elements of Parks Non-Term Contract Works expenditure, as set out below:

1. Approve the strategy for Play works expenditure as set out in Paras 3.15 to 3.16.

2. Approve the strategy for Hard Landscaping as set out in Para 3.17

3. Approve the Strategy for Parks Furniture procurement as set out in Paras 3.21 to 3.22

4. Approve the strategy for Soft Landscape Works as set out in Paras 3.27 to 3.28.

5. Approve the strategy for Plants Shrubs and bedding as set out in Para 3.31

1 Corporate Policy 1. Policy Status: Existing Policy: 2. BBB Priority: Excellent Council Quality Environment : ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated Cost £509k per annum 2. Ongoing costs: Recurring Cost £509k per annum 3. Budget head/performance centre: Parks and Greenspace 4. Total current budget for this head: £509k 5. Source of funding: Existing revenue budget 2013/14 ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 2 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: Non-Statutory - Government Guidance 2. Call-in: Applicable: ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Number of users unknown but LBB Parks and open spaces are available to be used by all residents and visitors ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Not Applicable 2. Summary of Ward Councillors comments:

2 3. COMMENTARY

3.1In 2012 an Internal Audit review of Parks & Greenspace division’s procurement of non- programmed works highlighted a number of issues that needed to be addressed to ensure compliance with: the Council’s Standing Orders and Financial regulations; best practice in procurement; and to demonstrate value for money.

3.2This report outlines the work undertaken since that time to address these concerns, and proposes a long-term strategy for the commissioning of work in this area. This aligns with the overall strategy for procurement of Grounds Maintenance services, to provide maximum flexibility over future contracting options at the conclusion in 2017 of the current contract with The Landscape Group.

Commissioning Strategy for Works Expenditure outside Term Contracts

3.3An exercise was undertaken to examine non-programmed works expenditure over a 23 month period (1 April 2011 – 22 March 2013). This sought to identify opportunities to rationalise expenditure, identify common elements across different sections, and consequently draw together a targeted spend profile, highlighting those areas which would lend themselves to a common procurement approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PROCUREMENT STRATEGY FOR NON-PROGRAMMED PARKS WORKS EXPENDITURE AND SOFT LANDSCAPING PROCUREMENTReport 345 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. PROCUREMENT STRATEGY FOR NON-PROGRAMMED PARKS WORKS EXPENDITURE AND SOFT LANDSCAPING PROCUREMENTThis decision
  2. Gateway 0, commissioning strategy for transport services prior to proceeding to procurementAgreed
  3. Gateway 0: initial procurement strategy for provision of care services in extra care housing.Approved
  4. Gateway 0: initial procurement strategy for provision of care services in extra care housingNoted
  5. Procurement strategy for insurance claims handling agreementDecided
  6. Gateway 0, commissioning strategy for transport services prior to proceeding to procurementNoted

More from Bromley Environment and Community Services Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
17 Jun 2026 MINUTES OF THE MEETING HELD ON 17th MARCH 2026RESOLVED that the minutes of the meeting that took place on 17 th March 2026 be noted and agreed as a correct record. Noted Open
17 Jun 2026 Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding... Noted Open
17 Jun 2026 Update from the portfolio holder for transport, highways and road safetyRESOLVED that the update from the Portfolio Holder for Transport, Highways and Road Safety be noted. Noted Open
17 Jun 2026 Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a... Noted Open
17 Jun 2026 Draft Air Quality Action Plan 2026-2031: Consultation and Implementation (TO FOLLOW)RESOLVED that: 1) The draft AQAP 2026-2031 be subject to public and stakeholder consultation for a period of six week... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies