Environment and Community Services Policy Development and Scrutiny Committee approved this item on Wednesday 29 January 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Portfolio Holder be recommended to: (1) approve the tender process to bring the six soft landscape elements into one package, to be tendered as one contract from May 2014 to December 2017; with the option of awarding single or multiple elements to a single provider or a number of providers; and based on a term co-terminus with the expiry of existing contracts in December 2017; and (2) approve the tendering timetable outlined in Report ES14018 for soft landscape works.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report to Environment and Community Services Policy Development and Scrutiny Committee
Report No. London Borough of Bromley ES14018 PART ONE - PUBLIC
Decision Maker: Environment Portfolio Holder
For Pre-Decision Scrutiny by the Environment Policy Development and Scrutiny Committee on Date: 29th January 2014 Decision Type: Non-Urgent Executive Non-Key
Title: SOFT LANDSCAPING PROCUREMENT
Contact Officer: Dan Jones, Assistant Director Street Scene and Green Space Tel: 0208 313 4211 E-mail: [email protected]
Chief Officer: Nigel Davies, Executive Director of Environment & Community Services
Ward: All
1. Reason for report
This Gateway Report seeks approval for the Soft Landscaping tendering process. This is consistent with the procurement strategy for Non-Programmed Parks Works reported elsewhere on this agenda. The recommendation seeks to ensure maximum flexibility at the end of the current Main Term Contract for Grounds Maintenance in December 2017. Appendix 1 details the current contracts in place, the corresponding contractors and the value.
2.1Approves the tender process to bring the six soft landscape elements into one package, to be tendered as one contract from May 2014 to December 2017; with the option of awarding single or multiple elements to a single provider or a number of providers; and based on a term co-terminus with the expiry of existing contracts in December 2017.
1 Corporate Policy 1. Policy Status: Existing Policy 2. BBB Priority: Quality Environment ________________________________________________________________________________ Financial 1. Cost of proposal: Estimated Cost £183k per annum (£732k over 4 years) 2. Ongoing costs: £183k per annum 3. Budget head/performance centre: Parks and Greenspace 4. Total current budget for this head: £183k
5. Source of funding: Existing revenue budget 2013/14 ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 1 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: Non-Statutory - Government Guidance: 2. Call-in: Applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): Number of users unknown but LBB Parks and open spaces are available to all residents and visitors ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Not Applicable 2. Summary of Ward Councillors comments:
2 3. COMMENTARY
3.1An Internal Audit review of Parks non- programmed works procurement in 2012 highlighted a number of issues that needed to be addressed to ensure compliance with: Council Standing Orders, Financial regulations and best practice in procurement; and to demonstrate value for money.
3.2An exercise was undertaken to examine non-programmed works expenditure over a 23 month period to: identify what opportunities there were to group the spend; note common elements across different sections; and as a consequence draw together a targeted spend profile, highlighting those areas which would lend themselves to a shared procurement approach. The objective was, through improved procurement, to realise the potential to achieve increased savings and demonstrate better value for money.
3.3The spend analysis identified a number of areas that appeared to share common themes. Through consolidation these could be combined into a package more attractive to the market, and reduce the workload involved in commissioning separate contracts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Community Services Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
Matters arising and work programmeRESOLVED that the Matters Arising and Work Programme report be noted and that the issue of finalising any outstanding...
Ecs performance overview quarter 4RESOLVED that the Environment and Community Services Policy Development and Scrutiny Committee note the performance a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.