BROMLEY YOUTH EMPLOYMENT PROJECT: PERFORMANCE UPDATE FOR QUARTER 2

Approved Executive 1 paper

Executive, Resources and Contracts Policy Development and Scrutiny Committee approved this item on Wednesday 5 February 2014. Below is the council's own wording, with the papers it was decided on.

Item440a

Resolved

RESOLVED that the proposals to terminate the contract for the delivery of the Bromley Youth Employment Project with Bromley College by providing three months notice, to reallocate the earmarked reserve to support the objectives behind the Project and to approve a task and finish group overseen by a Member Working Group to undertake an options appraisal be supported.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive, Resources and Contracts Policy Development and Scrutiny Committee

Report No. London Borough of Bromley DRR14/015 PART ONE - PUBLIC

Decision Maker: RESOURCES PORTFOLIO HOLDER

For Pre-Decision Scrutiny by the Executive and Resources Policy Date: Development and Scrutiny Committee on Wednesday 5 February 2014 Decision Type: Non-Urgent Non-Executive Key Non-Key

Title: BROMLEY YOUTH EMPLOYMENT PROJECT: PERFORMANCE UPDATE FOR QUARTER 2

Contact Officer: Colin Brand, Assistant Director Leisure and Culture Tel: 0208 313 4107 E-mail: [email protected]

Chief Officer: Nigel Davies, Executive Director of Environment & Community Services

Ward: (All Wards);

1. Reason for report

1.1This report provides a progress update on the delivery of the Bromley Youth Employment Project which is being delivered by Bromley College of Further and Higher Education on behalf of the Council.

1.2After disappointing performance in the first quarter, this report outlines the College’s performance in the second quarter and identifies that a satisfactory improvement has not been achieved.

1.3Although the College have recovered their performance in relation to the delivery of apprenticeships, they have conceded that they will not recover their performance in relation to the internship profile over the life of the project.

1.4This report therefore recommends that members terminate the contract with the College for the delivery of this project. As the contract specification included a payment mechanism whereby funds will only be released when evidence is released to substantiate that specific outcomes have been achieved or delivered, this report considers further options open to members with regard to the outstanding balance of money.

1.5Given the changes to employment support for young people and the reduced number of young people claiming Job Seekers Allowance in the borough, it is recommended that a task and finish group be established, overseen by a member working party, to consider alternative ways to deliver the Council’s objectives relating to youth unemployment in a second phase of support.

1 ________________________________________________________________________________

2. RECOMMENDATION(S)

2.1The Executive and Resources PDS Committee is asked to examine Bromley College’s progress in delivering the project and consider the report’s recommendations for the future of the project and provide their comments to the Resources Portfolio Holder.

2.2It is recommended that the Resources Portfolio Holder, after reviewing Bromley College’s progress in the delivery of the project, agree to:

 Terminate the contract with the College for the delivery of the Bromley Youth Employment Project by providing three months’ notice following the decision.

 Approve the reallocation of the earmarked reserve to support the objectives identified in paragraph 3.21

 Approve the creation of a task and finish group, overseen by a member working party, to undertake an options appraisal to identify the best way to achieve those objectives, with a report being brought back with the outcome of that appraisal in June 2014.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BROMLEY YOUTH EMPLOYMENT PROJECT: PERFORMANCE UPDATE FOR QUARTER 2Report 361 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. BROMLEY YOUTH EMPLOYMENT PROJECT: PERFORMANCE UPDATE FOR QUARTER 2This decision
  2. Annual update from bromley youth councilNoted
  3. Bromley Youth Council Mid Year ReportNoted
  4. Bromley Youth Justice Service UpdateDecided
  5. Bromley youth employment scheme project extensionAgreed
  6. Bromley youth employment project - progress updateNoted

More from Bromley Executive, Resources and Contracts Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Matters outstanding and work programmeThat the report be noted. Noted Open
14 Sep 2026 Capital programme monitoring - quarter 1 2026/27That the recommendations be supported. Decided Open
14 Sep 2026 Pre-decision scrutiny of executive reportsThat the recommendations be supported. (6) CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27 Report FSD26037 The repor... Noted Open
14 Sep 2026 Corporate contracts registerThat the report be noted. Noted Open
14 Sep 2026 Risk registersThat the report be noted. Noted Open