London Borough of Bromley

CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27

Decided Executive 1 paper

AI summaryBromley Executive, Resources and Contracts scrutiny committee has supported Q1 2026/27 capital programme recommendations, with full financial details to go to the Executive on 16 September 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedQ1 2026/27 capital programme monitoring supported
Money£5.25mAnticipated total spend for Churchill Court Phase 4
What happens next16 September 2026Full financial implications to go to Executive
Who it affectsCouncil services and residentsProperty schemes, IT systems, social care systems

What was decided

The committee supported the recommendations on capital programme monitoring for quarter 1 2026/27.

Full financial implications will be reported to the Executive on 16 September 2026, with changes to the Resources, Commissioning and Contract Management portfolio capital programme set out in the appendix. Report 5.1

Why

Capital programme monitoring and review is part of the planning and review process for all council services. Report 6.1

The capital review process requires Chief Officers to ensure that bids for capital investment provide value for money and match Council plans and priorities. Report 6.1

What happens next

Full financial implications to be reported to the Executive on 16 September 2026. Report 5.1

Officers are reviewing options for the SharePoint Productivity Platform upgrade or replacement, with recommendations to be presented through the council's governance process before implementation. Report P9

An Executive paper will be brought forward in September to draw down funds and set the programme for Facilities Management Planned Works. Report P8

The money

  • circa. £5.25m (Net) Anticipated total project spend for Churchill Court Phase 4 (HWBC) Report P8
  • £6k Miscoding on Churchill Court to be corrected Report P8

Options considered

  • Chosen: Support the recommendations. Standard capital programme monitoring report for the portfolio
  • Rejected: Not support the recommendations

Implications

  • Financial: Full financial implications to be reported to the Executive on 16 September 2026; the report notes the need to draw down funds for Facilities Management Planned Works. Report 5.1, P8
  • Risk: PSTN Switch Off work is described as essential to continuity of service, reducing operational risk, and maintaining compliance with nationally mandated transition timescales. Report P9
  • Staffing: Recruitment will take place to determine the full programme of Facilities Management Planned Works once the Executive paper is approved. Report P8

Who and where

  • Residents receiving adult day services at OPR sites including Widmore Road, Rydal Mount, Blenheim (Saxon Centre) and Astley Report P8
  • NHS users of Churchill Court Phase 4 (1st floor), where the 12-month rectification period ends on 12 December 2026 Report P8
  • Council staff using IT systems including financial, payroll, social care case management, IT infrastructure, SharePoint and telephony Report P8, P9

Timeline

  • Q1 2026/27: Reporting period for the capital programme monitoring Report P7
  • 16 September 2026: Full financial implications to be reported to the Executive Report 5.1
  • September (Executive paper): Paper to draw down funds for Facilities Management Planned Works Report P8
  • 12 December 2026: End of 12-month rectification period for Churchill Court Phase 4 Report P8

Plain English for the jargon

  • OPR: Older Persons Resources, used in scheme names for adult social care properties and services
  • PSTN Switch Off: The national switch-off of the Public Switched Telephone Network, requiring migration to alternative telephony
  • HWBC: Health and Wellbeing Centre, referring to Churchill Court Phase 4
  • RAAC: Reinforced Autoclaved Aerated Concrete, a building material subject to a survey and works programme
  • FRI lease: Full Repairing and Insuring lease, where the tenant is responsible for all repairs and insurance
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item30a

Resolved

That the recommendations be supported.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive, Resources and Contracts Policy Development and Scrutiny Committee

Report No. London Borough of Bromley FSD26039 PART 1 – PUBLIC

Title: CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27

Decision Maker: PORTFOLIO HOLDER FOR RESOURCES, COMMISSIONING AND CONTRACT MANAGEMENT

Date: 14 September 2026

For Pre-Decision Scrutiny by the Executive, Resources and Contracts Policy Development and Scrutiny

Decision Type: Non-Urgent Executive Non-Key

Contact Officer: Abdul Munim, Head of Capital, Treasury and Banking Tel: 0208 313 4334 E-mail: [email protected]

Chief Officer: Peter Turner, Director of Finance

Ward(s): N/A

1. REASON FOR REPORT

1.1On 16 September 2026, the Executive will receive a report summarising the current position on capital expenditure and receipts following the first quarter of 2026/27 and be asked to agree a revised capital programme for the period 2026/27 to 2030/31. This report highlights changes to be considered by the Executive in respect of the capital programme for the Resources, Commissioning and Contract Management portfolio. The revised programme for this portfolio is set out in Appendix A and detailed commen ts on individual schemes are shown in Appendix B; while Appendix C details the variance between the 2025/26 budget and the outturn position at year end.

________________________________________________________________________________

2. RECOMMENDATION(S)

The Portfolio Holder is asked to note and acknowledge the current position in respect of capital schemes, to be considered by the Executive on 16 September 2026.

1 3. KEY SUMMARIES ________________________________________________________________________________ Financial 1. Cost of proposal: Not Applicable 2. Ongoing costs: Not Applicable 3. Budget head/performance centre: Capital Programme 4. Total current budget for this head: £34.2m 5. Source of funding: Capital grants, capital receipts, external borrowing and earmarked revenue reserves. ________________________________________________________________________________ Legal 1. Legal Requirement: Non-Statutory - Government Guidance 2. Call-in: Not Applicable ________________________________________________________________________________

Background Capital programme monitoring Q1 25/26 (Executive 17/09/2025) Documents: Capital programme monitoring Q2 25/26 (Executive 26/11/2025) (Access via Contact Capital programme monitoring Q3 25/26 (Executive 11/02/2025) Officer) Capital programme Outturn 25/26 (Executive 24/06/2026)

2 4. COMMENTARY

Capital monitoring – variations to be considered by the Executive on 16 September 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING: QUARTER 1 2026/27Report 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 18 attended
SS
Councillor Shaun SlatorChairman, present
AD
Councillor Andy DourmoushVice-Chairman, present
JA
Councillor Jeremy AdamsCommittee Member, present
GB
Councillor George BarnesCommittee Member, present
KB
Councillor Kim Botting FRSACommittee Member, apologies, sent representative
MB
Councillor Mark BrockCommittee Member, present
AJ
Councillor Adam Jude GrantCommittee Member, present
CM
Councillor Christopher MarlowCommittee Member, present
RM
Councillor Ruth McGregorCommittee Member, present
AM
Councillor Alexa MichaelCommittee Member, present
TO
Councillor Tony OwenCommittee Member, present
IF
Councillor Ian F. PayneCommittee Member, present

All 18 on the meeting page

On this subject at Bromley

Search all
  1. CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27This decision
  2. Capital programme monitoring - quarter 1 2026/27Noted
  3. 2026/27 q1 capital programme monitoringNoted
  4. Capital programme monitoring - quarter 1 2026/27Decided
  5. Capital programme monitoring - quarter 1 2026/27Decided
  6. Capital programme monitoring - quarter 3 2025/26Noted

More from Bromley Executive, Resources and Contracts Policy Development and Scrutiny Committee

All decisions
MeetingDecisionOutcome
14 Sep 2026 Matters outstanding and work programmeThat the report be noted. Noted Open
14 Sep 2026 Pre-decision scrutiny of executive reportsThat the recommendations be supported. (6) CAPITAL PROGRAMME MONITORING - QUARTER 1 2026/27 Report FSD26037 The repor... Noted Open
14 Sep 2026 Corporate contracts registerThat the report be noted. Noted Open
14 Sep 2026 Risk registersThat the report be noted. Noted Open