RESOLVED that (1) The Variation to the current Grounds Maintenance Contract with the Landscape group to include the functions outlined in the Report, and extend the Contract to 31 st March 2019 to allow the packaging and tendering of all Streetscene & Greenspace Contracts at that date, be approved. (2) The transfer of Parks and Greenspace Services and the associated staff, as outlined in Appendix A to the report, to The Landscape Group, be approved as outlined in the report. (3) Authority be delegated to the Executive Director of Environment and Community Services, in consultation with the Director of Resources, to transfer the unplanned maintenance functions associated with parks and greenspaces to The Landscape Group if deemed appropriate.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
2.1That the Environment Policy Development and Scrutiny Committee is asked to comment on the proposals in the report, noting the comments from staff, stakeholders and staff representatives as outlined in Appendix B.
2.2That the Executive is asked to: i. Approve the Variation to the current Grounds Maintenance Contract with the Landscape group, to include the functions outlined in this Report, and extend the Contract to 31st March 2019 to allow the packaging and tendering of all Streetscene & Greenspace Contracts at that date; ii. Agree the transfer of Parks and Greenspace Services and the associated staff, as outlined in Appendix A, to The Landscape Group, as outlined in this report;
1 iii. Delegate to the Executive Director of Environment and Community Services, in consultation with the Director of Resources, the authority to transfer the unplanned maintenance functions associated with parks and greenspaces to The Landscape Group if deemed appropriate.
2 Corporate Policy 1. Policy Status: Existing Policy: 2. BBB Priority: Quality Environment: ________________________________________________________________________________ Financial 1. Cost of proposal: £9.7m for the variation and extension of existing contract to 31.3.19, with an option to add a further £0.7m for reactive property maintenance. Potential redundancy costs of between £200k and £300k. 2. On-going costs: Part year savings of between £70k to £110k (2015/16) and full year savings of between 250k and £300k (2016/17 onwards) 3. Budget head/performance centre: Street Scene and Green Space Division 4. Total current budget for this head: £30.8m 5. Source of funding: Existing controllable revenue budget for 2015/16 ________________________________________________________________________________ Staff 1. Number of staff (current and additional): 80 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: Statutory and Non-Statutory - Government Guidance: 2. Call-in: Applicable: ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): All residents ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Not Applicable 2. Summary of Ward Councillors comments: N/A
3 3. COMMENTARY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.