RESOLVED that (1) The expiry of the Exclusivity Agreement with ZRG be noted. (2) The exploration and development of a sustainable business plan for the establishment of an alternative management option for Crystal Palace Park be approved as set out in section 3; the progress made on this business planning work will be reported back to Members in autumn 2015, with an expected request to Members to proceed with the formation of a Trust or other not-for-profit management option. (3) Up to £495k in capital receipts be contributed and added to the capital programme for the development of an alternative management option and a capital scheme for the improvement of the park in line with the Masterplan, as set out in section 3 of the report. (4) It is approved in principle that capital receipts generated through the implementation of the Masterplan will be reinvested in the park, contributing to the development of a sustainable business plan for the park. (5) The delivery of the six Crystal Palace Park Improvement Scheme projects at a total cost of £2.16m be approved subject to any necessary statutory consents, as set out in section 4 of the report. (6) Confirmation of the £1.84m from the GLA is noted. (7) The £1.84m balance of funding from the GLA will not directly lead to a reduction in revenue funding for the park, and that additional income from the café will be ring fenced for the park, as set out in section 4 of the report. (8) The marketing of a new café lease be approved - the lease for the new premises will be tendered on the open market.
Word for word from the decision Bromley published for this meeting.Source: cds.bromley.gov.uk
Report No. London Borough of Bromley DRR15/020 PART ONE - PUBLIC
Decision Maker: EXECUTIVE
Date: Wednesday 25 March 2015 Decision Type: Non-Urgent Executive Non-Key
Title: CRYSTAL PALACE PARK
Contact Officer: Colin Brand, Assistant Director Leisure and Culture Tel: 0208 313 4107 E-mail: [email protected]
Lydia Coelho, Community Development Manager Tel: 0208 313 4456 E-mail: [email protected]
Chief Officer: Director of Regeneration & Transformation
Ward: Crystal Palace;
1. Reason for report
1.1The Exclusivity Agreement with ZRG expired on 1st February 2015. This Exclusivity Agreement has not been renewed.
1.2Following the end of the ZRG exclusivity agreement, the Crystal Palace Park Executive Board and Community Stakeholder Group wish to twin track the setting up of a new form of governance for the park; and a delivery plan for the park, bringing to fruition aspects of the Masterplan, to realise capital receipts and create revenue generating activity, to enable a sustainable business model for a new form of governance.
1.3Additionally, in July 2014 Members agreed to contribute £160k capital receipts towards the Crystal Palace Park Improvement Scheme. The July report DRR14/069 committed to bringing a further report back to Members in March 2015 following the feasibility works, to confirm which projects would be delivered and to confirm the £1.84m balance of funding from the GLA is secure.
1 Corporate Policy 1. Policy Status: Existing Policy 2. BBB Priority: Quality Environment ________________________________________________________________________________ Financial 1. Cost of proposal: £2.16m for improvement schemes and £495k towards alternative management option 2. Ongoing costs: None expected 3. Budget head/performance centre: Crystal Palace Park 4. Total current budget for this head: £299k£160k, £495k and £2m 5. Source of funding: Existing revenue budget, capital receipts, GLA funding ________________________________________________________________________________ Staff 1. Number of staff (current and additional): N/A 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: None 2. Call-in: Applicable ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): In 2006 the park’s visitor numbers were estimated at 1.68 million. ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? 2. Summary of Ward Councillors comments:
This park is a major resource and the setting up of a community based trust is no small challenge. However we believe the time is right, the proposals sound and that the community has the capacity and abilities to work with the Council to deliver along these lines.
NB. The content of this report was discussed at the Crystal Palace Executive Project Board meetings on the 9 February 2015 and the 26 February 2015. A local ward councillor is a member of this Board and was present at both meetings.
2 3. COMMENTARY
Exclusivity agreement with ZRG
3.1At the 16th October 2013 Executive Committee (report no. DRR13/131) Members agreed to grant ZhongRong International Group (ZRG) an exclusivity agreement for a period of 16 months, to allow negotiations to take place between ZRG and the Council on the development of a capital scheme on the top site of Crystal Palace Park. ZRG’s proposal was to rebuild the Crystal Palace on the top site, and restore the wider park in line with the agreed Masterplan. The cost of implementing the Masterplan was estimated at £100m, and therefore this proposal had potential to be of huge financial benefit to the park.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.