PROVISION OF HOUSING AND LIBRARY IMPROVEMENT WORKS IN WEST WICKHAM TOWN CENTRE

Approved Executive 6 papers

Executive approved this item on Wednesday 24 November 2021. Below is the council's own wording, with the papers it was decided on.

Item335

Resolved

RESOLVED that (1) The RIBA Stages 0-3 work undertaken proposing the redevelopment of the library and Station Road Car Park sites for housing, the expansion of the library, public realm improvements and the adoption of a service road to provide access be noted. (2) That Council be recommended to approve the addition of the scheme to the Capital Programme at an estimated cost of £9,641k (it is noted that this is the scheme cost, not the cost to the Council.) (3) That Council be recommended to approve the financing of the scheme as set out in paragraph 10.8 of the report, including an internal loan from the General Fund to the Housing Revenue Account of £2,147k. (4) The rent levels of the affordable housing be approved at London Affordable Rent (LAR) levels to utilise the GLA Building Homes for Londoners Grant. (5) The undertaking of the adoption of the service road off Croft Avenue which is required for access to the scheme be approved. (6) The spend of £173k to date, which is included in the capital scheme costs, be retained in the Housing Investment Fund earmarked reserve. (7) The utilisation of £356k Section 106 contributions towards the affordable housing element of the proposals be approved. (8) Approval to proceed to procurement for the design and build works contract at the end of RIBA Stage 4 with an estimated value of £8m be delegated to the Director of Housing, Planning, Property and Regeneration in consultation with the Renewal, Recreation and Housing Portfolio Holder, noting that a contract award will be coming back to Committee. (9) Authority be delegated to the Director of Housing, Planning, Property and Regeneration in consultation with the Director of Corporate Services and Governance and the Director of Finance to appropriate the affordable housing element of the site on completion of the construction works from planning purposes to housing within the Housing Revenue Account and any other appropriation. (10) It is noted that the land appropriation value to the HRA of the affordable housing element of the site has been independently valued at £260k. (11) It is noted that the Council is foregoing a potential capital receipt of £1,270k from the housing part of the site, for the development to continue in line with the recommendations, and to achieve the Temporary Accommodation savings and a new library.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Exec 241121 West Wickham Appendix 1 Design Access Statement 2of2Appendix 11 MB Copy on its way
PDF
Exec 241121 West Wickham Appendix 2 West Wickham Library Physical Condition SurveyAppendix 5 MB Copy on its way
PDF
Exec 241121 West Wickham Appendix 3 Statement Community InvolvementAppendix 2 MB Copy on its way
PDF
Exec 241121 West Wickham Appendix 4 TransportAppendix 7 MB Copy on its way
PDF
Exec 241121 West Wickham Appendix1 Design Access Statement 1of2Appendix 12 MB Copy on its way
PDF
PROVISION OF HOUSING AND LIBRARY IMPROVEMENT WORKS IN WEST WICKHAM TOWN CENTREReport 465 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. PROVISION OF HOUSING AND LIBRARY IMPROVEMENT WORKS IN WEST WICKHAM TOWN CENTREThis decision
  2. Gateway 0: initial procurement strategy for provision of care services in extra care housing.Approved
  3. Gateway 0: initial procurement strategy for provision of care services in extra care housingNoted
  4. Provision of affordable housing in west wickhamApproved
  5. Provision of housing and library improvement works in west wickham town centreNoted
  6. Provision of housing at west wickham library and station road car park, west wickham (part 1)Noted

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open