BROMLEY NORTH HOUSING PROJECT UPDATE AND AWARD OF WORKS CONTRACT

Approved Executive 1 paper

Executive approved this item on Wednesday 22 January 2025. Below is the council's own wording, with the papers it was decided on.

Item141

Resolved

That 1. A supplementary capital estimate of £ 6.2m be approved to cover construction price inflation since September 2023 when the scheme was originally added to the Capital Programme at an estimate of £ 25.5m , and to cover an increased contingency allowance, noting that even with this increase the savings to the Council are improved. 2. The revised financing of the scheme as set out in paragraph 6.4 of the report be approved. 3. The further recommendations in relation to the award of the works contract set out in Part 2 be noted. 4. The tenure change of Block 02 in the scheme to affordable housing be approved. 5. It be noted that this scheme will be progressed subject to a Secretary of State Direction to either (a) hold the properties outside of the Housing Revenue Account ( HRA ) or (b) by Secretary of State’s Direction to allow the transfer of an appropriate sum from the General Fund to the HRA as set out in Paragraph 6.6 of the report.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
BROMLEY NORTH HOUSING PROJECT UPDATE AND AWARD OF WORKS CONTRACTReport 820 KB Copy on its way

At this meeting

Whole meeting
126APOLOGIES FOR ABSENCEDecided 127DECLARATIONS OF INTERESTDecided 128QUESTIONSDecided 129TO CONFIRM THE MINUTES OF THE MEETINGS HELD ON 27 NOVEMBER 2024 AND 9 DECEMBER 2024Agreed 130DRAFT BUDGET 2025/26 AND UPDATE ON THE COUNCIL'S FINANCIAL STRATEGYAgreed 131COUNCIL TAX SUPPORT SCHEME FROM 2025/26Noted 132TRANSFORMING BROMLEY 2024-28 YEAR ONE PROGRESS REPORT 2024/25Noted 133EXTENDED OPERATIONAL PROPERTY REVIEWAgreed 134HOMES FOR UKRAINENoted 135WELFARE FUND - ESSENTIAL HOUSEHOLD GOODS PART 1 (PUBLIC) REPORTNoted 136BROMLEY HOMES FOR BROMLEY RESIDENTS - ACQUISITION PROGRAMMEApproved 137CRYSTAL PALACE PARK REGENERATION PLAN UPDATE AND AWARD OF MAIN WORKS CONTRACTApproved 138APPROPRIATION FOR PLANNING PURPOSES IN RELATION TO PROPERTY AT BECKENHAM CAR PARK AND PROPERTY AT MANORFIELDS AND APPROVAL OF A TENDER FOR THE BECKENHAM HOUSING DEVELOPMENT PART 1 (PUBLIC) REPORTAgreed 139WEST WICKHAM ENABLING WORKS PHASE 2Agreed 140CONNECT TO WORK PROGRAMMEDecided
141BROMLEY NORTH HOUSING PROJECT UPDATE AND AWARD OF WORKS CONTRACTThis decision
142CONSIDERATION OF ANY OTHER ISSUES REFERRED FROM THE EXECUTIVE, RESOURCES AND CONTRACTS POLICY DEVELOPMENT AND SCRUTINY COMMITTEEDecided 143LOCAL GOVERNMENT ACT 1972 AS AMENDED BY THE LOCAL GOVERNMENT (ACCESS TO INFORMATION) (VARIATION) ORDER 2006 AND THE FREEDOM OF INFORMATION ACT 2000Agreed 144EXEMPT MINUTES OF THE MEETINGS HELD ON 27 NOVEMBER 2024 AND 9 DECEMBER 2024Agreed 145PART 2: EXTENDED OPERATIONAL PROPERTY REVIEWPrivate 146PART 2: WELFARE FUND - ESSENTIAL HOUSEHOLD GOODS REPORTDecided 147PART 2: CRYSTAL PALACE PARK REGENERATION PLAN UPDATE AND AWARD OF MAIN WORKS CONTRACTPrivate 148PART 2: APPROPRIATION FOR PLANNING PURPOSES IN RELATION TO PROPERTY AT BECKENHAM CAR PARK AND PROPERTY AT MANORFIELDS AND APPROVAL OF A TENDER FOR THE BECKENHAM HOUSING DEVELOPMENT REPORTPrivate 149PART 2: BROMLEY NORTH HOUSING PROJECT UPDATE AND AWARD OF WORKS CONTRACTPrivate 25Appendix AOn the agenda

On this subject at Bromley

Search all
  1. BROMLEY NORTH HOUSING PROJECT UPDATE AND AWARD OF WORKS CONTRACTThis decision
  2. (25/01757/full1) - land north of dobbie’s garden centre, oakley road, bromleyDecided
  3. (18/04769/TPO) - 5 Northumberland Gardens, Bickley, Bromley, BR1 2XDRefused
  4. Bromley north village final evaluation reportNoted
  5. Bromley North Village Public Realm ImprovementsApproved
  6. Bromley north village - public realm improvements outline designAgreed

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies