Resolved
RESOLVED that the results of the evaluation report and the outcomes of the delivered public realm improvements to Bromley North Village be noted.
Renewal, Recreation and Housing Policy Development and Scrutiny Committee noted this item on Thursday 26 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the results of the evaluation report and the outcomes of the delivered public realm improvements to Bromley North Village be noted.
Report No. London Borough of Bromley DRR17/008 PART ONE - PUBLIC
Decision Maker: RENEWAL AND RECREATION POLICY DEVELOPMENT AND SCRUTINY COMMITTEE Date: Tuesday 26 January 2017 Decision Type: Non-Urgent Non-Executive Non-Key
Title: BROMLEY NORTH VILLAGE POST SCHEME EVALUATION UPDATE
Contact Officer: Kevin Munnelly, Head of Renewal Tel: 020 8313 4582 E-mail: [email protected]
Chief Officer: Executive Director of Environment & Community Services
Ward: Bromley Town;
1. Reason for report
1.1Public Realm improvements to Bromley North Village have been a key part of the improvement programme for Bromley Town Centre as set out in the Bromley Town Centre Area Action Plan. The improvement works to the original scheme area were substantially completed in November 2014. An initial evaluation of the scheme was completed in February 2015 as part of the Outer London Fund Programme.
1.2This report provides Members with the results of a 2 year post-scheme evaluation which focuses on assessing the impact of the improvements on businesses and town users, particularly bus users.
________________________________________________________________________________
2. RECOMMENDATION(S)
2.1That Members note the results of the evaluation report and the outcomes of the delivered public realm improvements to Bromley North Village.
1 Impact on Vulnerable Adults and Children
1. Summary of Impact: NA ________________________________________________________________________________ Corporate Policy
1. Policy Status: Not Applicable: 2. BBB Priority: Quality Environment Safer Bromley Vibrant, Thriving Town Centres: ________________________________________________________________________________ Financial 1. Cost of proposal:: N/A as this is a post completion report 2. Ongoing costs: N/A 3. Budget head/performance centre: Capital Programme 4. Total current budget for this head: £6.652m 5. Source of funding: TfL funding, Outer London Funding & LBB capital receipts ________________________________________________________________________________ Personnel 1. Number of staff (current and additional): 5 2. If from existing staff resources, number of staff hours: ________________________________________________________________________________ Legal 1. Legal Requirement: None: 2. Call-in: Applicable: ________________________________________________________________________________ Procurement 1. Summary of Procurement Implications: Single Quote from RFQ under £5k ________________________________________________________________________________ Customer Impact 1. Estimated number of users/beneficiaries (current and projected): ________________________________________________________________________________ Ward Councillor Views 1. Have Ward Councillors been asked for comments? Yes 2. Summary of Ward Councillors comments: Ward Councillors support the need for post scheme evaluation.
2 3. COMMENTARY
3.1During the period from 2012 to 2015, the Council implemented a programme of physical interventions in Bromley North Village (BNV) with the objective of improving the evening economy, providing better wayfinding and creating a clear identity for BNV. It has been assessed through detailed analysis that the benefits derived include increased footfall and the overall economic vitality by generating inward investment that has resulted in a general improvement in the overall appearance and perception of the area.
3.2As reported in the last R&RPDS on 22nd November 2016 [DRR16/083] an initial evaluation of the BNV improvement works was undertaken by Regeneris Consulting in February 2015, as part of the Outer London Fund post scheme evaluation. As previously reported this evaluation report concluded the improvements have contributed to the creation of greater town centre coherency and a stronger and more diverse offer that has changed the perceptions and image of the town centre, thus resulting in making the town centre more competitive in the long term.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BROMLEY NORTH VILLAGE FINAL EVALUATION REPORTReport | 6 pages | DownloadRead as text |
PDF |
Enc. 1 for BROMLEY NORTH VILLAGE POST SCHEME EVALUATIONReport | 20 pages | Download |
Follow Renewal, Recreation and Housing Policy Development and Scrutiny Committee at Bromley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Minutes of the renewal, recreation and housing pds committee meeting held on 9 june 2026That the minutes of the meeting held on 9 June 2026 be agreed and signed as a correct record. | Agreed | Open |
| 1 Sep 2026 | Matters outstanding and forward work programmethat the report be noted. | Noted | Open |
| 1 Sep 2026 | Housing, planning and regeneration portfolio plan update 2026/27 q1 updateThat progress on the actions associated with the Housing, Planning and Regeneration Portfolio Plan for Quarter 1 of t... | Noted | Open |
| 1 Sep 2026 | Budget monitoring reportThat the recommendations in the report be supported. | Decided | Open |
| 1 Sep 2026 | Capital programme monitoring - quarter 1 2026/27That the recommendations in the report be supported. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.