HOUSING SCHEMES PROGRESS COMMITTEE REPORT - PART 1 (PUBLIC) - INCLUDING AWARD OF MAIN WORKS CONTRACT

Noted Executive 1 paper

AI summaryLondon Borough of Bromley Executive has delegated authority to award the Beckenham Housing Scheme works contract and to add £353,962 of Section 106 contributions to the capital programme. The Director of Housing will also bid for GLA affordable homes funding.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedSubject to grant being secured
Money£353,962Total S106 for Beckenham scheme
What happens nextGLA funding bidBid for GLA affordable homes funding
Who it affectsBeckenham Housing SchemeNew council housing in Beckenham

What was decided

Authority has been delegated to the Director of Housing, Planning and Regeneration, in consultation with the Portfolio Holder for Renewal, Recreation and Housing, to finalise contract documentation and enter into a contract with the successful contractor for the Beckenham Housing Scheme, subject to grant monies being secured so the total cost stays within budget.

A supplementary capital estimate of £353,962, funded through Section 106 contributions, is to be added to the capital programme.

Authority has been delegated to submit a bid for the Greater London Authority's London Social and Affordable Homes Programme 2026-36.

What happens next

The Director of Housing, Planning and Regeneration is to finalise the contract and enter into it with the successful contractor for the Beckenham Housing Scheme, once grant monies are secured.

A bid is to be submitted to the Greater London Authority for the London Social and Affordable Homes Programme 2026-36 by the April 2026 deadline.

Any additional grant funding secured for the Beckenham Housing Scheme is to be accepted and added to the capital programme.

The money

  • £40,446.16 Section 106 monies allocated to the Beckenham Housing Scheme in December 2021
  • £101,025.93 Section 106 monies allocated to the Beckenham Housing Scheme in December 2023
  • £212,489.88 Section 106 monies allocated to the Beckenham Housing Scheme in December 2025
  • £353,962 Total Section 106 monies now allocated to the scheme; supplementary capital estimate to be added to the capital programme

Implications

  • Financial: A supplementary capital estimate of £353,962 funded by Section 106 contributions is to be added to the capital programme, and further grant funding is to be sought to keep the scheme within budget.
  • Legal: A contract and any ancillary documentation are to be entered into with the successful contractor for the Beckenham Housing Scheme; further recommendations on the contract award are in the Part 2 report.
  • Other: A bid is to be made to the Greater London Authority for affordable housing funding under the London Social and Affordable Homes Programme 2026-36.

Who and where

  • Beckenham Housing Scheme (new council housing development)
  • Future residents of the Beckenham Housing Scheme

Timeline

  • December 2021: Section 106 monies of £40,446.16 allocated to the Beckenham Housing Scheme
  • December 2023: Section 106 monies of £101,025.93 allocated to the Beckenham Housing Scheme
  • December 2025: Section 106 monies of £212,489.88 allocated to the Beckenham Housing Scheme
  • February 2026: Greater London Authority London Social and Affordable Homes Programme 2026-36 opens for bids
  • April 2026: Deadline for bids to the Greater London Authority London Social and Affordable Homes Programme 2026-36

Plain English for the jargon

  • Section 106: Money that a developer pays to a council as part of a planning permission, used to offset the impact of a new development.
  • GLA: Greater London Authority, the regional governing body for London.
  • Capital programme: A council's planned spending on long-term assets such as buildings and major projects.
  • Supplementary capital estimate: Extra money added to an existing capital programme budget for a specific purpose.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item102

Resolved

That 1. It be noted that the Part 2 report has further recommendations in relation to the award of the Beckenham Housing Scheme works contract. 2. Authority be delegated to the Director of Housing, Planning and Regeneration, in consultation with the Portfolio Holder for Renewal, Recreation and Housing, to finalise contract documentation and enter into a contract and any ancillary documentation with the successful contractor on the Beckenham Housing Scheme, subject to grant monies being secured so that the total cost of the scheme is within budget. 3. Authority be delegated to the Director of Housing, Planning and Regeneration, in consultation with the Portfolio Holder for Renewal, Recreation and Housing, to accept and add to the capital programme any additional grant funding to support delivery of the Beckenham Housing Scheme. 4. It be noted the Beckenham Housing Scheme was allocated Section 106 monies totalling £40,446.16 in December 2021, £101,025.93 in December 2023, and £212,489.88 in December 2025, which brings Section 106 monies allocated to the scheme to a total of £353,962. 5. Approval to include a supplementary capital estimate of £353,962, funded through Section 106 contributions, in the capital programme be requested. 6. Authority be delegated to the Director of Housing, Planning, Property and Regeneration, in consultation with the Portfolio Holder for Renewal Recreation and Housing, to submit a bid for the next round of affordable housing funding administered by the GLA, known as the ‘London Social and Affordable Homes Programme 2026-36’, which opens in February 2026 and has a deadline for bids of April 2026.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
HOUSING SCHEMES PROGRESS COMMITTEE REPORT: PART 1 (PUBLIC): INCLUDING AWARD OF MAIN WORKS CONTRACTReport 866 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. HOUSING SCHEMES PROGRESS COMMITTEE REPORT - PART 1 (PUBLIC) - INCLUDING AWARD OF MAIN WORKS CONTRACTThis decision
  2. Contract monitoring report - extra care housing schemesNoted
  3. Contract monitoring report - extra care housing schemesNoted
  4. Contract monitoring report - extra care housing schemesNoted
  5. Thematic Session: Housing Schemes and the Revenue AccountNoted
  6. Contract monitoring - extra care housing schemesNoted

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies