TRANSFORMING BROMLEY 2024-2028 TWO YEAR PROGRESS REPORT 2025-26

Noted Executive 1 paper

AI summaryBromley Council's Executive noted delivery of £18m in first year transformation savings and endorsed a further £29.3m programme for year two, including £1.5m of staffing cuts.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedStaffing savings of £1.5m agreed through realignment and redundancies
Money£29.3mAdditional year two savings programme endorsed
What happens nextNot stated
Who it affectsCouncil staffPosts deleted or realigned, some redundancies expected

What was decided

The Executive noted delivery of £18m of savings in the first year of the Transformation Programme, equal to 95% of the £18.9m target.

Members endorsed an additional £29.3m year two savings programme as reflected in the Council's Full Budget Report (2026).

The Executive agreed £1.5m of staffing budget savings within that total, to be achieved through realignment, deletion of vacant posts and a small number of redundancies.

Why

The £29.3m year two programme is set out in the Council's Full Budget Report (2026), with £1.5m identified as staffing savings.

What happens next

Deletions of existing vacant posts and realignments will be carried out in line with the Council's Managing Change HR procedures.

Officers were congratulated by the Executive on successful delivery of the programme.

The money

  • £18m First year transformation savings delivered
  • £18.9m Total first year savings target
  • £29.3m Year two savings programme endorsed
  • £1.5 million Staffing budget savings within the year two programme

Implications

  • Staffing: A small number of redundancies are expected, alongside deletion of vacant posts and role realignments, handled under the Council's Managing Change HR procedures.
  • Financial: The total transformation savings target rises from £18.9m in the first year to a further £29.3m in the second year.

Who and where

  • Council staff in posts subject to realignment, deletion of vacant posts, or redundancy

Timeline

  • First year of the Transformation Programme: £18m of £18.9m savings delivered, equal to 95% of target
  • Year two: Additional £29.3m savings programme endorsed for delivery

Plain English for the jargon

  • Realignment: Reorganisation of posts or responsibilities within the council.
  • Managing Change HR procedures: The council's formal process for handling organisational change that affects staff.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item101

Resolved

That 1. The successful delivery of £18m of savings (95% of £18.9m) identified during the first year of the Transformation Programme be noted. 2. An additional £29.3m Year Two savings programme as reflected in the Councils Full Budget Report (2026) be endorsed. 3. £1.5 million of staffing budget savings (included in the £29.3m) to be achieved through realignment, deletion of vacant posts and a small number of redundancies be agreed. The deletion of existing vacant posts and realignments to be in line with the Councils Managing Change HR procedures. 4. Officers be congratulated on the successful delivery of the programme.
Word for word from the decision Bromley published for this meeting. Source: cds.bromley.gov.uk

Follow this further

Built from Bromley's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
TRANSFORMING BROMLEY 2024-2028 TWO YEAR PROGRESS REPORT 2025-26Report 284 KB Copy on its way

At this meeting

Whole meeting

On this subject at Bromley

Search all
  1. TRANSFORMING BROMLEY 2024-2028 TWO YEAR PROGRESS REPORT 2025-26This decision
  2. Transforming bromley 2024-29 year two mid-year report 2026/27Noted
  3. Transforming bromley 2024-28 year one progress report 2024/25Noted
  4. Transforming bromley 2024-28Noted
  5. Transforming bromley 2019--2023: first two yearsNoted
  6. Transforming bromley 2019 - 2023: first two yearsNoted

More from Bromley Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Apologies for absenceNone. Decided Open
16 Sep 2026 Declarations of interestNone. Decided Open
16 Sep 2026 QuestionsTwo written questions. Decided Open
16 Sep 2026 To confirm the minutes of the meeting held on 22 july 2026Agreed. Agreed Open
16 Sep 2026 Budget monitoring 2026-2027That 1. The latest financial position be considered; 2. It be noted that a projected net overspend on services of £4,... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies