RESOLVED a temporary permission of one year be granted with the precise wording to be delegated to the Head of Neighbourhoods and Prosperity in consultation with the Chair of the Planning Committee and also subject to the following conditions: 1. The development hereby permitted shall be retained in accordance with the Block Plan (1:500) received on 3 April 2018 and the Floor Plan and Elevation Plan (1:100) received by the Local Planning Authority on 11 April 2018. 2. The poly tunnel hereby permitted shall be sprayed dark green within 3 months of the date of this decision, and shall thereafter be retained this colour for the lifetime of the development. 3. The permission shall be for a limited period of one year expiring on the 14th September 2019 when the building works carried out under this permission shall be removed and the land reinstated to the satisfaction of the Local Planning Authority unless prior permission has been obtained in writing from the Local Planning Authority for its retention. 4. The poly tunnel hereby permitted shall not be used except between the hours of 09.00 - 18.00 Wednesday to Sunday and 09.00 - 20.00 on Mondays and Tuesdays. Reasons 1. For the avoidance of doubt. 2. To ensure a satisfactory standard of external appearance and in accordance with the aims of Policy 10 of the Aligned Core Strategy (2014) and Policy 17 of the Draft Part 2 Local Plan. 3. The building by virtue of its construction and appearance is not suitable for permanent retention. 4. To protect nearby residents from excessive operational noise. Note to Applicant The Council has acted positively and proactively in the determination of this application by communicating with the agent throughout the course of the application.
Word for word from the decision Broxtowe published for this meeting.Source: democracy.broxtowe.gov.uk
1.1This planning application seeks to retain a poly tunnel at Babbington Hall. The poly tunnel is used in association with the dog rescue centre that is operated from the site and is used as a training space for rescue dogs. It is also used as general behaviour training for dogs not raised at the rescue centre. The poly tunnel has dimensions of 27.47m by 9.18m, with a maximum height of 3.73m.
2 Site and surroundings
2.1The application site is set within the grounds of Babbington Hall, in the south corner of the site adjoining Westby Lane. It is positioned approximately 13.7m from the boundary adjoining Westby Lane, and approximately 6.6m from the south west boundary of the site. There is an existing vehicular access from Westby Lane along the south boundary of the site in close proximity to the poly tunnel. The poly tunnel is positioned on a relatively flat part of the site, although the land slopes up significantly to the north east to where Babbington Hall and the rescue centre is located.
2.2The site is located entirely within the Nottinghamshire Green Belt and within a Mature Landscape Area. The surrounding area largely consists of agricultural land, including Westby House Farm which operates to the south side of Westby Lane. There are a small number of residential dwellings, mainly to the east of the site along Westby Lane.
Elevation facing Westby Lane. North east side elevation.
56 Planning Committee 12 September 2018
Photo taken from the north east of Babbington Hall and Rescue the site close to Babbington Hall. Centre.
Vehicular access to the site from Internal photograph of the poly Westby Lane. tunnel.
3 Relevant Planning History
3.1It is understood that the site has been used for kennelling dogs since 1962. The application site has a detailed planning history and the details of the most relevant historic applications are outlined below.
3.288/00289/FUL - In 1988, planning permission was granted to construct a purpose built cattery building.
3.392/00404/FUL – In 1993, planning permission was granted for the refurbishment of the existing dog pens and an extension to form new pens and a feed store.
3.499/00543/FUL – In 1999, planning permission was granted to extend the residential element of Babbington Hall.
57 Planning Committee 12 September 2018
3.504/00174/FUL – In 2004, planning permission was granted to erect timber stabling at the site. The stables were positioned in the more built up area of the application site, to the north east of Babbington Hall.
3.608/00286/FUL – In 2008, planning permission was granted to construct a new kennel block and to extend the curtilage of the kennelling operation including the change of use of land from agriculture. This application was determined by Planning Committee with the case for Very Special Circumstances being put forward due to the demand for the nature of the applicants work in housing rescue dogs, notably from a number of neighbouring authorities. In this case it was noted that the positioning of the extension to the kennels would not project significantly further into the open countryside when seen in context with the existing buildings on the site. A condition was attached to this permission stating that the development shall only be used for the kennelling of rescue dogs, and for no other purpose.
3.709/00095/FUL – In 2009, planning permission was granted by Planning Committee for the construction of a new building incorporating a reception, office, education centre and staff facilities. Whilst it was established that the development was inappropriate in the Green Belt, it was concluded that the requirement for the facilities in supporting an established kennelling facility represented very special circumstances which outweighed the harm to the Green Belt.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies