22/00166/FUL

Refused Planning 1 paper

Planning Committee refused this item on Wednesday 5 October 2022. Below is the council's own wording, with the papers it was decided on.

Item33.1

Resolved

RESOLVED that planning permission be refused with the precise wording of the refusal delegated to the Chair of the Planning Committee in conjunction with the Head of Planning and Economic Development. Reasons Loss of a heritage asset, biodiversity, net gain and substantial harm caused to the conservation area.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of report

The application is brought to the Committee at the request of Councillor J C Patrick, due to the high level of interest that the proposal has generated.

Recommendation

The Committee is asked to resolve that planning permission be granted subject to conditions outlined in the appendix.

1.3Detail

1.3.1 The application seeks planning permission to demolish Oban House, to facilitate the construction of a detached building for the use as a medical centre, incorporating a pharmacy, along with associated parking, highway and landscape works.

1.3.2 The site contains a three storey Victorian building which was originally a house but was last in use as offices. The site is located within the St John’s Grove Conservation Area and is also a Local Interest Building. The site is also directly adjacent to West End Conservation Area, which is to the south east.

1.3.3 The main issues relate to whether the loss of the building and associated landscaping would result in harm to the character and appearance of the conservation area; whether the replacement building would make a positive contribution to the character and appearance of the conservation area, and if not, would the public benefit outweigh any harm; whether the building is acceptable in terms of design and layout; whether the development would have an impact on highway safety; whether the development would result in harm to biodiversity; and whether there would be an acceptable impact on neighbouring amenity.

1.3.4 The benefit of the proposal is that it would provide a health and community use to address local shortfall. The negatives are the loss of a heritage asset and the impact of that loss on the character and appearance of the St Johns Grove Conservation Area and the wider surrounds.

Financial implications

There are no additional financial implications for the Council with the costs/income being within the normal course of business and contained within Planning Committee 5 October 2022

existing budgets. Any separate financial issues associated with Section 106s (S106), or similar legal documents, are covered elsewhere in the report.

The comments from the Head of Legal Services were as follows: The Legal implications are set out in the report where relevant, a Legal advisor will also be present at the meeting should legal considerations arise.

1.6Data Protection Compliance Implications

Due consideration has been given to keeping the planning process as transparent as possible, whilst ensuring that data protection legislation is complied with.

Background papers

• Preliminary Environmental Risk Assessment • Design and Access Statement • Drainage Strategy • Transport Statement • Arboricultural Report • Preliminary Ecological Appraisal Report. Planning Committee 5 October 2022

APPENDIX

2. Details of the application

2.1Oban House would be demolished. The proposed development would consist of a substantial three storey detached building (third floor accommodation being to the roof space) which would be sited to the south west of the plot, built close to the front boundary. Car parking would be provided toward the rear of the site, to the north west boundary, accessed from Chilwell Road and utilising the existing access. A bin store and a substation would be positioned within the parking area, to the south east boundary where it adjoins the rear of 8a and 8b Chilwell Road (offices). A cycle store and parking area would be to the front of the proposed building.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
22/00166/FULReport 1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 17 attended
DK
Councillor David K WattsChair, present
MH
Councillor Margaret HandleyVice-Chair, apologies
DB
Councillor David BagshawCommittee Member, apologies, sent representative
LA
Councillor Lydia A Ball BEMCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, present
RI
Councillor Richard I JacksonCommittee Member, apologies, sent representative
GM
Councillor Greg MarshallCommittee Member, present
PJ
Councillor Philip J OwenCommittee Member, present
SP
Councillor Sue PatersonCommittee Member, present
DP
Councillor Don PringleCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, apologies, sent representative

All 17 on the meeting page

On this subject at Broxtowe

Search all
  1. 22/00166/FULThis decision
  2. 26/00581/fulRefused
  3. 26/00495/fulApproved
  4. 26/00516/fulAgreed
  5. 26/00564/fulAgreed
  6. 26/00404/fulAgreed

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open