22/00534/FUL

Approved Planning 1 paper

Planning Committee approved this item on Wednesday 2 November 2022. Below is the council's own wording, with the papers it was decided on.

Item38.4

Resolved

RESOLVED that planning permission be granted subject to the following conditions: 1. The development hereby permitted shall be commenced within six months of the date of this permission with works completed within ten months of the date of the permission. Reason: To comply with S91 of the Town and Country Planning Act 1990 as amended by S51 of the Planning and Compulsory Purchase Act 2004. 2. The existing dormer shall be removed within ten months of the date of the decision, unless otherwise modified in accordance with the plans approved under this permission. Reason: To ensure a satisfactory standard of external appearance and in accordance with the aims of Policy 17 of the Broxtowe Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014). 3. The development hereby permitted shall be carried out in accordance with drawings numbered D202-06/04/2020 Rev C, D203-06/04/2020 Rev C, D201, -06/04/2020 Rev C, D103-06/04/2020 Rev C, D102-06/04/2020 Rev C and D403-06/04/2020 Rev C received by the Local Planning Authority on 11 July 2022. Reason: For the avoidance of doubt. 4. The dormer shall be constructed using materials of a type, texture and colour so as to match those of the existing building. Reason: To ensure a satisfactory standard of external appearance and in accordance with the aims of Policy 17 of the Broxtowe Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014). 5. The windows on the east (side) elevation annotated as being obscurely glazed on drawing no. D202 - 06/04/2020 rev C shall be obscurely glazed to Pilkington Level 4 or 5 (or such equivalent glazing which shall first have been agreed in writing by the Local Planning Authority) and non-opening. Reason: In the interests of privacy and amenity for nearby residents and in accordance with the aims of Policy 17 of the Broxtowe Part 2 Local Plan (2019) and Policy 10 of the Aligned Core Strategy (2014). NOTES TO APPLICANT 1. The Council has acted positively and proactively in the determination of this application by working to determine it in line with adopted policies. 2. The proposed development lies within a coal mining area which may contain unrecorded coal mining related hazards. If any coal mining feature is encountered during development, this should be reported immediately to the Coal Authority on 0345 762 6848. Further information is also available on the Coal Authority website at: www.gov.uk/government/organisations/the-coal-authority
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

The application is brought to the Committee at request of Councillor S Dannheimer.

2 Recommendation The Committee is asked to resolve that planning permission is approved subject to the reasons outlined in the appendix.

3 Detail

3.1The application seeks to amend an existing flat roof dormer to a detached bungalow. The dormer is sited on the north eastern elevation and seeks to amend the dormer by reducing the length to 8.7m, 1.7m in height, set back from the principle elevation by 1.8m and 1.5m to the rear elevation and be almost on the ridge but 0.9m from the eaves. The windows will be increased in size to two large windows serving two bedrooms and one small window serving a bathroom. There are other alterations to facilitate three bedrooms (one with a wet room on ground floor), bathroom, lounge, open plan kitchen/dining/family room.

3.2There has been several planning applications for the retention of the dormer window. 20/00606/FUL was refused to retain the dormer and loft conversion. 21/00105/FUL approved with a time constraint for works to be completed within one year of decision notice. The last application was for the same size dormer window but with three smaller high level windows.

3.3The main issues relate whether the scale, siting and design of the dormer is acceptable and whether the development has an unacceptable impact on the visual amenity of the area and neighbour amenity.

3.4The benefits of the scheme are that the loft conversion and dormer provide enhance living accommodation for the occupiers. The negatives of the dormer are of a size and prominence that harms the character and appearance of the building and the wider area. This application seeks to remediate this by reducing the bulk and mass of the dormer.

3.5The Committee is asked to resolve that planning permission be granted for the reason set out in the appendix. Planning Committee 2 November 2022

APPENDIX

Financial implications

4.1There are no additional financial implications for the Council with the costs/income being within the normal course of business and contained within existing budgets. Any separate financial issues associated with S106s (or similar legal documents) are covered elsewhere in the report.

5.1The comments from the Head of Legal Services were as follows: The Legal implications are set out in the report where relevant, a Legal advisor will also be present at the meeting should legal considerations arise.

6 Data Protection Compliance Implications

6.1Due consideration has been given to keeping the planning process as transparent as possible, whilst ensuring that data protection legislation is complied with.

Background papers

7.1None submitted 8 Details of the Application

8.1The application seeks to retain the existing loft conversion and dormer, with some amendments. The dormer is sited on the north eastern elevation and seeks to amend the dormer by reducing the length to 8.7m, 1.7m in height, set back from the principle elevation by 1.8m and 1.5m to the rear elevation and be almost on the ridge but 0.9m from the eaves. The windows will be amended to be two large windows serving two bedrooms and one small window serving a bathroom. There are other alterations to facilitate three bedrooms (one with a wet room on ground floor), bathroom, lounge, open plan kitchen/dining/family room.

8.2The application form states that the dormer window will be amended using a rubber flat roof material to match the dormer cheeks and re use the existing dormer materials, that are dark grey to match the existing roof.

9 Site and Surroundings

9.1The application site lies within the built framework of Beeston and is a detached bungalow with detached garage. The site is located within Flood Zones 2 and 3. Planning Committee 2 November 2022

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
22/00534/FULReport 548 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 18 attended
DK
Councillor David K WattsChair, present
MH
Councillor Margaret HandleyVice-Chair, present
DB
Councillor David BagshawCommittee Member, apologies, sent representative
LA
Councillor Lydia A Ball BEMCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, present
RI
Councillor Richard I JacksonCommittee Member, apologies, sent representative
GM
Councillor Greg MarshallCommittee Member, present
PJ
Councillor Philip J OwenCommittee Member, apologies, sent representative
SP
Councillor Sue PatersonCommittee Member, apologies, sent representative
DP
Councillor Don PringleCommittee Member, apologies, sent representative
HE
Councillor Helen E SkinnerCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, present

All 18 on the meeting page

On this subject at Broxtowe

Search all
  1. 22/00534/FULThis decision
  2. 26/00581/fulRefused
  3. 26/00495/fulApproved
  4. 26/00516/fulAgreed
  5. 26/00564/fulAgreed
  6. 26/00404/fulAgreed

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open