Planning Committee, Wednesday 7 June 2023 at 6.00pm

APPLICATION NUMBER 23/00051/REG3

Agreed Planning 1 paper

Planning Committee agreed this item on Wednesday 7 June 2023. Below is the council's own wording, with the papers it was decided on.

Item4.6

Resolved

RESOLVED that planning permission be granted subject to the following conditions: 1. The development hereby permitted shall be commenced before the expiration of three years beginning with the date of this permission. Reason: To comply with S91 of the Town and Country Planning Act 1990 as amended by S51 of the Planning and Compulsory Purchase Act 2004. 2. The development hereby permitted shall be carried out in accordance with the following plans: · Site Location Plan · Utility Survey 45652_T_UG Rev. 0 · Topographical Survey 45652_T Rev. 0 · Existing Site Plan 0101 Rev. P02 · Existing Building 0016 Rev. P01 (All received by the Local Planning Authority 19/01/23) · Proposed Floor Plans 0010 Rev. P06 · Proposed Roof Level Plan 0012 Rev. P04 · Proposed Elevations 0015 Rev. P05 (All received by the Local Planning Authority 04/05/23). · Proposed Site Plan 0102 Rev. P06 (Received by the Local Planning Authority 25/05/23). Reason: For the avoidance of doubt. 3. No development above slab level shall commence until samples/details of the proposed external facing materials have been submitted to and agreed in writing by the Local Planning Authority and the development shall be constructed only in accordance with those details. Reason: To ensure the satisfactory appearance of the development in accordance with Policy 10 – Design and Enhancing Local Identity of the Aligned Core Strategy Part 1 Local Plan 2014 and Policy 17 - Place-making, Design and Amenity of the Broxtowe Part 2 Local Plan 2019. 4. a) No part of the development hereby approved shall be commenced until an investigative survey of the site has been carried out and a report submitted to and approved in writing by the Local Planning Authority. The survey must have regard for any potential ground and water contamination, the potential for gas emissions and any associated risk to the public, buildings and/or the environment. The report shall include details of any necessary remedial measures to be taken to address any contamination or other identified problems. b) No building to be erected pursuant to this permission shall ... view the full minutes text for item 4.6
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

1.1The application seeks full planning permission for the demolition of the existing changing pavilion and the construction of a new community leisure pavilion including associated external works including the installation of a multi-use games area (MUGA) and replacement of a skate park with a community garden. The application includes the extension of the existing car parking facilities replacing the existing basketball court within the north-western corner of the site. The existing play area and bowling green located within the south- western corners of the site will be retained.

Recommendation

The Committee is asked to resolve that planning permission be granted subject to conditions outlined in the appendix.

3. Detail

3.1The application seeks planning permission for the demolition of an existing changing pavilion and the construction of a new community leisure pavilion together with associated external works including the installation of a MUGA and the replacement of a skate park with a community garden. The proposal has been amended in response to concerns raised from local residents in relation to the siting and design of the proposal. The layout of the scheme has been changed with the inclusion of the replacement of the skate park with a community garden. The application includes the extension of the existing car parking facilities replacing the existing basketball court within the north-western corner of the site. The existing play area and bowling green located within the south-western corners of the site will be retained.

3.2The project forms part of the Stapleford Town Centre Investment Plan and follows extensive community engagement. The Stapleford Town Deal was agreed in June 2021, on the signing of Heads of Terms, with 6 core projects identified from its TIP (Town Improvement Plan). As part of the Project Confirmation Process, the Stapleford Town Deal Executive Board confirmed its intention to progress with the six core projects in October 2021. Planning Committee 7 June 2023

3.2The site includes Hickings Lane recreation Ground in Stapleford which is afforded protection under Policy 16: Green Infrastructure, Parks and Open Space of the Aligned Core Strategy (2014) and Policy 28: Green Infrastructure Assets of the Part 2 Local Plan (2019).

3.3The main issues relate to the impact of the proposal on Hickings Lane playing pitches, the impact on the character and appearance of the area, the impact on amenity of neighbouring properties and highway safety.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APPLICATION NUMBER 23/00051/REG3Report 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 16 attended
DB
Councillor David BagshawChair, present
RS
Councillor Richard S FalveyVice-Chair, present
PJ
Councillor Peter J BalesCommittee Member, present
LA
Councillor Lydia A Ball BEMCommittee Member, apologies, sent representative
RE
Councillor Ross Edward BofingerCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, present
GS
Councillor Graham S HillsCommittee Member, present
GM
Councillor Greg MarshallCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
PA
Councillor Pauline A SmithCommittee Member, present
HG
Councillor Halimah G Khaled MBECommittee Member, apologies, sent representative

All 16 on the meeting page

On this subject at Broxtowe

Search all
  1. APPLICATION NUMBER 23/00051/REG3This decision
  2. Application Number 24/00863/VOCApproved
  3. Application Number 24/00864/VOCApproved
  4. Application Number 24/00687/REG3Approved
  5. Application Number 24/00700/FULApproved
  6. Application Number 23/00447/FULRefused

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies