CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Broxtowe Borough Council
Planning Committee, Wednesday 6 September 2023 at 6.00pm

23/00126/FUL

Decided Planning 1 paper

Planning Committee decided this item on Wednesday 6 September 2023. Below is the council's own wording, with the papers it was decided on.

Item21.5

Resolved

RESOLVED that planning permission be granted subject to the following conditions. 1. The development hereby permitted shall be carried out in accordance with Site Location Plan 1: 1250, LP01A received by the Local Planning Authority 11 August 2023, Metal Gate Elevations, LP01, Gate Location, BP01, Section of track, FT01 received by the Local Planning Authority on 27 March 2023 and Block Plan, LP01A received by the Local Planning Authority on 14 August 2023. Reason: For the avoidance of doubt. 2. Within 3 months from the date of this decision, the access will be required to be surfaced in a hard-bound material (not loose gravel) for a minimum of 8.0 metres behind the Highway boundary. The surfaced access shall then be maintained in such hard-bound material for the life of the development. Reason: To reduce the possibility of deleterious material being deposited on the publichighway (loose stones etc.), in accordance with policy 10 of Aligned Core Strategy (2014) and Policy 17 of the Part 2 Local Plan (2019). NOTES TO APPLICANT 1. The Council has acted positively and proactively in the determination of this application by working to determine it within the determination timescale. 2. The proposed development lies within an area that has been defined by the Coal Authority as containing coal mining features at surface or shallow depth. These features may include: mine entries (shafts and adits ); shallow coal workings; geological features (fissures and break lines); mine gas and former surface mining sites. Although such features are seldom readily visible, they can often be present and problems can occur, particularly as a result of new development taking place. Any form of development over or within the influencing distance of a mine entry can be dangerous and raises significant land stability and public safety risks. As a general precautionary principle, the Coal Authority considers that the building over or within the influencing distance of a mine entry should be avoided. In exceptional circumstance where this is unavoidable, expert advice must be sought to ensure that a suitable engineering design which takes into account all the relevant safety and environmental risk factors, including mine gas and mine-water. Your attention is drawn to the Coal Authority Policy in relation to new development and mine entries available at: ww.gov.uk/government/publications/building-on-or-within-the-influencing-distance-of-mine-entries Any intrusive activities which ... view the full minutes text for item 21.5
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of the report

1.1The application seeks planning permission to retain the provision of hardstanding to an agricultural track along with the provision of an access off New Road and gate.

Recommendation

The Committee is asked to resolve that planning permission be granted subject to conditions outlined in the appendix.

3. Detail

3.1The application site is within the Nottinghamshire Green Belt. The proposal is considered to be an exception to inappropriate development in accordance with paragraph 150(b) of the National Planning Policy Framework 2021 (NPPF), which allows engineering operations; so long as it they do not result in additional harm of the openness of the Green Belt.

3.2Whilst the access track and the hardstanding covers a large area, leading from an access off New Road to the bottom of the field boundaries and to the rear in both directions along a dismantled railway line, the visual impact is minimal.

3.3Overall it is considered that the proposal is in accordance with the policies set out in the Council’s Local Plan 2019 and the NPPF 2021. It is therefore considered that the proposal is acceptable and that planning permission should be granted in accordance with the recommendations set out in the appendix.

Financial implications

4.1The comments from the Head of Finance Services were as follows: There are no additional financial implications for the Council with the costs/income being within the normal course of business and contained within existing budgets. Any separate financial issues associated with Section 106s (or similar legal documents) are covered elsewhere in the report. Planning Committee 6 September 2023

5.1The comments from the Head of Legal Services were as follows: The Legal implications are set out in the report where relevant, a Legal advisor will also be present at the meeting should legal considerations arise.

6 Data Protection Compliance Implications

6.1Due consideration has been given to keeping the planning process as transparent as possible, whilst ensuring that data protection legislation is complied with.

Background papers

Nil. Planning Committee 6 September 2023

APPENDIX

1 Details of the Application

1.1The application seeks planning permission to retain the provision of hardstanding to an agricultural track along with the provision of an access off New Road and gate.

2 Site and surroundings

2.1The agricultural track is located to the north of New Road and its route passes the field boundaries and along a dismantled railway line. The land surrounding the track is used for agricultural purposes which allows machinery access to the surrounding fields.

3 Relevant Planning History

3.1No relevant Planning History

4 Relevant Policies and Guidance

4.1Greater Nottingham Aligned Core Strategies Part 1 Local Plan 2014:

4.1.1 The Council adopted the Core Strategy (CS) on 17 September 2014.

• Policy A: Presumption in Favour of Sustainable Development • Policy 2: The Spatial Strategy • Policy 10: Design and Enhancing Local Identity • Policy 11: Historic Environment

4.2Part 2 Local Plan 2019:

4.2.1 The Council adopted the Part 2 Local Plan on 16 October 2019.

• Policy 17: Place-making, Design and Amenity • Policy 8: Development in the Green Belt • Policy 23: Proposals affecting Designated and Non-Designated Heritage Assets

4.3National Planning Policy Framework (NPPF) 2019:

• Section 2 – Achieving Sustainable Development. • Section 4 – Decision-making. • Section 12 – Achieving well-designed places. • Section 13 – Protecting Green Belt land. • Section 16 – Conserving and Enhancing the historic environment. Planning Committee 6 September 2023

5 Consultations

5.1The Highway Authority – No objections subject to a condition relating to the access point of New Road consisting of a bound material for the first 8m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
23/00126/FULReport 1.9 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 17 attended
DB
Councillor David BagshawChair, present
RS
Councillor Richard S FalveyVice-Chair, apologies, sent representative
PJ
Councillor Peter J BalesCommittee Member, present
LA
Councillor Lydia A Ball BEMCommittee Member, present
RE
Councillor Ross Edward BofingerCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, present
GS
Councillor Graham S HillsCommittee Member, present
GM
Councillor Greg MarshallCommittee Member, present
DP
Councillor Don PringleCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
PA
Councillor Pauline A SmithCommittee Member, present

All 17 on the meeting page

On this subject at Broxtowe

Search all
  1. 23/00126/FULThis decision
  2. 26/00581/fulRefused
  3. 26/00495/fulApproved
  4. 26/00516/fulAgreed
  5. 26/00564/fulAgreed
  6. 26/00404/fulAgreed

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open