Capital Programme 2025/26 – Capital Budget Variations

Approved Executive 1 paper

AI summaryBroxtowe Cabinet approves 2025/26 capital budget variations covering Disabled Facilities Grants, housing works and Craft Workshops, with no net change to overall borrowing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDFG, HRA works and Craft Workshops revised
Money£391,150 additional DFG grantPlus virements within existing budgets
What happens nextFurther changes reported as neededFuture variations return to Cabinet for approval
Who it affectsSocial housing tenants and disabled residentsPlus Craft Workshops tenants in Eastwood

What was decided

Cabinet approved the 2025/26 capital budget variations set out in the appendix, covering Disabled Facilities Grants, housing capital works and Craft Workshops. Report P1, P5

The total DFG budget rises to a rounded £1,857,800, split as £1,782,800 for DFG and £75,000 for Warm Homes on Prescription, fully funded by capital grants through the Better Care Fund. Report P30, P31, P32

Several HRA capital budgets are vired between lines, with a £200,000 boost to boiler replacement, £250,000 moved to aids and adaptations, and £100,000 redirected to structural repairs. Report P37, P38, P39, P40

Why

The variations are said to more accurately reflect delivery expectations in the current financial year. Report P4

Boiler breakdowns rose above forecast, with 149 by August 2025 and a further 250 expected before March 2026, prompting the transfer into boiler replacement. Report P38

A 75 metre, 2 metre high retaining wall at Scargill Walk requires a full rebuild at £170,000, driving the move of funds into structural remedial repairs. Report P39

What happens next

The Assistant Director of Finance Services confirmed the financial implications are set out in the report and appendix. Report P12

Any further changes to the Capital Programme will be reported to Cabinet as necessary for approval. Report P6

The money

  • £34.966m Original 2025/26 Capital Programme value Report P3
  • £32.484m Original 2025/26 Capital Programme excluding reserve items Report P3
  • £800,000 Original DFG budget for 2025/26 Report P29, P31
  • £590,150 DFG budget carried forward from 2024/25 Report P29, P31
  • £76,500 WHOP budget carried forward from 2024/25 Report P29, P32
  • £1,220,946 Expected DFG allocation from BCF for 2025/26 Report P30
  • £114,713 Amount retained as council contribution to handyperson scheme Report P30
  • £751,576 Finalised DFG budget brought forward from 2024/25 Report P30
  • £1,857,800 Total rounded revised DFG and WHOP budget for 2025/26 Report P30
  • £1,782,800 Revised DFG budget for 2025/26 Report P30, P31
  • £75,000 Revised WHOP budget for 2025/26 Report P30, P32
  • £391,150 Additional DFG amount recognised in Capital Programme, funded by BCF grant Report P30
  • £11.8m Approved HRA capital works for 2025/26 Report P34
  • £250,000 Transfer from Decent Neighbourhoods to Aids and Adaptations Report P37
  • £200,000 Transfer from Modernisations to Boiler Replacement Report P38
  • £100,000 Transfer from Pre-Paint Repairs to Structural Remedial Repairs Report P39
  • £170,000 Cost of full rebuild of retaining wall at Scargill Walk Report P39
  • £40,000 Original Craft Workshops budget Report P43, P46
  • £56,000 Revised Craft Workshops budget Report P45, P46
  • £3,000 Virement from Queen Elizabeth Pavilion Cladding underspend Report P45, P46
  • £13,000 Virement from Beeston Square Phase 2 Fitting Out Works budget Report P45, P46

Options considered

  • Chosen: Approve the capital budget variations as set out in the appendix. Variations would more accurately reflect delivery expectations in the current financial year Report P1, P4
  • Chosen: Transfer £250,000 from Decent Neighbourhoods to Aids and Adaptations. To support backlog of occupational therapist referrals and increased demand Report P37
  • Chosen: Transfer £200,000 from Modernisations to Boiler Replacement. 149 boiler breakdowns by August 2025 and 250 more anticipated before March 2026 Report P38
  • Chosen: Transfer £100,000 from Pre-Paint Repairs to Structural Remedial Repairs. Including £170,000 retaining wall rebuild at Scargill Walk Report P39

Implications

  • Financial: Capital financing will not be adversely affected: variations are funded by capital grants or by adjusting previously agreed prudential borrowing to match actual spend. Report P4, P40
  • Legal: The Head of Legal Services confirmed there are no direct legal implications arising from the report. Report P14
  • Equalities: No equality impact assessment is required because there is no change to policy. Report P24
  • Climate: Climate change is a key consideration in the budget setting process; the Craft Works roof insulation is expected to improve energy efficiency at the Eastwood units. Report P20, P44
  • Risk: Structural Remedial Repairs budget is largely committed by the £170,000 Scargill Walk retaining wall rebuild, which could limit new works. Report P39
  • Staffing: No comments were received from the Human Resources Manager. Report P16

Who and where

  • Disabled residents in private sector dwellings receiving DFG and WHOP grants Report P29, P30
  • Tenants of the council's 4,300 HRA owned dwellings awaiting heating, adaptations and structural works Report P35, P38, P39
  • Tenants and users of the Craft Workshops in Eastwood Report P43, P44
  • Occupational therapy referral clients awaiting aids and adaptations work Report P37

Timeline

  • 4 February 2025: Cabinet recommended the Capital Programme Report P3
  • 5 March 2025: Council approved the Capital Programme for 2025/26 to 2027/28 Report P3
  • By August 2025: 149 boiler breakdowns already experienced, triggering the boiler replacement budget uplift Report P38
  • 4 November 2025: Cabinet approved the capital budget variations Report P10
  • Before March 2026: A further 250 boiler breakdowns are anticipated, prompting the £200,000 transfer Report P38

Plain English for the jargon

  • DFG: Disabled Facilities Grants, paid to improve facilities for disabled people in private sector dwellings.
  • WHOP: Warm Homes on Prescription scheme, part of the DFG budget.
  • BCF: Better Care Fund, through which Nottinghamshire County Council finances DFG.
  • HRA: Housing Revenue Account, the council's landlord account for its own housing stock.
  • Virement: Transfer of budget from one spending line to another within the same overall budget.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item65.3

Resolved

RESOLVED that the capital budget variations for 2025/26, as set out in the appendix to the report, be approved. Reason The variations would more accurately reflect delivery expectations in the current financial year.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to RESOLVE that the capital budget variations for 2025/26 as set out be approved.

3. Detail

The Capital Programme for 2025/26 to 2027/28 was approved by Council on 5 March 2025 following recommended by Cabinet on 4 February 2025. The total value of the original Capital Programme for 2025/26 was £34.966m (£32.484m excluding ‘reserve items’).

Several capital schemes require amendments to the budgets to more accurately reflect expectations in the current financial year. In all cases the capital financing will not be adversely affected with schemes either being funded by capital grants or through previously agreed prudential borrowing which will be adjusted accordingly to match spends.

These schemes include Disabled Facilities Grants and Capital Works for both the Housing and General Properties. These are set out in the Appendix which includes the proposed amendments to the current Capital Programme together with likely financing that will be confirmed at the end of the financial year.

Any further changes to the Capital Programme will be reported to Cabinet as necessary for approval.

4. Key Decision

This report is not considered a key decision as defined under Regulation 8 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

5. Updates from Scrutiny

Not applicable. Cabinet 4 November 2025

Financial implications

The comments from the Assistant Director Finance Services were as follows:

The financial implications are included in the report narrative and appendices.

The comments from the Head of Legal Services were as follows:

There are no direct legal implications that arise from this report.

8. Human Resources Implications

There were no comments from the Human Resources Manager.

9. Union Comments

Not applicable.

10. Climate Change Implications

The Council’s response to Climate Change is a key consideration as part of the budget setting process.

11. Data Protection Compliance Implications

This report does not contain any OFFICIAL(SENSITIVE) information and there are no Data Protection issues in relation to this report.

12. Equality Impact Assessment

As there is no change to policy an equality impact assessment is not required.

Background papers

Nil. Cabinet 4 November 2025

Appendix

Capital Programme 2025/26 – Proposed Capital Budget Changes

1. Disabled Facilities Grants and Warm Homes on Prescription

The Capital Programme for 2025/26 includes a budget of £800,000 for Disabled Facilities Grants (DFG), including the Warm Homes on Prescription scheme (WHOP). This scheme provides grants to improve facilities for disabled people living in private sector dwellings. The budget is financed by Nottinghamshire County Council through the Better Care Fund (BCF). A further £590,150 (DFG) and £76,500 (WHOP) was carried forward from unspent budgets in 2024/25.

The Council has since received confirmation of its DFG budget for 2025/26. An allocation from the BCF of £1,220,946 is now expected (less £114,713 retained as the Council’s contribution to the handyperson scheme managed by the County Council on behalf of all Nottinghamshire districts). The finalised budget brought forward from 2024/25 is £751,576. This gives a total rounded budget of £1,857,800, with the proposed split of £1,782,800 for DFG and £75,000 for WHOP. The additional £391,150 will be recognised in the Capital Programme and be fully funded by capital grants (BCF).

DFG Schemes Approved Budget Total Revised Budget Brought Budget Budget 2025/26 Forward 2025/26 2025/26 £ £ £ £ Disabled Facilities Grants 800,000 590,150 1,390,150 1,782,800

Warm Homes on Prescription - 76,500 76,500 75,000

2. Housing Capital Works

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2025/26: Capital Budget VariationsReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
GB
Councillor Gabrielle BunnCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
TA
Councillor Teresa A CullenCommittee Member, present
RD
Councillor Richard D MacRaeCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, apologies

On this subject at Broxtowe

Search all
  1. Capital Programme 2025/26 – Capital Budget VariationsThis decision
  2. Capital Programme 2025/26 – Capital Budget VariationsApproved
  3. Vehicle Fleet Replacement Programme Reallocation of the Capital BudgetsApproved
  4. Capital Programme 2025/26 – Capital Budget VariationsApproved
  5. Capital Programme 2024/25 – Capital Budget VariationsApproved
  6. Capital Programme – Budget Variations 2024/25Approved

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies